Judge OKs tritium
plan at Braidwood
May 25, 2006 - Chicago Tribune
Author(s): Hal Dardick
May 25--Exelon Nuclear plans to start removing radioactive tritium
from groundwater outside a nuclear power plant in Will County within
weeks under an agreed court order entered Wednesday.
The 23-page order, approved by Circuit Judge Richard Siegel, came
after months of talks among Exelon Nuclear officials, State's Atty.
James Glasgow, attorneys working for Atty. Gen. Lisa Madigan and
officials of the Illinois Environmental Protection Agency.
"We've been negotiating non-stop since we filed this thing," Glasgow
said, referring to the suit he and Madigan filed in mid- March, after
Exelon disclosed that groundwater outside the plant had been
contaminated by tritium that spilled from Braidwood Generating Station.
The order was described as a "first step" that does not bring an end
to the lawsuit. It includes fines of up to $1,500 a day if Exelon
Nuclear, part of Exelon Generation, fails to meet its terms.
"Lawsuits take time," Madigan said. "This order is about requiring
Exelon Generation to take steps to protect public and environmental
health and safety now."
Joe Cosgrove, who as director of the Park District in nearby Godley
has worked years to shed light on the tritium issue, praised the
agreement.
"I definitely think it's a good start," Cosgrove said. "At least
Exelon is trying to remediate and acknowledging that there is an issue."
Exelon officials said the cleanup would start in about two weeks. The
company first announced the cleanup plan in late March, but the county
withheld a work permit until the court order was entered.
To lower tritium concentrations in groundwater near the plant, Exelon
will pump water from a contaminated pond to the Kankakee River. Once the
water is pumped out, it is expected contaminated groundwater will flow
into the pond from surrounding land.
That water, in turn, will be pumped to the river through the
underground pipe from which tritium spilled 22 times between 1996 and
early this year, according to Nuclear Regulatory Commission documents.
Three of the spills were significant and led to most of the
contamination, the documents state.
Glasgow said Exelon has installed alarms on valves along that pipe.
If the valves leak, as they did in the past, an alarm will go off and
pumping of tritium into the pipe will be immediately halted, he said.
Vaults holding those valves have been sealed, so if the valves do
leak, water with tritium will not penetrate the ground, he said. The
order also requires Exelon to regularly inspect the pipe and monitor
groundwater adjacent to its path.
Though tritium in groundwater outside the plant exceeds government
limits, tests found only one private well had significantly elevated
levels of the substance. But those levels were well below the point at
which state and federal agencies deem tritium dangerous.
Slightly elevated levels of tritium were found in about six shallow
wells in Godley, but those levels were barely above what can be expected
in nature, county Health Department officials said.
Chronic exposure to tritium, a byproduct of nuclear generation, can
increase the risk of cancer. But government agencies have said the
levels found near the plant pose no risk to public health.
"While state and federal agencies have confirmed that the levels of
tritium in the groundwater are not a health or safety hazard to our
neighbors, we have pledged that we would clean up the groundwater,"
Exelon Nuclear President Christopher Crane said. "All unplanned releases
of tritium are unacceptable to Exelon."
The initial groundwater cleanup could take more than a year, Exelon
officials said. But it is expected to quickly halt further migration of
contaminated groundwater and reduce the size of the contaminated area,
which measures about 4 million square feet, officials said.
Under the order, Exelon must give Glasgow and Madigan 28 days' notice
if the company plans to again regularly dispose of tritium created at
the plant by sending it through the underground pipe, in which it is
diluted before being legally dumped into the river.
Cooling water containing no radioactive material is constantly being
sent through the pipe, but Exelon last year stopped injecting tritium
into that water.
Exelon is temporarily storing tritium in containers on site, while
the company evaluates options for reducing tritium production and future
disposal.
The company by July 1 also must come up with a plan to prevent
groundwater with tritium at levels exceeding government limits from
migrating off site.
A month later it must submit a plan for reducing tritium levels
outside the plant in spots where it exceeds government standards. The
company also must work to prevent off-site tritium levels from rising
above what is considered normal.
If tritium does leak again, Exelon must notify state officials within
24 hours.
Exelon also must hold regular meetings with residents to explain its
efforts, and it must reimburse the state EPA and Will County for costs
incurred addressing the tritium issue.
hdardick@tribune.com
© Copyright 2006 NetContent, Inc. Duplication and
distribution restricted.Visit http://www.powermarketers.com/index.shtml
for excellent coverage on your energy news front.
|