Offshore windfarms have high risks, says analysis
FRANKFURT, Germany, 2004-07-07 (Refocus Weekly)
Offshore windfarms still have high risk from construction, technological and operational issues, according to an assessment by a company involved in credit analysis.
“The turbine technology for windfarms a long way from shore is not
sufficiently tested, and the distance from the coast and poor weather conditions
could prevent necessary repairs,” says Jan Willem Plantagie of Standard &
Poor's Ratings Services in the report, ‘Winds of Change Blow Through The U.K.
Wind Power Sector.’ Maintenance costs could increase if there were a failure
in the connection between the windfarm and the main grid, and construction and
repair costs are likely to be high.
“All these factors would have a direct negative impact on turbine
availability,” he adds.
Britain is particularly focussed on developing offshore wind projects, but such
projects carry “significantly higher risks than onshore ones.” In addition,
few offshore projects have been undertaken and, although Germany, the
Netherlands and Denmark want to develop them, the UK's proposals are “the most
ambitious.”
Considerable uncertainty surrounds wind power planning requirements,
infrastructure and grid access costs in Britain, and this uncertainty “may
threaten the sector's development in future years and constrain its contribution”
to government targets for renewable energies. “Conflicting messages sent by
different government departments further increase the uncertainty about future
support for the industry,” the report warns.
“The UK's abundance of windy weather could deliver significant clean renewable
power for the nation over the next decade,” which would put the country on
track to meet the target of 15% of electricity from renewables by 2015. The
industry expects Britain to have the fourth-largest wind capacity in the EU by
2010, but these goals seem “optimistic” given that total capacity at the end
of last year was only 649 MW, equivalent to 0.5% of the country’s power,
explains Plantagie.
“It is likely that an improved planning permission process would be required,
along with a long-term, benign regulatory framework to deliver the government's
expected targets,” he says.
Despite the positive signals such as extending the Renewables Obligation Scheme
to 2015, the installation of 100 MW of new wind capacity during 2003 and the
opportunity to install large windfarms beyond the 12-nautical-mile limit, the
domestic industry still has a high level of objections to windfarms from the
Ministry of Defence, as well as a generally protracted proposal evaluation
process for turbines. “Recent renewable energy studies have concluded that
other energy sources are cheaper than wind power, leading to renewed debate
about its viability.”
“In Standard & Poor's opinion, however, offshore wind power generation is
still developing, and construction, technological, and operational risks are
high,” the report concludes, and a list of factors would have a “direct
negative impact” on turbine availability. The long-term maintenance needs of
turbines in deep saltwater have not been gauged and the entry of “new and
inexperienced offshore developers” into the offshore sector “may further
increase risks.”