By Brice
Wallace
Deseret Morning News
PacifiCorp, catching heat for picking itself from among dozens of bidders to
build a proposed power generation plant, contended Wednesday that it did not
have a conflict of interest in being both a bidder and bid selector.
At issue is whether PacifiCorp, which operates as
Utah Power in Utah and Idaho, acted properly when it selected itself to
construct a gas-fired plant in Mona, Juab County. The utility contends it was
the best choice from a group of 79 bidders. That contention was backed up by its
hired consulting company, Navigant Consulting Inc., although other bidders say
that choice ultimately could be more costly to customers than other options.
PacifiCorp says the plant will cost $350 million,
which it believes is $320 million less expensive, over the life of the plant,
than the next-best bid.
Several bidders have claimed that PacifiCorp's
bid process was too confusing and that its "self-build" choice is
suspect. But during a Wednesday Utah Public Service Commission hearing on the
Currant Creek project, Mark Tallman, PacifiCorp's managing director for trading
and origination, testified that he sees no conflict, adding, "I think the
commission is the ultimate judge.
"I don't believe that PacifiCorp has a
conflict. Our perspective is to bring the best resource to customers. I am aware
that others believe we have a conflict," he said Wednesday.
"Our proposal wasn't a competitor. Our
proposal was a benchmark. It was there to serve as a benchmark and a cost-based
alternative for comparison purposes and to be implemented if necessary."
"It wasn't a competitor, but it won. Is that
your testimony?" asked Gary Dodge, an attorney for the Utah Association of
Energy Users, a group of industrial companies.
"It didn't 'win.' It was the best choice,
the best course of action. It wasn't a case of winning and losing," Tallman
replied.
"There were no preconceived notions about
'build' vs. 'buy,' " he said later. "There was no underlying tone that
came down from on high to make sure the process gets the right answer. The right
answer in the process was the least-cost alternative, regardless of build vs.
buy."
Navigant, he said, "looked over our
shoulder" to ensure PacifiCorp was "evaluating things in a fair and
balanced fashion."
Tallman said the utility is restricted, unlike
the other bidders, from recovering the construction costs over a 20-year period.
Instead, it must recover them over the expected 35-year life of the plant.
"My testimony shows that the Currant Creek
project is still the most economic choice for customers, even if all costs are
accounted for over a 20-year term, which of course we would not be allowed to
do, instead of a 35-year term. And even on that basis, Currant Creek enjoys a 14
percent advantage over any of the other offers that were received."
Tallman also said the utility chose to not
publicize its own proposal during the bidding process because it would have made
bidders less aggressive and less creative.
The utility is expecting to be about 1,049
megawatts short of meeting demand during summer 2005. A megawatt is enough
electricity to power about 500 homes. Currant Creek would put 280 megawatts
toward meeting that amount by then, on the way to being a 525-megawatt plant,
and the company has found other supplies to add to that for the 2005 summer
season.
Without Currant Creek, the company has a
"daunting task" to secure enough resources for that summer, Tallman
said.
Critics also have said the bid comparison was
skewed because PacifiCorp solicited bids for "peaking" electricity —
used during high-demand periods — but its own option included peaking and
baseload components.
Some bidders also have chastised the utility for
trying to cram the regulatory process into a short period of time, leaving
inadequate time to prepare. Tallman said the company decided to move forward
with the Currant Creek project in late September.
His testimony indicated the company made the
decision when the bidding process would begin. But, he said, "to infer that
we maliciously delayed the process is just wrong."
Dodge has called PacifiCorp's actions
"blackout blackmail," contending that the commission is faced with
approving the project on PacifiCorp's terms and timetable or dealing with
rolling blackouts in summer 2005.
"Without Currant Creek, the chances of any
of those events occurring and resulting in an outcome that is undesirable is
higher," Tallman said. He said it would be unwise "to sit and sit and
wait and hope that a resource will show up."
Under questioning from Dodge, Tallman said the
company has done no analysis on any savings to ratepayers if the Currant Creek
project were delayed one year and the summer 2005 demand were met by buying
power elsewhere. "Our premise has been that Currant Creek is needed, and
that's how we've moved forward," he said.
Tallman was the only witness Wednesday, and the
hearing is expected to continue into next week. The commission has decided to
not have oral public comment but instead welcomed the public to provide written
comment until Feb. 27. It is encouraging the public to work with the state
Committee of Consumer Services, which represents individuals, small businesses
and farmers on utility matters.