Coal may be abundant. But, transportation is not. And
therein lay the dilemma: Coal generators nationally are at
the beck and call of rail operators to deliver their
essential commodities. As such, transportation costs are
rising while some power facilities are experiencing fuel
shortages and subsequently higher costs.
|
Ken Silverstein
EnergyBiz Insider
Editor-in-Chief |
At issue are fuel adjustments that are linked to the
consumer price index. Utilities and others are not
necessarily opposed to such rate increases to keep pace
with climbing fuel prices. But, they are against what they
say are arbitrary price hikes that are meant to increase
profits. The rail companies deny such practices and say
that they are unable to move coal fast enough because of
limitations in the nation's infrastructure.
What to do? Well, Congress is now considering a
proposal to give the railway companies a 25-percent tax
credit for investments in rail infrastructure. Fine, say
utilities, so long as it is part of a broader legislative
package to increase capacity -- or, the number of lines to
carry coal to their generators.
"Railroads impose fuel surcharges not simply to recover
their unanticipated and uncontrollable increases in the
cost of fuel, but rather in excess of their increased fuel
costs in such a manner as to enhance their net revenues,"
says Steve Sharp, principal engineer with the Arkansas
Electric Cooperative Corp., at a hearing before the
Surface Transportation Board.
Fuel surcharges are a relatively new phenomenon. In
2002, for example, they were small at 2 percent of freight
charges. But, now, and specifically from coal supplies
delivered from the Powder River Basin in Wyoming that is
the nation's largest source of low-sulfur coal, they are
18.5 percent.
The rail industry's return on investment has risen from
2 percent in the 1970s to 7 percent today. With the
industry's improved financial condition, the rail
companies are investing an average of $6 billion a year in
infrastructure and equipment.
Rail operators say that it takes billions to upgrade
their systems. And these investments are risky because it
takes time to go through the regulatory and construction
processes. And by the time any improvements are made, the
entire economic scenario could change. That's why they
advocate tax credits as a way to lessen their risks.
Re-investment by today's standards is still considered
inadequate. And that's why the Surface Transportation
Board is given the authority to regulate rates where rail
competition is negligible and where shippers might need
protection. The Surface Transportation Board estimates
that as of the mid-1990s, 16 percent of all such traffic
remained regulated.
Captive Generators
Rural cooperatives are particularly affected by
constraints in the nation's rail system. While the nation
depends on coal for half of its electricity generation,
the electric cooperative community relies on coal to
supply 80 percent of the power generated by its plants.
And because few such facilities are located near the
actual coal mines, the commodity must be transported.
To complicate matters, consolidation among rail
operators has resulted in many generators being held
captive to a single transporter, the National Rural
Electric Cooperative Association says. The group openly
questions the intent of the rail companies: Certainly, all
parties recognize that constraints in the system do exist.
But, the co-ops think that the rail companies are not
committed to fixing the problem because rail shortages are
good for business. The result: Rail stocks are at a
premium and some utilities are paying the price.
Take the Laramie River Station in Wyoming: In the
spring of 2005, two derailments on the tracks coming from
the Powder River Basin occurred. Those accidents reduced
rail deliveries of coal by 80-85 percent. And, deliveries
have yet to recover. In the case of the Arkansas Electric
Cooperative that relies on the system there, it has turned
to alternate forms of energy production that have raised
its cost by $100 million over 12 months.
"We recognize that rail traffic is growing and there is
a need for investment in rail infrastructure," says Glenn
English, CEO of the National Rural Electric Cooperative
Association. "That need for investment, however, is not an
excuse for the unfair practices that are now standard
operating procedures for the railroads."
Indeed, the U.S. Energy Information Administration says
that the rail industry set a new high for freight traffic
transporting more than 1.5 trillion revenue ton-miles,
which is a unit of measurement that incorporates both
weight and distance. Coal makes up 40 percent of that
total, with farm and chemical products totaling 9 percent
each.
Deals are taking place today. The Dakota, Minnesota and
Eastern Railroad received permission to build from the
Surface Transportation Board in February. It will be the
largest such deal to be constructed in 100 years -- a
900-mile project involving upgrades and new construction
that heads eastward.
"It's been a long time coming," says Kevin Schieffer,
CEO of the Dakota, Minnesota and Eastern Railroad project.
"This project will have a tremendous positive impact on
agriculture, grain prices and economic development in our
area. And it will help lower energy costs and expand rail
capacity nationally."
While an important development, more needs to be done
to ease the capacity crunch and to lessen the cost of
transportation. Toward that end, the big utilities have no
objection to a fair method of adjusting rail rates for the
cost of fuel. The Edison Electric Institute says that if a
railroad has agreed with customers by contract to rate
adjustments, then a buyer must live with the terms of the
deal. Conversely, the institute says that it is patently
unfair to add fees for more than the carrier's cost of
fuel.
Rail companies may be sincere in their desire to expand
their infrastructure and keep prices down. But the methods
by which they impose rate surcharges deserve more scrutiny
and must become more transparent. If Congress decides tax
breaks are needed to build more lines, then development
should start where the tightest constraints exist and
where certain generators are held captive to single
carriers.
For far more extensive news on the energy/power
visit: http://www.energycentral.com
.
Copyright © 1996-2005 by CyberTech,
Inc. All rights reserved.
|