06-09-04
According to the CCTV since the first station of the west-to-east natural gas
transfer project successfully received gas natural gas from Xinjiang Tarim has
been rushing toward the west terminal in Shannxi Jingbian station at a speed of
18 km per hour. The west-to-east natural gas transfer project started in July 2002. With
Shannxi Jingbian as the linking point it is divided into the west line and the
east line. The east line has been put to commercial operation.
Source: People's Daily OnlineWest-to-east natural gas transfer to reach west line terminal
In several days the natural gas has successfully passed the Taklamakan Desert,
the Gobi desert, the depopulated region and the Hexi Corridor. Along the Qilian
Mountains and passing through the Yellow River Irrigation area it would reach
Shannxi Jingbian after travelling 2,500 km. Then it would be linked to the east
line that has been completed to realize full-line flow.
According to plan the whole west-to-east natural gas transfer project will be
put into production by October 1 and then into commercial operation by October
1, 2005.