Wind and ice
can't knock down buried cables, so . . .Why not go UNDERGROUND?
Cities and power companies debate burying
electric utility lines to reduce the impact of mass power outages versus
the cost.
Aug 6, 2006 - St. Louis Post-Dispatch
Author(s): Jeffrey Tomich; St. Louis Post-Dispatch
As a freshly minted chief executive, Ameren Corp.'s Gary L. Rainwater
declared in 2004 that one of his goals was to systematically bury the
company's power lines over a period of decades to avoid mass power
outages and improve relationships with customers.
Not long after that, the CEO crunched numbers with Chief Operating
Officer Tom Voss and realized that, despite the benefits, putting 61,000
miles of overhead distribution line below ground wasn't feasible.
"Tom educated me on the numbers, and I said, 'Scratch that one off
the list,'" Rainwater said at the company's Chouteau Avenue
headquarters. "The cost to provide underground service would be
literally hundreds of dollars a month. It would triple or quadruple the
price of electricity."
Across the country -- especially in the hurricane-prone Southeast --
utilities continue to look at putting more electric lines below ground
to storm-proof systems and improve aesthetics. And in most new
subdivisions in the St. Louis area and elsewhere in the country,
developers and utilities often share the cost of putting new lines
underground.
But even after the July 19 and 21 thunderstorms that spawned
tornadoes and severed power to 700,000 customers -- some for more than a
week -- rewiring the region isn't viewed as a realistic solution.
Ameren officials cite a survey by the Edison Electric Institute, a
trade association for investor-owned utilities, that showed customers
are willing to pay about $25 a month extra to put lines underground. But
the real cost of digging up streets and sidewalks and replacing
equipment would be about $50,000 per customer.
Despite the high price tag, industry analysts say underground systems
aren't immune to disruption. Just ask Consolidated Edison customers in
Queens, where it took 10 days to restore power to tens of thousands of
customers last month in part because lines were underground, prolonging
repairs.
Underground electric systems also are susceptible to water incursion.
And typically, not all of a circuit can be placed underground, exposing
at least part of it to damage from falling trees or ice.
"Underground systems go down less often, but the outage in duration
is much longer," said Gautam Mukherjee, an analyst at Cambridge Energy
Research Associates. "Unfortunately, with storms there's no single good
solution."
The Washington-based Edison Institute last month released a detailed
study on underground power lines called "Out of Sight, Out of Mind?" It
estimates the cost of installing underground lines at $1 million a mile
compared with about $100,000 a mile for overhead lines.
The study looked at data from Virginia and Long Island Power
Authority and showed that, on average, underground circuits had only 20
percent to 25 percent of the outages of overhead circuits. However,
repairs took 2 times as long because problems are harder to find and
underground lines require special equipment and crews.
Despite the costs, at least two municipal utilities in Missouri are
moving forward with plans to put more of their distribution systems
below ground to avoid widespread outages like the one the St. Louis area
dealt with last month.
In Columbia, voters will go to the polls Tuesday to decide whether to
approve spending $5.8 million over five years to bury existing overhead
lines, said Connie Kacprowicz, a spokeswoman for Columbia Power & Light.
Farther west, Independence Power & Light is taking a more aggressive
approach.
The city of 110,000 residents is spending $1.5 million a year to put
existing overhead lines underground. Since a 2002 ice storm crippled the
city, it has received about $4 million in federal grants to bury
thousands of individual lines to customers' homes.
The utility also shares the cost of burying lines to customers' homes
with the customers' payments spread over five years. About 200 a year
sign up, the utility says.
IPL doesn't have statistics to show its initiative is making the
city's distribution system more reliable, but Jack Looney, an
engineering planner and supervisor for the utility, says proof should
come when the next big storm hits.
"The system operates much more efficiently and much more reliably
than it did 10 years ago and certainly 20 years ago," he said. "And
we're not going to stop here."
---
Overhead vs. underground
Miles of Ameren overhead distribution line: 61,824
Miles of Ameren underground distribution line: 12,547
Average cost per mile to install underground line: $1 million
Average cost per mile of overhead line: $100,000
Source: Ameren Corp., Edison Electric Institute
© Copyright 2006 NetContent, Inc. Duplication and
distribution restricted.Visit http://www.powermarketers.com/index.shtml
for excellent coverage on your energy news front. |