If cooling
towers are required, plant might close
Feb 15, 2006 - Asbury Park Press, N.J.
Feb. 15--Can the Oyster Creek nuclear power plant afford to install
costly cooling towers, or would the plant close to avoid the expense?
State environmental officials want towers to be built to preserve
aquatic life from Barnegat Bay, but the plant's operator, AmerGen Energy
Co., said they are costly and unneeded.
At a state Department of Environmental Protection public hearing in
October, Oyster Creek technician Dave Most said he believed AmerGen will
close the site if the state requires cooling towers. "It's not viable as
a business case," he said.
Most is a newly elected township committeeman in Lacey, where the
plant is located.
In a 2004 meeting with DEP officials, managers with Exelon, which
owns AmerGen, said cooling towers, if required, "would cost $25 million
to install and would result in Oyster Creek no longer being financially
viable," according to the DEP.
A recent AmerGen estimate pegged the cost of building cooling towers
at $92.4 million, in 2002 dollars, according to a company document. It
said the cost of the towers will far outweigh the benefits.
Asked if that cost would make the plant unprofitable, Exelon nuclear
communications manager Peter C. Resler said: "That's proprietary
information whether or not we would continue to operate the plant."
At issue is a draft DEP water intake and discharge permit for Oyster
Creek. The DEP prefers that the plant install towers and cut back on 95
percent of the water it draws from Barnegat Bay. But AmerGen officials
don't think towers are needed and say they would actually have a greater
environmental impact because they would release salt into the air.
A nuclear plant with cooling towers releases exhaust heat from its
reactor to the air -- mainly by evaporating water -- instead of
releasing heated water into a body of water, such as Barnegat Bay.
Under the Beach Boulevard bridge spanning the South Branch of the
Forked River, water flows west all day in evident defiance of nature and
tides.
Oyster Creek, which began operating in 1969, withdraws about 1.3
billion gallons of water a day from an intake canal linked to the South
Branch for cooling, according to a DEP fact sheet.
The water intake and discharge system kills millions of small fish,
shrimp and other aquatic species each year, according to estimates cited
by the DEP.
According to AmerGen, previous studies "suggest that Oyster Creek
Generating Station very likely achieves, or nearly achieves," national
standards for reducing losses of aquatic life trapped against plant
intake screens or entering the plant's cooling water system.
"Our concern about the (current) cooling system is simply that it
kills too many fish," said Bradley M. Campbell, who was DEP commissioner
until he left office Jan. 17. "And it's not a concern limited only to
this plant. It's not a concern limited to New Jersey. This has been a
long-standing concern.
"In a state where our recreational and commercial fisheries are worth
billions to our economy, we can't afford to put a fisheries resource at
risk from excessive fish kills caused by these structures," he said.
The DEP also has given AmerGen the option of upgrading its current
system and restoring wetlands. But New Jersey and five other Northeast
states have asked a federal appeals court to toss out part of a U.S.
Environmental Protection Agency regulation allowing power plants to
restore wetlands in lieu of installing cooling towers.
"I take a skeptical view as to the extent to which mitigation
(wetlands restoration) can offset fish kills associated with cooling
structures, but it may be that AmerGen or other applicants will be able
to make their case on that issue as the record's developed," Campbell
said.
In the early 1990s, the DEP backed off from demanding that Public
Service Electric & Gas Co. build cooling towers to replace the once-
through cooling system at its Salem 1 and 2 nuclear reactors on Delaware
Bay. A once-through system uses water once and then discharges it into a
water body.
Instead, the company was allowed to embark on open space preservation
and wetlands restoration projects that are still criticized by
environmental activists.
"Nine-tenths of the environmental groups never supported mitigation
in place of best available technology at Salem," said Jane Nogaki of the
New Jersey Environmental Federation. Nor would they support it at Oyster
Creek, she added.
"The plant's once-through cooling is continually killing fish,"
Nogaki said. "Mitigation can be used to make up for the past, but it
can't be used as a bank for future losses."
"We got some nice bird habitat out of the deal" on Delaware Bay, said
Thomas P. Fote, legislative director for the Jersey Coast Anglers
Association. "I don't think it did much for the fish."
By Todd B. Bates and Kirk Moore. This story includes material from
previous Press stories and the Associated Press.
© Copyright 2006 NetContent, Inc. Duplication and
distribution restricted.Visit http://www.powermarketers.com/index.shtml
for excellent coverage on your energy news front.
|