Federal energy regulators have taken the first steps
toward implementing the 2005 Energy Policy Act. The
Federal Energy Regulatory Commission has proposed
transmission pricing changes in an effort to promote
needed investment.
|
Ken Silverstein
EnergyBiz Insider
Editor-in-Chief |
Investors have long been weary of putting capital
towards transmission infrastructure, largely because the
returns don't justify the risks. Simply, it takes too long
to go through the permitting process and the allowable
rates of return don't reflect that. By establishing
incentive-based rates and using its backstop permitting
authority, the FERC says it will enhance reliability and
cut the cost of delivering power because there would be
less congestion.
Transmission investment has declined in real terms --
adjusted for inflation -- from 1975 to 1998. While there
have been increases since 1998, FERC says that the level
is still less than what was invested in 1975. Over the
same time period, however, the demand for electricity has
doubled. That's resulted in a significant decrease in
transmission capacity, requiring new lines get built.
"Under-investment is a national problem," says Joe
Kelliher, chairman of the FERC. "The commission proposes a
national solution that encourages investment in all
regions of the country."
The incentives apply to traditional utilities and to
transcos, or those that operate transmission lines but do
not own any generation. Specifically, the commission would
authorize a higher rate of return on these regulated
assets as well as recovery of accumulated deferred income
taxes. It would also allow companies to recover
transmission-related construction costs and provide higher
rates of return for utilities that join regional
transmission organizations that are independent and
schedule all power deliveries for participating utilities.
Winning Permits
While everyone recognizes the need, new transmission is
not getting built at the pace that is necessary. The
difficulties in winning permits coupled with lack of
capital flowing to such projects mean that less expensive
generation may sit idle because of inadequate or congested
transmission lines.
ISO New England, for example, says that about $900
million is needed for upgrades to maintain reliability and
efficiency. Southwest Connecticut in particular has one of
the most severely constrained transmission systems in New
England. At the same time, Arizona-based UniSource Energy
Services, for example, has been trying to build a
high-voltage line in the populated Tucson area but has
been blocked by regulators and citizen activists.
More than 30 transmission projects have been planned or
proposed by electric companies in the Northeast.
Similarly, the Midwest ISO currently has several
transmission projects in the works. But, according to
FERC, they won't be enough to relieve the expected
congestion.
"With transmission making up only about five percent of
customer bills, even some traditional players don't think
the potential rewards outweigh the risks involved in
siting, maintaining, and operating the transmission
system," says Robert Bellemare, CEO of UtiliPoint
International. He points to the American Electric Power's
765 kilovolt line in West Virginia and Virginia, which
might end up being a 15-year process.
Despite the potential obstacles, four governors of
Western states have given their support to the building of
1,300 miles of power lines at a cost of $2 billion. If the
projects are constructed and begin delivering electricity
by 2011, lines would stretch from Wyoming and into Utah,
Nevada and Southern California. The governors say that the
new lines are essential: They note that the demand for
power has risen by 60 percent in the last 20 years but
that the region's transmission system has only grown by 20
percent.
Some states, however, may struggle to provide enough
power in 2006. In California, if reserve levels ever fall
below the 7 percent, then the energy commission there says
that it might ask for voluntary reductions or would
suggest rolling blackouts.
Open and Inclusive
Needless-to-say, the 2005 energy law aims to push
things along. The Department of Energy now has the
authority to identify "national interest electric
corridors" while the FERC can site the projects that fail
to win state approval, essentially giving the permit
holder the right of eminent domain. Meantime, the law not
only would include the North American Electric Reliability
Council in the development of standards but allow it to
enforce them as well -- all under the authority of a
so-called Electric Reliability Organization. Such
standards have been optional to this point.
The idea is that the permitting process would take no
more than one year. And, if the process gets stymied in
the court system, the interested parties could petition
the president of the United States for approval. At least
that's the theory. But, as FERC well knows, it has similar
rights when it comes to permitting natural gas pipelines.
And, oftentimes, the process is still mired in court
fights and regulatory battles that are time consuming. In
any event, FERC emphasizes that the permitting process
will always remain open and inclusive.
The ultimate goal is to build a transmission
infrastructure in line with the digital economy. Any
intrusion, for example, could be isolated while the rest
of the grid kept functioning. To get there, though, it
will be costly.
"An idealistic end point would be $100 billion
investment over 10 years," says Wade Malcolm, with Palo
Alto-based EPRI, a utility research group.
And that's where incentive-based rates come into play.
Through the FERC, Congress wants to implement the
incentives to expand the transmission infrastructure and
thereby increase reliability. Policy makers also want to
provide a predictable regulatory environment and ensure
rates remain stable. The proposal is new and will
certainly invite some criticism. But, it's a productive
start when it comes to addressing the country's energy
concerns.
For far more extensive news on the energy/power
visit: http://www.energycentral.com
.
Copyright © 1996-2005 by CyberTech,
Inc. All rights reserved.
|