Aug. 9--A battle is brewing among environmental groups, the coal industry and
regulators over enforcement of a July mountaintop removal ruling by U.S.
District Judge Joseph R. Goodwin. Last week, citizen groups sought federal inspections of several sites where
they believe coal operators may be violating Goodwin's decision. The U.S. Army Corps of Engineers has asked the state Department of
Environmental Protection -- the only agency that has inspectors patrolling the
sites regularly -- for help. But so far, the Wise administration has declined to
get involved. The dispute could end up in Goodwin's courtroom if it is not resolved soon. "We've heard rumors that operators may be trying to circumvent the
court's order, but I would be surprised if either the Army Corps of Engineers or
coal operators are not complying with Judge Goodwin's order," said Joe
Lovett, a lawyer and executive director of the Appalachian Center for the
Economy and the Environment. In the case before Goodwin, Lovett's organization and Trial Lawyers for
Public Justice represented the Huntington-based Ohio Valley Environmental
Coalition, Coal River Mountain Watch and the Natural Resources Defense Council. On July 8, Goodwin ruled that the corps could no longer approve mining valley
fills through a streamlined permit process meant only for activities that cause
minor environmental damage. Rather than these "general" or "nationwide" permits,
Goodwin said, coal companies must go through more rigorous individual permit
reviews when they propose to bury streams with waste dirt and rock. The judge ordered the corps not to issue new Clean Water Act permits for
valley fills without individual reviews. As for 11 specific general corps permit authorizations challenged in the
suit, Goodwin ordered the agency to suspend those for valley fills "on
which construction has not commenced as of today, July 8, 2004." In mountaintop removal, coal operators blast off entire hilltops to uncover
valuable, low-sulfur coal seams. Leftover rock and dirt - - the stuff that used
to be the mountains -- is shoved into nearby valleys, burying streams. Last year, federal regulators issued a report that concluded that 1,200 miles
of Appalachian streams have been buried or otherwise "directly
impacted" by valley fills between 1992 and 2002. That 4 1/ 2-year study
found that past, present and future mining in the region could destroy 1.4
million acres of forest, or 11.5 percent of the study area. The Bush administration, which has made several moves to make it easier for
companies to obtain mountaintop removal permits, has not issued a final version
of the study. Questions surfaced about compliance with Goodwin's ruling on July 30, when
Massey Energy Co. President Don Blankenship was asked about the decision in a
quarterly conference call with industry stock analysts. Massey holds five of the 11 specific permits that were cited in the lawsuit.
Those permits are for Massey subsidiaries Alex Energy, Elk Run Coal and
Independence Coal. While he complained that the judge's decision "will further complicate
and slow the already complicated permit process," Blankenship also
indicated that Massey didn't expect to stop its operations. "While what constitutes the commencing of construction has not yet been
specifically defined, Massey has started some construction on all five permits
by the date of the ruling," Blankenship told the analysts. Asked by one analyst for further details, Blankenship said, "It varies a
little bit, but in all cases we are, at a minimum, building ponds and in some
cases, we are dumping material into the fills." Four days after Goodwin issued his ruling, corps District Engineer William E.
Bulen sent letters to Massey and other companies whose already-issued permits
were cited in the decision. In the letter, Bulen told companies that their permit authorizations were
"suspended for valley fills and surface impoundments on which construction
has not commenced as of" July 8. The other companies who received the letters were Kingston Resources, Horizon
Resources and Fola Coal Co. In all, the permits halted by Goodwin would have buried or otherwise impacted
26.5 miles of West Virginia streams, according to government records filed with
the court. Chuck Minsker, a corps spokesman in Huntington, said that his agency is
considering plans to inspect mining operations to confirm that they have
complied with Goodwin's order. The corps, though, does not regularly inspect strip mines. So, the agency has
sought help from DEP. Ken Politan, an assistant chief for permitting at the DEP Division of Mining
and Reclamation, said that the corps asked him for help from state inspectors
during a July 20 meeting. Politan said that he told corps officials that he wasn't in charge of
inspectors, and that they should talk to Joe Parker, DEP's mining chief, or to
Jeff McCormick, assistant chief for inspection and enforcement. Last week, Politan said that he also forwarded the corps' request to Parker
and McCormick in an e-mail message. Parker did not return phone calls Thursday and was not in his office Friday. Perry McDaniel, chief of the DEP Office of Legal Services, said that it
appears that environmentalists and the coal industry disagree about what
constitutes starting construction of a fill under Goodwin's ruling. In some cases, McDaniel said, coal companies believe that they are exempt
from the ruling if they started construction of sediment ponds downstream of the
areas that will eventually become valley fills. Environmentalists, McDaniel
said, apparently believe that starting the pond is not sufficient for a company
to get around the injunction. McDaniel said that he advised DEP officials that they should steer clear of
that dispute. "We prefer not to be caught in the middle," McDaniel said. "At
best, we would provide some basic information, and let Judge Goodwin and the
parties to that lawsuit sort it out." One problem for environmentalists is that they do not have complete
information about what was happening on the ground at each of the mine sites
cited in Goodwin's injunction. That's the sort of information, environmentalists
say, that DEP could easily provide. On Friday, McCormick said that he's not sure he wants his inspectors to even
do that. "We would have to discuss it internally and see if it was something we
wanted to do or not," McCormick said. McCormick added that the in-person request to Politan is not sufficient for
DEP to consider helping the corps. DEP wants something in writing, McCormick
said. "To my knowledge, the corps has not made a request," McCormick
said. "I have not been contacted. Unless we get something official, we
would not consider that sort of request." On Thursday, Vivian Stockman of the Ohio Valley Environmental Coalition asked
the federal Office of Surface Mining to arrange a citizen inspection -- allowed
under federal strip mining law -- of seven of the operations cited in Goodwin's
ruling. In a letter to Roger Calhoun, director of the OSM field office in Charleston,
Stockman said that she has "reason to believe" that Goodwin's ruling
is "not being followed by certain coal operators in West Virginia." "Because there is an immediate danger to the environment, I request an
immediate inspection," Stockman said. Also last week, environmentalists asked the U.S. Environmental Protection
Agency, which handles Clean Water Act enforcement, to look into the situation. Officials from OSM and EPA could not be reached late Friday. Earlier, Lovett on July 19 asked the judge to expand the ruling to cover six
other permits that may not have started filling streams before the July 8
decision. Goodwin has not yet ruled on that request. Two of those six permits are for Massey operations. In court papers filed last week, Massey lawyers said that an expansion of
Goodwin's ruling would cause those operations "a disruption of their
reasonably based investment expectations, a disruption to and possible loss of
their employees, and a potential inability to meet contractual
obligations." By contrast, Arch Coal Inc. President Steven Leer told industry analysts on
July 26 that the Goodwin decision would not cause major problems for three of
its permits specifically cited in the injunction. "Arch has been anticipating that this could be a likely outcome for a
number of years," Leer said in a conference call. Leer noted that Arch Coal is the only coal company that has gone through the
process of obtaining individual permit authorization from the corps. "We fell pretty comfortable with the individual permit process,"
Leer said. "It was a potential outcome that was likely," he said. "We had
planned for it. "I think it will make it more difficult for people to get permits,"
Leer added. "It will lengthen the time of the permit process, which is
already lengthy. But we've built that in and made it part of our modus
operandi."
Visit http://www.powermarketers.com/index.shtml for excellent coverage on your energy news front.