AWEA Files "Grid Code" Interconnection Standards for Wind Systems

On May 20, 2004, the American Wind Energy Association (AWEA) filed recommendations with the Federal Energy Regulatory Commission (FERC) regarding the treatment of wind generating plants under FERC's recent rulemaking (Order 2003 A) establishing national standards for interconnection of new generators to the interstate electricity grid. AWEA's recommendations are based on the work performed by the “Grid Code” industry group organized by AWEA policy director Jim Caldwell.

AWEA's proposed performance specifications include the following:

AWEA also proposes several process recommendations in its filing. Specifically, the organization recommended that transmission providers and manufacturers of wind generators participate in a formal process for developing, updating and improving engineering models and turbine specifications used for modeling wind plant interconnection. Furthermore, AWEA proposed that generators should be permitted to study interconnection feasibility in a manner analogous to the New York Independent System Operator's (NYISO) practices. AWEA believes this is necessary because engineering designs are normally not finalized until after feasibility studies are complete, and the developers understand the specific grid conditions at the point of interconnection.

AWEA also asked FERC to reiterate that meeting these standards will presumptively entitle a facility to gain the right to interconnect to a transmission system unless a utility can show just reason for more stringent standards. In addition, AWEA asked FERC to signify that transmission providers -- on a case-by-case basis -- should waive any requirements not needed to meet reliability standards.

In the filing, AWEA requested that FERC schedule a technical conference to formally introduce the "Grid Code" to the electric power industry. According to AWEA, FERC likely will hold the conference and issue a rule to adopt this proposal into the broader rulemaking over the summer and fall.

“The wind industry embraces the fact that the maintenance of the reliability of the transmission system is a responsibility shared by all users of that system," Caldwell said. "Wind plant developers also need consistent rules in order to plan for the future. With the 'Grid Code' filing, we are laying out what is feasible and responsive to transmission providers’ concerns for grid reliability. We invite a dialogue with transmission operators and engineers on the details of the rulemaking implementation.”

On March 3, 2004, FERC reaffirmed its July 2003 rule (Order No. 2003) that sets standard procedures and agreements for the interconnection of generators larger than 20 megawatts -- a move designed to facilitate development of needed infrastructure for the nation’s electric system. In this rule, FERC offered a forum to the industry to put forth its recommendations on what the appropriate standards for the wind industry should be.

In response to FERC's request, Caldwell convened an industry group to recommend best practices for the wind industry. The group researched emerging practice from utilities, turbine manufacturers and design engineers around the world; engaged transmission engineers from U.S. utilities purchasing wind power; and participated in several formal studies of the issue.

For a copy of AWEA's filing, contact Jim Caldwell at JCaldwell@awea.org or (202) 383-2517.

(Source: Wind Energy Weekly, 5/21/04)