| Tidal energy 
        project eyed for river 
 May 11, 2006 - Bangor Daily News, Maine
 Author(s): Rich Hewitt
 
 May 11--VERONA ISLAND -- A Washington, D.C., company is eyeing the 
        Penobscot River for a tidal energy project which would utilize as many 
        as 100 underwater generators to produce electric power. Maine Tidal 
        Energy Co. has filed an application with the Federal Energy Regulatory 
        Commission for a preliminary permit for the first phase of the project. 
        The project is in the very early stages of development and would utilize 
        emerging technology to tap tidal currents in the Penobscot River to 
        generate power, according to Charles Cooper of TRC Environmental Corp. 
        of Lowell, Mass., the environmental consultant for the project.  Without divulging confidential research information, Cooper said the 
        characteristics of the area appear to be "suitable" and could "support 
        potential tidal possibilities." The FERC permit, if issued, will give 
        the company three years to study the site and to determine whether to 
        develop the project. The permit would not authorize the company to do 
        any actual construction in the river, according to commission 
        spokesperson Celeste Miller. "All they are doing is looking at the 
        site," Miller said Wednesday. "The permit would give them priority over 
        another entity to determine if they want to develop it in the future." 
        The initial study phase of the METidal project will cost between $1 
        million and $4 million and will involve developing baseline studies of 
        the project area.  Although no construction is proposed at this time, the METidal 
        application indicates the project would be located in the Penobscot 
        River along the western side of Verona Island. The study area includes 
        the entire western shore of the island in the study area, but the 
        application notes the actual project footprint will be determined 
        through site studies and will be smaller than indicated. The project 
        will consist of one or more clusters of tidal generators referred to as 
        "tidal in stream energy conversion" devices, connected by underwater 
        transmission cables to electrical infrastructure on shore, according to 
        the FERC application.  The exact location of the onshore tie-ins has not yet been 
        determined, although the application identifies proposed cable areas on 
        the eastern side of the river near Bucksport and on the western shore 
        south of Fort Knox. The TISEC devices are "definitely developmental 
        technology," Cooper said Wednesday, and the company is still looking at 
        different designs for the project. Cooper emphasized that the company is 
        still reviewing potential designs and has to take into account the 
        specific characteristics of the river, not only in siting the TISECs, 
        but in determining their size and type. "The references to specific 
        dimension are very preliminary and general, and are, in fact, part of 
        the development effort," Cooper said.  Ideally, he said, the devices would generate power on both rising and 
        falling tides. "We want to have the devices work as often as possible," 
        he said. "It's really too early to tell, but we'd like to see them 
        working on as many tides and as many stages of the tide as we could." 
        According to the application, the project will consist of rotating 
        propeller blades approximately 20-to-50 feet in diameter, an integrated 
        generator producing 500 kilowatts to 2 megawatts of electricity, an 
        anchoring system, a mooring line and a transmission line to shore. Each 
        of the 100 devices, or generators, is capable of providing power to 
        about 750 homes, for a total of 75,000.  However, the company has a target of 80 percent of capacity, and 
        expects to average approximately 8,760 megawatt hours per unit per year. 
        The company initially plans to build 100 units, although the actual 
        number will be determined "on a site-specific basis, taking into account 
        the need to co-exist with other uses of the area, including navigation." 
        The permit process includes no environmental review because the company 
        cannot construct anything, she said. Before METidal could build anything 
        in the river, it would have to apply for a FERC license, which is a 
        "more involved" process which would include obtaining other state and 
        federal permits, including environmental permits.  The project could provide an economic boost to the state, although 
        Cooper said, again, that it is too early to tell how significant the 
        impact could be. The project will generate jobs for the region, he said, 
        although the exact number will depend on how many units are built. There 
        also is a renewable energy component to the project, he said, noting 
        that the units will not depend on fossil fuel to operate. "There may be 
        other economic benefits that might not be realized locally, but will be 
        there," he said. FERC is now soliciting comments, protests and motions 
        to intervene in the permitting process.  Those wishing to comment have 60 days to file their comments by mail: 
        The Secretary, FERC, 888 First St. NE, Washington, D.C., 20426, or 
        electronically to the FERC Web site, 
        www.ferc.gov.      © Copyright 2006 NetContent, Inc. Duplication and 
        distribution restricted.
 Visit http://www.powermarketers.com/index.shtml
for excellent coverage on your energy news front. |