Power Engineers Helps Commission New Iraqi Power Plant
Oct 27 - Bulletin. Northwest Public Power Association
POWER Engineers (Boise, Idaho) has helped bring welcomed relief to Iraq in August 2004 when the new power plant was completed in Buzurgan, Iraq, and connected to the Iraqi electrical grid.
The new plant is a 40 megawatt, GE EM6000PC, which was designed and equipped
to utilize either natural gas or diesel as the operating fuel. In October, there
was nothing at the site but a high voltage transmission tower, with gas wells
burning in the distance. As a subcontractor to Perini Corporation, POWER was
part of the team that designed the plant, as well as the adjacent switchyard to
connect to the nearby 132-kilovolt transmission line. Perini was the prime in
charge of construction of this plant; POWER was the lead design engineer, with
Tetra Tech and General Electric's Aero Energy and Industrial Systems divisions
providing specialized support.
POWER is involved in another 40 megawatt generator installation at an
existing power plant in Southern Iraq that is nearing completion, and has just
turned over two refurbished 63 megawatt generators at a second existing plant to
the Ministry of Electricity. Together with the Buzurgan plant, these projects
will contribute nearly 200 megawatts to the national grid, enough to service an
estimated 600,000 Iraqi homes. In April, under a contract with Perini, POWER
Engineers completed the rehabilitation of 360 kilometers of high voltage
transmission line and towers in Southeastern Iraq. All of these projects were
awarded under a previously announced contingency contract with the U.S. Army
Corps of Engineers. The new power will benefit the local population, which now
receives 15-24 continuous hours of power a day, according to Colonel Thomas
Koning of the Corps. This is in comparison to approximately only three hours of
power per day before the war. Colonel Koning recently spent six months in
Southern Iraq as the District Engineer of the Corps' Gulf Region Division-South
District.
"This has been some of the most challenging work ever undertaken by our
company," said Perini President & Chief Operating Officer Robert Band.
"While we have a history of completing complex projects in short time
frames in our U.S. markets, to complete this amount of work in just 10 months in
Iraq was quite a feat. It is a real tribute to the dedication and team spirit of
our employees, subcontractors and the U.S. Army Corps of Engineers. We are very
proud of the entire team."
"POWER'S philosophy of teamwork was evident. We believe in working
together to get the job done," said POWER Engineers Vice President and
Manager of Transmission & Distribution Bill Eisinger. "That's how we do
all of our projects. Working in a war zone brought some unique and difficult
challenges that made teamwork all that more important."
Copyright Northwest Public Power Association Oct 2004