Grid issues
pounds 500m demand Company faces backlash from wind farm developers as
it calls for mo...
Jul 31, 2006 - Daily Telegraph London
Author(s): Cosima Marriner
NATIONAL Grid is demanding up to pounds 500m from prospective wind
farm developers before it expands the electricity network capacity to
accommodate new sources of power.
Wind farm developers that have applied to connect to the electricity
grid have been told they must first put up financial guarantees, known
as final sum liabilities. National Grid is seeking a total of pounds
500m from the top 20 wind farm developers.
National Grid wants developers to provide bank guarantees to cover
the cost of the network expansion to cope with the expected extra power.
It wants to weed out opportunistic wind farm developers and protect
itself financially.
"They say they don't have the money and they're reluctant to deal
with more than five or six major utilities,'' said one source.
Developers that don't use their transmission connections will forfeit
the money. But those that connect to the network will get their money
back from National Grid.
Some developers have withdrawn their applications after being told
they would have to put up a financial guarantee.
It is also understood that some major oil companies are considering
running electricity cables underground alongside their oil and gas
pipelines rather than negotiate connections with National Grid.
Fledgling wind farm developers argue the bank guarantees sought by
National Grid impose a financial strain on companies before they have
even started producing power and making money. "This is putting a lot of
people off,'' said a source. "When people have to start putting up
letters for those sums of money, it starts to impact on people's balance
sheets.''
Scotland and outlying islands are the UK's biggest sources of wind
power. Although Scottish Power owns the electricity network in Scotland,
National Grid manages the network. National Grid says it will cost
pounds 550m to upgrade its network to accommodate the extra 3 gigawatt
to 5 gigawatt of power that wind farms in Scotland are expected to
generate and to transport it to centres of demand.
It told the Government's recent energy review that this investment is
necessary to transport all the promised new power generated by remote
wind farm sites to the main centres of electricity demand. It will also
have to spend money to increase further the bulk transfer of power from
the north to the south.
A National Grid spokesman confirmed the company was seeking financial
guarantees from wind farm developers before spending money on new
capacity for them.
"We don't want to build something that isn't going to be used. There
has to be some shared risk.''
National Grid is currently sifting through 170 requests for
connection from power companies. If all these went ahead, the amount of
electricity generated in Scotland would double.
"This is an unprecedented level of requests at one time,'' the
spokesman said.
Faced with a backlash from wind farm developers, National Grid has
offered to cut the amount of money it is seeking. It is considering
asking for smaller guarantees at the outset, gradually increasing the
amount as the project nears completion. It has also suggested developers
in the same area "cluster'' together on their connection and share the
final sum liability.
© Copyright 2006 NetContent, Inc. Duplication and
distribution restricted.Visit http://www.powermarketers.com/index.shtml
for excellent coverage on your energy news front.
|