Dutch Moving Wind
Turbines Offshore
September 18, 2006 — By Toby Sterling, Associated Press
AMSTERDAM, Netherlands — For centuries,
Dutch windmills have pumped water out of the low-lying country, and
old-fashioned wooden mills are as closely linked with the Netherlands'
international image as its dikes and bikes.
But in the face of a large and growing lobby against the windmill's modern
electricity-generating counterpart -- the wind turbine -- the country has
started moving them offshore and out of sight.
The Egmond aan Zee wind farm, the first major offshore Dutch project, is
nearing completion 8 miles from Haarlem and is scheduled to go on line
this fall. It has 36 turbines, each with arms reaching higher than a
football field, capable of producing a combined 108 megawatts an hour --
enough to power roughly 100,000 households.
It's the first in a flood of similar-sized offshore projects proposed for
Britain, Ireland, France, Germany and the United States, in Texas, New
Jersey and Massachusetts.
In the Netherlands, which targets having 9 percent of its electricity
generated from renewable sources by 2010, the need to move offshore is
growing more urgent due to the increasing number of wind turbine critics.
They say the towering mechanical structures are blighting landscapes that
once inspired Dutch painters like Rembrandt van Rijn.
"We have such a flat country, normally nothing blocks your view of the
sky," said Jim Mollet, leader of an anti-windmill group that claims 15,000
members. "These days, any turbine worthy of the name dwarfs even the
church towers."
He said his group offers a play-book to local protesters on how to resist
proposals for new turbines, often by farmers seeking generous state
subsidies. He said the turbines are not only responsible for "horizon
pollution," but are noisy and inefficient as well.
"We're not just NIMBY about wind energy," Mollet said, referring to the
"not in my backyard" acronym. "We're NIABY -- not in anybody's backyard."
While land-based wind turbines have made significant inroads in Europe and
now claim around 2.7 percent of the total European generation market,
offshore turbines have remained little more than a curiosity because the
economics are daunting.
Europe has 40,000 megawatts of installed wind capacity, the U.S. has 9,000
megawatts, and an additional 10,000 megawatts are scattered around the
globe, mostly in Asia. But so far just 600 megawatts are generated
offshore -- more than half in Denmark.
Christian Kjaer, policy director for the European Wind Energy Association,
predicts onshore wind generation will continue to grow, especially in
areas less densely populated than the Netherlands. But he expects offshore
generation will grow even faster, increasing its share to a third of all
wind energy in Europe by 2020 and half by 2030.
Building the turbines offshore means they don't spoil anybody's view, and
they can harness more consistent and stronger offshore winds. But they
must be rugged enough to weather salty sea air and the pounding of ocean
storms.
"It's a new technology, so costs are falling," Kjaer said. "At a certain
point the cost curves will collide" and offshore electricity will become
cheaper than onshore production. "But the question is, when?"
The Egmond project -- jointly owned by Royal Dutch Shell PLC. and the
Dutch utility company Nuon NV -- is costing $250 million to build,
debatably more than the revenue it will generate over its 20-year
lifetime.
A package of direct aid, tax breaks and production subsidies will cover
more than 100 percent of the construction costs over the first decade.
Anti-windmill activist Mollet says this money is little more than a
handout, but the companies argue they face hard-to-quantify maintenance
costs and other risks.
"It's at sea that a company like Shell has a competitive edge, on a large,
capital-intensive project with large technical challenges," said Huub den
Rooijen, director of the joint venture.
One late difficulty was the need to find a new location for the coastal
substation where cables carrying electricity from the turbines connect
with the Dutch power grid. A town successfully contested the original
plan.
The big, 1,000-megawatt London Array project in Britain is stalled by a
similar fight over the location of a substation.
In the Netherlands, the Dutch government has carefully mapped out space
for 65 wind farms in the North Sea during a 10-year consensus-building
phase.
They chose sites in shallow waters, out of sight except under extremely
clear conditions, avoiding shipping lanes around Rotterdam, Europe's
largest port, and far enough from shore to reduce the danger of their
whirling blades to coastal and migratory birds.
Hans Peeters, director of the Netherlands' Bird Protection Society, said
his group has opposed several projects where the proposed sites might
threaten birds, but he supports the offshore projects.
"It's too bad when any bird is killed, but as a nature organization we are
for wind energy," he said. "You must balance the threat to birds from
turbines in the short term against the threat of global warming in the
long run."
Peeters said his group drew hope from a Danish study that found fewer
migrating birds were killed by offshore turbines than expected.
"Apparently, birds see the turbines and avoid them," he said.
Source: Associated Press