Missed Deadline Could Stall Yucca
Sep 07 - Deseret News (Salt Lake City)
LAS VEGAS -- The Energy Department failed to meet a self-imposed deadline for making documents public about a national nuclear waste repository in Nevada, a federal panel said in a late August ruling that might slow the Yucca Mountain project.
Adams said the decision by the Nuclear Regulatory Commission's Atomic Safety
and Licensing Board, coupled with a recent court decision invalidating an
Environmental Protection Agency radiation standard, seemed certain to stall the
project 90 miles northwest of Las Vegas.
An Energy Department spokesman said lawyers were reviewing the 54- page
opinion and would decide whether to appeal the panel's ruling to the full
commission.
"We're continuing to move forward," spokesman Joe Davis said from
Washington, D.C. "We've got a goal of opening Yucca Mountain in 2010. With
all the process of getting the NRC license and congressional funding, that
remains our goal."
He declined to say whether the Energy Department will meet another
self-imposed deadline for submitting a license application for the project to
the Nuclear Regulatory Commission by Dec. 31.
The department had declared June 30 that it had made public some 1.2 million
documents about its plan to entomb spent nuclear fuel from 39 states at Yucca
Mountain.
The state, which opposes the repository, challenged the declaration July 12
-- just three days after a federal court in Washington, D.C., ruled that a
10,000-year EPA radiation safety standard for the project was insufficient.
Energy Department officials have insisted after both actions that they could
press on toward the Dec. 31 deadline. A delay could push back the government's
tight time line, which aims to open the repository in 2010.
The Energy Department is required by law to certify six months before
applying for a license that all Yucca Mountain documents are publicly available
on a Nuclear Regulatory Commission Web site.
The Energy Department had said it made the documents, totaling 5.6 million
pages and accumulated over 20 years, available to the NRC through a DOE Web
site.
The NRC panel, appointed to rule on the state's challenge, said the Energy
Department had not met NRC requirements. But it added that it did not appear it
would take long for the Energy Department to re-certify that the documents are
available.
Davis said the process could take about a month.
Nevada and other participants in the licensing process will then have 90 days
to submit their project documents.
The Nuclear Regulatory Commission is expected to spend several years deciding
whether to allow the repository to open. For far more extensive news on the energy/power
visit: http://www.energycentral.com
. Copyright © 1996-2004 by CyberTech,
Inc. All rights reserved.