Tidal energy
project eyed for river
May 11, 2006 - Bangor Daily News, Maine
Author(s): Rich Hewitt
May 11--VERONA ISLAND -- A Washington, D.C., company is eyeing the
Penobscot River for a tidal energy project which would utilize as many
as 100 underwater generators to produce electric power. Maine Tidal
Energy Co. has filed an application with the Federal Energy Regulatory
Commission for a preliminary permit for the first phase of the project.
The project is in the very early stages of development and would utilize
emerging technology to tap tidal currents in the Penobscot River to
generate power, according to Charles Cooper of TRC Environmental Corp.
of Lowell, Mass., the environmental consultant for the project.
Without divulging confidential research information, Cooper said the
characteristics of the area appear to be "suitable" and could "support
potential tidal possibilities." The FERC permit, if issued, will give
the company three years to study the site and to determine whether to
develop the project. The permit would not authorize the company to do
any actual construction in the river, according to commission
spokesperson Celeste Miller. "All they are doing is looking at the
site," Miller said Wednesday. "The permit would give them priority over
another entity to determine if they want to develop it in the future."
The initial study phase of the METidal project will cost between $1
million and $4 million and will involve developing baseline studies of
the project area.
Although no construction is proposed at this time, the METidal
application indicates the project would be located in the Penobscot
River along the western side of Verona Island. The study area includes
the entire western shore of the island in the study area, but the
application notes the actual project footprint will be determined
through site studies and will be smaller than indicated. The project
will consist of one or more clusters of tidal generators referred to as
"tidal in stream energy conversion" devices, connected by underwater
transmission cables to electrical infrastructure on shore, according to
the FERC application.
The exact location of the onshore tie-ins has not yet been
determined, although the application identifies proposed cable areas on
the eastern side of the river near Bucksport and on the western shore
south of Fort Knox. The TISEC devices are "definitely developmental
technology," Cooper said Wednesday, and the company is still looking at
different designs for the project. Cooper emphasized that the company is
still reviewing potential designs and has to take into account the
specific characteristics of the river, not only in siting the TISECs,
but in determining their size and type. "The references to specific
dimension are very preliminary and general, and are, in fact, part of
the development effort," Cooper said.
Ideally, he said, the devices would generate power on both rising and
falling tides. "We want to have the devices work as often as possible,"
he said. "It's really too early to tell, but we'd like to see them
working on as many tides and as many stages of the tide as we could."
According to the application, the project will consist of rotating
propeller blades approximately 20-to-50 feet in diameter, an integrated
generator producing 500 kilowatts to 2 megawatts of electricity, an
anchoring system, a mooring line and a transmission line to shore. Each
of the 100 devices, or generators, is capable of providing power to
about 750 homes, for a total of 75,000.
However, the company has a target of 80 percent of capacity, and
expects to average approximately 8,760 megawatt hours per unit per year.
The company initially plans to build 100 units, although the actual
number will be determined "on a site-specific basis, taking into account
the need to co-exist with other uses of the area, including navigation."
The permit process includes no environmental review because the company
cannot construct anything, she said. Before METidal could build anything
in the river, it would have to apply for a FERC license, which is a
"more involved" process which would include obtaining other state and
federal permits, including environmental permits.
The project could provide an economic boost to the state, although
Cooper said, again, that it is too early to tell how significant the
impact could be. The project will generate jobs for the region, he said,
although the exact number will depend on how many units are built. There
also is a renewable energy component to the project, he said, noting
that the units will not depend on fossil fuel to operate. "There may be
other economic benefits that might not be realized locally, but will be
there," he said. FERC is now soliciting comments, protests and motions
to intervene in the permitting process.
Those wishing to comment have 60 days to file their comments by mail:
The Secretary, FERC, 888 First St. NE, Washington, D.C., 20426, or
electronically to the FERC Web site,
www.ferc.gov.
© Copyright 2006 NetContent, Inc. Duplication and
distribution restricted.Visit http://www.powermarketers.com/index.shtml
for excellent coverage on your energy news front.
|