ESTIMATE OF COSTS OF INSTALLATION

OF SOLAR PANELS

As of August, 2002

 

Estimate between 15% to 20% of cost of total materials and equipment.The bigger the system the greater the cost of installation.

Actual installation happens as follows:

  1. Initial analysis estimated 1 hour (plus one way travel if more than 25 miles from Snowflake) 1 hour
    • Concrete & Pole work (cost of concrete) $130)
    • 12’ galvanized poles 6" diamater ($13.87/ft) $166 estimated 10 hours
  2. Install components
    • Tracker panels (outside team)
    • Electrical Components (inside team) 2 days @ 10 hrs 20 hours
  3. Follow Up
    • Tie up loose ends
    • Walk through (about one or two weeks after initial install) 4 hours 

Cost per hour $40.00 : Total number of estimated hours: 40 = Guideline approximation $1,600.00

Install materials cost:

Concrete $130

Poles $166 = Total $296

(For a standard 8 Panel installation.)