Utilities violating state mandate on renewable energy
Apr 12 - Las Vegas Review - Journal
The utilities, both subsidiaries of Reno-based Sierra Pacific Resources,
contracted with independent power companies to build renewable energy facilities
rather than build their own. But the two utilities have faced a series of
"supplier delays, defaults and terminations" for renewable power, they
said in filings with utility regulators.
Because of those delays and postponements, Nevada Power and Sierra Pacific
will not meet the state's minimum requirements for renewable energy for 2003 and
2004, the companies reported.
The utilities are asking that they be exempt from the renewable energy
requirements for the two years so they will not be fined under the 2001
so-called renewable portfolio standard law.
The renewable-energy law requires Nevada Power Co. and Sierra Pacific Power
Co. to obtain increasing portions of their power supply from renewable
resources, including the wind, the sun and geothermal wells that tap hot
underground water, the wind and sun.
It mandated that the two electric companies obtain 5 percent of the power
they sell from renewable or green power sources last year, increasing to 15
percent by 2013.
In their report, the utilities said many of the projects they were counting
on to meet the requirements have been canceled.
"The ATS (Advanced Thermal Systems) geothermal project planned for
Steamboat near Reno lost its ability and/or rights to use resources owned by
third parties," the report said. "That project failed."
And the Desert Queen wind project, which was being developed at Goodsprings
by Cielo Wind of Austin, Texas, depended on extensions of federal tax credits.
"When those extensions weren't granted, that project failed," the
utilities reported.
Also, the MNS Wind project that was to be built at the Nevada Test Site was
scheduled to start operation by the end of 2003, but the U.S. Air Force objected
and the project was scuttled.
Those three terminated projects accounted for 60 percent of the green power
Nevada Power needed to comply with minimum requirements under state law.
The two utilities reported that other projects have been delayed.
Earth Power Resources planned a geothermal project 60 miles north of Elko,
but it "has experienced resource and permitting difficulties" and has
been delayed one year or longer, according to the utilities.
The Ely Wind project near the city of the same name has been delayed two
years. Solargenix Energy is developing a solar thermal project at a site 20
miles southeast of Las Vegas but that project has been delayed nine months or
more. Ely Wind and Solargenix "experienced difficulty finalizing their
financing arrangements," the utilities said.
Ormat provided some good news about its two geothermal projects near Fallon.
Its 20-megawatt project is delayed three months, and a 10-megawatt project
"is on time for commercial operation June 30, 2005," the utilities
wrote.
Neither Nevada Power nor Sierra will satisfy requirements for solar
generation in the two years, both having contracted with Solargenix for a plant
in the Eldorado Valley, according to the report.
However, the utilities have issued requests for proposals for green power
projects in 2005 and 2006.
"In addition, the utilities are working with developers who are
dependent on the utilities' balance sheet to finance their projects on
alternative financing structures ... ," the summary said.
Analysts explained that renewable power developers are having difficulty
financing their projects because the two Nevada utilities have junk bond ratings
and lenders fear that the utilities might default on power purchase contracts. Copyright © 1996-2004 by CyberTech,
Inc. All rights reserved.