Jun. 18--Nevada Power Co. is asking state regulators to approve the third and
last leg of the $300 million Centennial transmission project. "This has been a huge project for this company, and, I might add, it's
been a very successful project," said Matt Davis, vice president of
distribution services for Nevada Power. The Public Utilities Commission approved the project in 2001, the start of a
new century, and it was named the Centennial projects. Nevada Power proposed the project as a way to transport additional
electricity to the explosively growing population in Las Vegas. At the time, it
was in the midst of a Western energy crisis that sent wholesale prices soaring.
The transmission lines help the utility import power from other areas and enable
independent power producers in the area to sell some of their energy in other
states. The last phase runs 60 miles from the Harry Allen switch yard at the Apex
Industrial Park, around the east side of the valley, and along a corridor
followed by two existing transmission lines to the Mead Substation south of Las
Vegas. The Harry Allen-Mead transmission lines and related improvements will cost an
estimated $118 million. The company has obtained all of the required governmental approvals, with the
exception of an environmental permit from the Public Utilities Commission. The
PUC has scheduled a hearing in Las Vegas on Aug. 3. If the commission gives Nevada Power a permit, Davis expects construction to
start in the second half of 2005, with completion by early 2007. The Centennial project originally was designed to provide transmission for
new merchant power plants, including Pinnacle West Capital Corp.'s Silverhawk,
Mirant Corp.'s Apex Generation Station and some projects that have been delayed
or shelved. The Centennial project would provide transmission capacity for 3,000
megawatts of electricity, but the Mirant and Pinnacle West projects together
have only about 1,000 megawatts of power generation capacity, Davis said. Nevada Power also will use some of the transmission capacity for its proposed
500-megawatt gas-fired plant and 75-megawatt gas-fired plant, both at Apex. Nevada Power acted as general contractor for the project. It was the first
time it designed and built 500-kilovolt transmission lines, one of the largest
types of power lines now in use. The electric company last year completed the 500-kilovolt Harry Allen to
Northwest substation near Kyle Canyon Road. It also has finished the
500-kilovolt line between the Crystal Substation north of the Apex Industrial
Park. A year ago, it installed two of the largest transformers in the world at
the Crystal Substation.
Visit http://www.powermarketers.com/index.shtml for excellent coverage on your energy news front.