When Connecticut-based United Illuminating wanted to
build a 69-mile transmission line and place 24 miles of it
underground, the idea got a warm reception from the
citizens of the affected communities. All in all, the
price tag in this case would not be any higher than doing
it all above ground because of rights-of-way issues. But
despite the good PR, no one likes to have their
neighborhoods dug up.
|
Ken Silverstein
EnergyBiz Insider
Editor-in-Chief |
Without a doubt, an underground electrical
infrastructure is aesthetically more appealing. And,
during periods of extreme weather conditions, it has
proven to be more reliable. But going underground is an
expensive proposition. The Connecticut case withstanding,
the direct costs are much higher than those associated
with traditional overhead power lines. Meantime, it is
much more difficult to find trouble spots -- and more
time-consuming to fix them. The trend, though, is toward
placing electrical lines underground and particularly in
new communities that are under development.
"On the face of it, undergrounding is the way everyone
wants to go," says Kate Shanley, who handles public
outreach for United Illuminating. "Cost is a nebulous
issue until you get into the nuts and bolts."
Undergrounding has been driven by the inability to
accommodate overhead construction, she adds. The
Middletown-Norwalk project won't be completed until 2009
in part because of the complexity surrounding the
permitting process. For example, the cable must make a
river crossing and it appears that the utility will be
forced to build a bridge to do that. "People like
underground better than overhead but they like it better
in someone else's neighborhood," says Shanley.
The Edison Electric Institute funded a study on
underground transmission lines in 2004. The report
concluded that such technologies cost about 10 times that
of overhead power lines. And while underground lines
suffer a third of the outages as overhead ones, they take
twice as long to repair. Specifically, undergrounding is
about $1 million a mile. And the obvious question is who
will pay the price of installing that infrastructure?
The utility sector, by-and-large, says it is willing to
ante up at least the amount of what it would cost them to
go above ground. In fact, it says that about half of the
money it has spent constructing transmission lines in the
last decade has gone toward undergrounding.
One of the major costs involved with burying power
lines is the need to dig trenches. If, however, there is
new residential or commercial construction, the effort
could accommodate other utilities such as phone and cable
companies. The costs could then be shared. The cost is
oftentimes split among customers, developers and
utilities. In the end, though, it is consumers who
ultimately pay through higher taxes or higher rates.
Highest Costs
Lines above the ground come into contact with trees,
high winds, rain and ice storms. But, such wires are much
easier to repair because they can be visually inspected
whereas underground lines require special equipment and
crews to locate a fault and to fix. That takes more time
and money. At the same time, water can seep underground,
and particularly after heavy flooding, that can cause
systems to break down.
Florida Power and Light had been resistant to building
underground power lines or converting existing overhead
lines to underground ones. It said that the price tag was
"exorbitant" and that the process to do so was too
invasive. In fact, a March 2005 report by the state's
public service commission staff estimated undergrounding
the entire state could cost up to $94 billion -- raising
electric rates by 81 percent for all.
But, the utility has changed its thinking because of
zoning laws in combination with having to endure its fair
share of hurricanes. Altogether, about 37 percent of its
71,000 miles of distribution lines are buried underground.
Of note, 84 percent of its lines built in newly
constructed communities use underground power lines. Going
forward, FPL adds that it will pay a quarter of the cost
to convert overhead lines underground while supporting
municipalities' efforts to win state and federal funding
for future endeavors.
The highest expenses are tied to excavation,
installation and service connection. In some cases,
customers in areas with underground wires will agree to
pay extra to cover the costs of construction. Dominion
Virginia Power, for instance, is required to collect one
dollar a month from residential customers and no more than
$5 a month from business customers. The money is escrowed
and used to covert overhead power lines to underground.
"Underground distribution lines will improve the
potential for reduced outage interruption during normal
weather, and limit the extent of damage to the electrical
distribution system from severe weather-related storms,"
says Duke Power, in the institute's report. "However, once
an interruption has occurred, underground outages normally
take significantly longer to repair than a similar
overhead outage."
But there are other variables that businesses and
communities take into consideration: reduced motor vehicle
accidents, less economic harm as a result of fewer outages
and increased property values. And utilities enjoy other
advantages, too: fewer greenhouse gas emissions are
released, the efficiency of the system is increased and
trees do not need to be trimmed to avoid power lines --
all because of undergrounding.
The technologies to build underground lines are also
getting better and cheaper. Horizontal directional
drilling allows conduits to be placed underground without
opening trenches. Similarly, high-voltage insulated
underground cables are proving to be more durable while
cable trenches located in sidewalks and covered by
"pavers" are supposedly easy to remove and allow for
simple maintenance.
Cloudy Projections
Some utilities are embracing the potential trend.
Pacific Gas & Electric just installed two underground
systems. The first is a 230 kilovolt transmission line at
a cost of $221 million. All but three miles of the 27-mile
Jefferson-Martin are underground. The second -- the
Potrero-Hunters Point Cable -- is a 115 kilovolt
transmission line that cost $40 million and spans 2.5
miles.
Meanwhile, ComEd plans to make a $190 million
investment to increase the electric power supply to the
northern portion of the central business district, where
consumption continues to grow. The 345 kilovolt, 12-mile
line will be mostly underground. "Our customers depend on
electricity for their quality of life, and they expect us
to operate, maintain and invest in a reliable electricity
delivery system to keep up with the economic growth of
Chicago," says Fidel Marquez, ComEd's vice
president-external affairs for Chicago operations.
Clearly, it's difficult to make an economic case for
building underground transmission lines. But, communities
are interested in the idea and particularly customers who
will live in newly developed areas where costs can be
shared among various utilities. Indeed, the aesthetical
value along with the possibility of avoiding widespread
blackouts has gained credence in the utility world. The
stumbling block, though, remains over the issue of who
will pay for the advances. And that still clouds the
future of undergrounding.
For far more extensive news on the energy/power
visit: http://www.energycentral.com
.
Copyright © 1996-2005 by CyberTech,
Inc. All rights reserved.
|