Kewaunee nuclear
employee accused of falsifying Ohio reports
Feb 1, 2006 - Milwaukee Journal Sentinel
Author(s): Thomas Content
Feb. 1--A nuclear power plant employee indicted on suspicion of
misleading federal regulators about the condition of a troubled Ohio
plant later moved to Wisconsin, where he worked for the past three years
at the Kewaunee nuclear plant.
David Geisen of De Pere is scheduled to be arraigned this afternoon
in federal court in Toledo, Ohio, on five charges of falsifying reports
to the Nuclear Regulatory Commission. He is one of three people who
worked for the Davis-Besse nuclear plant who have been indicted on
charges of filing reports that concealed problems at the plant outside
Toledo.
Geisen was part of a group of Davis-Besse workers who left
FirstEnergy in fall 2002 as part of management changes that resulted
from an intensive NRC investigation of problems at the plant. A
spokesman for FirstEnergy Corp., which owns Davis-Besse, said he
couldn't comment on the circumstances surrounding Geisen's departure
from FirstEnergy.
Geisen was hired as nuclear oversight manager at the Kewaunee nuclear
power plant in January 2003, said Arlene Datu, a spokeswoman for
Hudson-based Nuclear Management Co.
Nuclear Management was formed more than five years ago to run nuclear
plants in the upper Midwest, including the Kewaunee and Point Beach
plants.
Geisen continued to work at Kewaunee after the reactor was sold in
July to Dominion Resources Inc. of Richmond, Va. Joe Reid, a Dominion
spokesman, said Geisen was barred from continuing to work at Kewaunee.
The NRC on Jan. 4 imposed a five-year ban preventing Geisen from working
in any reactor or other facility regulated by the commission.
Geisen's lawyer, Richard Hibey of Washington, D.C., said he will seek
to have Geisen cleared of the charges in a jury trial.
"A fair-minded review of all of the evidence compels the conclusion
that he did not knowingly make false statements to the NRC," Hibey said
in an e-mailed statement.
While at Kewaunee, Geisen served first as manager of nuclear
oversight until March 2005, when his job was changed, Datu said. That
change took place during a prolonged shutdown of Kewaunee to address
several safety concerns raised by regulators.
The Davis-Besse nuclear plant was shut down for two years after
inspectors discovered a football-size hole inside the reactor's vessel
head, or cover. Leaking boric acid had caused a hole, and a plant
accident was barely averted.
The NRC and federal Justice Department indictment contend that
Geisen, then Davis-Besse's engineering manager, and other workers at
Davis-Besse gave incomplete, misleading and false information concerning
the condition of the vessel head and the nozzles inside it, after NRC
inspectors raised concerns that plants such as Davis- Besse might have
leaks.
If that information had been disclosed earlier, the plant would have
been shut down sooner, officials said.
After the plant was shut for refueling in February 2002, the hole
inside the reactor vessel head was discovered -- a problem so severe
that many nuclear experts have called the incident the nuclear
industry's biggest near-miss since the Three Mile Island accident in
1979.
The indictment was filed on the same day that the Justice Department
announced a settlement with Davis-Besse owner FirstEnergy Corp., which
agreed to pay $28 million to settle charges against it. FirstEnergy also
filed papers accusing its former employees of misleading regulators.
Other indicted former Davis-Besse workers, including both a plant
employee and a contractor, entered not guilty pleas last week, and
Geisen is expected to do the same today.
In a statement released after the indictment, Hibey said, "We will
defend this case vigorously and fully expect that when that jury
considers all the evidence, it will exonerate Mr. Geisen completely."
Hibey also said in the statement that "The allegation . . . that Mr.
Geisen was involved in a 'scheme' to mislead the NRC and to hide
significant safety issues in order to keep Davis-Besse open for an
additional month and a half is unsupported by facts and contradicts
logic."
The boric acid leaking problem in reactors such as Davis-Besse
resulted in a more rigorous review of reactor vessel heads every time
nuclear reactors of the same design, including Wisconsin's three
operating reactors, were shut down for refueling.
To avoid the costs and extra time out of service associated with
these reviews, the owners of both the Kewaunee and Point Beach nuclear
plants have replaced their vessel heads in the last two years, at a cost
of $72 million.
© Copyright 2006 NetContent, Inc. Duplication and
distribution restricted.Visit http://www.powermarketers.com/index.shtml
for excellent coverage on your energy news front.
|