Electric Power Supply OK Through 2007, But Parts Of Grid Near Limit: NERC
North America will likely have sufficient generating capacity to meet demand
through 2007, if proposed capacity additions are built, the North American
Electric Reliability Council said in its 2003-2012 Reliability Assessment.
The report projected that total electricity demand in the U.S. and Canada will
increase by 67,000 MW from 2003 through 2007, well below the 89,000 MW of new
generating capacity that is expected to be added over the same period.
While the council said the outlook for 2008 through 2012 is more uncertain, it
said that if current trends continued, there should be sufficient capacity to
meet expected long-term demand.
The report also said the transmission system is expected to perform reliably
over the near term, but warned that as customer demand increases and
transmission systems experience increased power transfers, "portions"
of the grid "are reaching their reliability limits." NERC further
cautioned that some parts of the grid will not be able "to transmit the
output of all new generating units to their targeted markets. Some well-known
transmission constraints are recurring, while new constraints are appearing as
electricity flow patterns change." Transmission problems, the report added,
can be avoided if transmission limits "are adhered to and operating
procedures are implemented as required."
"In cases where generation redispatch options have been exhausted or are
ineffective, the only way to remove these constraints is to build new generation
close to the demand center...or increase the capability of the transmission
system." NERC said more than 7,400 miles of new transmission lines (230 kV
and above) are proposed to be added through 2007, with a total of 11,600 miles
added over the 2003-2012 period covered by the study. The study said that most
of the reliability regions in the U.S. and Canada do not anticipate any fuel
problems over the study period.
The report, which examined transmission and generation reliability in each of
NERC's 10 regional reliability councils, cited, among other things,
"growing concern" within the Electric Reliability Council of Texas
over the future adequacy of natural gas supplies. More than 60% of existing and
projected generating capacity in ERCOT is fueled solely by natural gas and
officials are hoping to avoid a repeat of the widespread gas curtailments to
generators that occurred last February, when the region experience
colder-than-normal weather. ERCOT officials, the study said, are considering
offering economic incentive for generators that can switch fuels.
The Mid-America Interconnected Network said although it expects its transmission
system to perform adequately over the report period, delays in the completion of
the Arrowhead-Weston 345-kV reinforcement project could impact future
reliability. The Western Electricity Coordinating Council said it expects to be
able to reliably meet demand through the study period, but warned that
California may experience generation shortfalls by 2007 because of the decrease
in new generating projects. In fact, the entire West, the report added, has seen
a "dramatic reduction" in the amount of new generation proposed to be
constructed and placed in operation from that reported in last year's
reliability assessment.