The Alaskan natural gas pipeline might finally get rolling. One of
the principal conglomerates has agreed to the proposed terms outlining
a risk-sharing arrangement, which has given the $24 billion project
better odds than at any time in 25 years.
|
Ken
Silverstein
EnergyBiz Insider
Editor-in-Chief |
The construction of this pipeline is considered vital in the effort
to bring Alaska's vast natural gas reserves to the rest of the United
States. That gas would help alleviate price pressures that have been
driving up consumers' heating bills. And that's why Alaska Governor
Frank Murkowski and ConocoPhillips have agreed to a potential deal
whereby the state would finance the project to the tune of $4 billion
while energy producers would ante up $20 billion.
"The time is right to move forward," says Jim Bowles, president of
ConocoPhillips Alaska in a news conference. "We are now one step
closer to making the Alaska natural gas pipeline a reality."
BP and ExxonMobil are the two other central figures in the
discussion. The three oil companies applied to the state last year in
an effort to negotiate how the pipeline would be financed. Congress
had previously authorized loan guarantees that would require the
government to pick up 80 percent of the first $18 billion if the
project should not be completed.
Clearly, conditions are better than ever before. For starters, the
price of natural gas is now at record highs -- $14 per million BTUs
for January deliveries. That's well beyond the $3.25 floor that the
principals said they would need to offset the risks associated with
the 10-year project. For its part, Alaska gets some valuable financial
guarantees as well as millions of dollars in new tax revenues
associated with the effort and hundreds of new jobs for state
residents.
The final deal has not been made public but must still go through a
comment period before it would be approved by the state legislature.
Ultimately, the project needs permission from federal regulators who
will listen to all sides, some of which fear the potential route any
line might take for environmental and economic reasons.
Congress has said it wants to promote the development of natural
gas resources in Alaska. As such, the Federal Energy Regulatory
Commission has been given 20 months to review the deal once it gets
the paperwork. "We are under mandate to streamline the processes,"
says Robert Cupina, a deputy director at FERC.
The pipeline was originally authorized by the FERC under Alaska
Natural Gas Transportation Act that went into effect July 1, 1979.
Construction began soon after but stopped in the early 1980s, largely
because of the availability of low-cost Canadian gas. Developers have
spent more than $125 million studying the project.
Significant Milestone
The pipeline would be a 3,400-mile project that would send 4-5
billion cubic feet per day from Alaska's North Slope to the Lower 48.
The fields where the gas is found hold 35 trillion cubic feet of known
reserves and would undoubtedly help serve America's energy needs. Some
experts say the region holds even more natural gas resources.
The natural gas and the oil have been separated during processing
and the gas has subsequently been re-injected into the ground in the
Alaskan fields in an effort to keep the crude flowing. Now, it's just
waiting to be tapped and used by electric generators but the
transportation costs to get it to the Lower 48 are high.
"There's no question, this is a significant milestone," says Gov.
Murkowski, at the news conference announcing the deal with
ConocoPhillips. BP and ExxonMobil are withholding formal comments but
have said that some "outstanding issues" remain but that they don't
feel those matters will impede progress.
The loan guarantee passed earlier is considered by many a critical
financing provision because it assures investors they will not lose
money should gas prices drop so dramatically as to prevent completion
of any line once construction starts. The guarantee could reduce the
interest rate needed to attract financing for the line. If so, that
would cut its cost, while also protecting investors who would be
financing the largest private construction project in the nation's
history.
Beyond the financial exposure, logistical, environmental and
political risks are present. Alaska wants the gas line to follow the
oil pipeline down to Fairbanks, and then go eastward to Canada. This
would assure that only Alaska gas gets transported through the line.
But the Canadians want the route to go due east from Prudhoe Bay to
the Mackenzie Delta, where huge natural gas deposits are thought to
exist. The Canadians fear that a pipeline from the north that does not
include their Mackenzie region would leave them with "stranded" gas.
The country's thirst for new energy sources is propelling forward
the idea of an Alaskan pipeline. But that thirst would remain
unquenched if it were not for record-high natural gas prices that are
giving producers added confidence. The economic factors in combination
with some past legislative action and potentially favorable regulatory
rulings might finally bring this project to fruition.
For far more extensive news on the energy/power
visit: http://www.energycentral.com
.
Copyright © 1996-2005 by CyberTech,
Inc. All rights reserved.
|