Jul. 13--Valley utilities struggled to meet consumers' energy demands Monday
as higher temperatures and humidity drove electricity use to the highest level
so far this year. No outages had been reported as of late afternoon Monday, but
utilities officials were still holding their breath. The outdoor temperature
reached 114 degrees at the APS operations center in Phoenix while the humidity
reached as high at 25 percent. Arizona Public Service and Salt River Project urged Scottsdale and other East
Valley customers to shift nonessential electricity consumption away from the
peak-use hours late in the afternoon. The Valley's tight electric situation is the result of a transformer fire at
a West Valley substation more than a week ago, which knocked 14 transformers out
of operation. Utility crews restored service to three of the damaged transformers at the
Westwing substation on Thursday, but more work will be needed to restore the
others. The transformers "step down" the voltage of electric current
brought in by major transmission lines, preparing it for distribution to
endusers. Without the Westwing transformers, utilities have had to route more
electricity through three other Valley substations. On Saturday, APS acquired a replacement transformer from the Bonneville Power
Administration in Washington state. The 400,000- pound transformer was loaded on
a special highway hauler at Covington, Wash., and made the 36-mile trip to the
port of Tacoma, Wash., at an average speed of about 2 miles per hour, said APS
spokesman Alan Bunnell. The $2million piece of equipment arrived at Tacoma on Sunday night, he said. The process of loading the transformer on the barge, along with the hauler,
began Monday night, and the barge is expected to leave port in about two days.
Because the wheeled hauler is being transported with the transformer, the barge
ramp will have to be welded shut to hold the massive cargo in position, Bunnell
said. The barge will carry the transformer to a port in California, which is not
being disclosed for security reasons. The weld will then be broken and the
transformer unloaded for transport via the hauler to the Westwing substation at
Loop 303 and Happy Valley Road. The average speed between California and Arizona is expected to be about 10
miles per hour, faster than the Washington leg of the 1,500-mile journey because
of better roads, Bunnell said. It is expected to arrive at Westwing during the week of July 25. Installation
will require another three weeks. Completion of the task may ease the
electricity crisis, but other Westwing transformer replacements are not expected
to be completed until next summer. In the meantime, the utilities said they will
ask customers to conserve electricity for the rest of this summer, particularly
during the peak-use hours of 3 to 6 p.m. daily. So far there have been no outages related to the Westwing fire, but minor
interruptions were reported during the weekend because of problems at smaller
substations around the Valley.
Visit http://www.powermarketers.com/index.shtml for excellent coverage on your energy news front.