Coal-fired S.D.
power plant's price escalates
Jul 27, 2006 - Star Tribune, Minneapolis
Author(s): Tom Meersman
Jul. 27--The largest power plant in South Dakota history, a proposal
already under fire from environmental advocates for using coal instead
of wind, would be 50 percent more expensive than previously estimated,
according to utility executives.
Otter Tail Power Co. officials told Minnesota regulators last week
that the price of building the coal-burning Big Stone II plant could
reach $1.8 billion, up from $1.2 billion, because of higher costs for
labor, steel, pollution control equipment and other factors.
At stake are the first major coal-fired power plant to be built in
the region in more than two decades, and the interests of seven electric
utilities -- led by Otter Tail Power -- that are partners in the
project.
Higher costs would mean higher electric bills for customers, but the
bigger question is whether the project itself may be delayed or even
jeopardized.
Otter Tail senior vice president Ward Uggerud said that even with the
higher estimate, the project would be less expensive than producing the
same power from renewable energy or natural gas.
However, environmental leaders challenge those claims, and have said
that the plant will emit too much mercury and other air pollutants,
diminish stream flow and water quality in the Minnesota River, and
consume land with its high-voltage transmission lines.
South Dakota officials approved two important permits for the power
plant recently, one of them specifically against the wishes of the
Minnesota Department of Natural Resources. The project still needs
permits from Minnesota regulators because it includes about 85 to 125
miles of new or upgraded power lines in the state, depending upon which
routes are chosen.
Because the great majority of the electricity would be sent to
Minnesota, including the Twin Cities, the power lines are an essential
part of the project, according to Steve Schultz, external affairs
manager for the project. He said that the 600-megawatt power plant is
needed because electricity demand is growing by 2.5 percent annually in
the region, and coal supplies from the West are plentiful and
affordable.
It would be built near Milbank, S.D., next to an existing plant a few
miles from the Minnesota border. Schultz said the utilities chose a
coal-fired plant also because it is a mature technology and emissions
can be controlled.
"This is a piece of the puzzle," he said. "There's room for
renewables and other forms of [power] generation, too."
However, environmental leaders see the plant as a huge mistake,
saying the area has vast potential to develop wind-generated
electricity.
Big Stone II will "soak up" the demand for power that would otherwise
be met by new wind farms, said Beth Goodpaster, an attorney for the
Minnesota Center for Environmental Advocacy. The center was among four
groups that testified in the South Dakota case, arguing that developing
wind energy would produce seven times more long-term jobs and five times
more dollars for South Dakota's economy than the coal plant.
Duane Ninneman, who lives just north of Ortonville, Minn., said that
it doesn't make sense to build another coal plant when Minnesota already
receives almost three-quarters of its electricity from coal, and wind
power has proved to be the cheapest form of new electricity in the
state.
"It's not in the interests of Minnesota consumers to send their
dollars to the coal fields of Wyoming and to build a technology that's
really from the last century," said Ninneman, who works for a
western-Minnesota group called Clean Up the River Environment.
Opponents also argue that the plant will emit mercury that will
contaminate Minnesota waters and fish, and carbon dioxide that
contributes to global warming. The plant is an economic risk, they said,
because at some point legislators are sure to impose costs on carbon
emissions -- and those costs would be passed on to consumers.
Schultz countered that carbon dioxide is not regulated now, and no
one knows when or if it will be. "At some point you must move forward,"
he said, since additional electricity is needed in the region. "If new
regulations come, we'll deal with it."
Kent Lokkesmoe, director of the waters division for the Minnesota
Department of Natural Resources, asked the South Dakota Water Management
Board last month to postpone a decision about a water permit for the
plant until Minnesota and South Dakota officials could reach an
agreement on managing the level of Big Stone Lake, a prime fishing lake
on the states' border.
Lokkesmoe noted that taking too much water from Big Stone Lake could
lower lake levels 6 to 12 inches, threatening the flow and water quality
both in the lake and the Minnesota River.
Eric Gronlund, an engineering specialist with the South Dakota
Department of Environment and Natural Resources, said there are
safeguards for how much water may be withdrawn from Big Stone Lake
during periods of drought.
The South Dakota Water Management Board approved the plant's water
permit on July 12. Two days later, the South Dakota Public Utilities
Commission approved a siting permit for the plant.
Uggerud, the Otter Tail Power executive, said the utility partners
will likely meet in mid-August to discuss the latest cost estimates.
One partner with an 8 percent share of the project, Southern
Minnesota Municipal Power Agency, already has heard from one of its 18
members. Austin Utilities, which has 10,000 electricity customers in
southern Minnesota, has asked SMMPA to withdraw from the project even if
it means facing penalty fees.
"We see an increasing cost and we're not willing to take on more and
more debt," said Jerry McCarthy, Austin Utilities general manager.
Schultz said that the Big Stone II partners, led by Otter Tail Power,
have held meetings to discuss the project and the power lines in six
Minnesota cities: Morris, Benson, Willmar, Granite Falls, Canby and
Ortonville.
He said that 5,000 Minnesotans have received mailings that power line
corridors under consideration for the project are near their homes.
Public hearings on the need for the power lines and their likely routes
will begin in October, and ultimately will be decided by the Minnesota
Public Utilities Commission.
© Copyright 2006 NetContent, Inc. Duplication and
distribution restricted.Visit http://www.powermarketers.com/index.shtml
for excellent coverage on your energy news front.
|