State of New Jersey presses
nuclear concern
Feb 21, 2006 - The Record, Hackensack, N.J.
Author(s): Bob Ivry
Feb. 21--The state has "serious concerns" about safety at Oyster
Creek, the nation's oldest operating nuclear power plant.
Lisa Jackson, New Jersey's acting environmental commissioner, wants
the Nuclear Regulatory Commission to hold a public hearing on those
concerns before it rules on the plant's license renewal application.
Jackson threatened to hold her own hearing if the federal agency
declines to comply.
The NRC, which has sole authority over relicensing, and Exelon, the
Illinois-based energy giant that owns Oyster Creek through a subsidiary
called AmerGen, oppose a hearing. They argue that the state is worried
over nothing.
Jackson's demand falls short of expressing outright opposition to
relicensing -- New Jersey officials have no say in the NRC's final
decision -- but it nevertheless puts the state in the same corner as a
coalition of environmental and citizen groups. That coalition has
adopted the name STROC -- Stop the Relicensing of Oyster Creek -- and
has enlisted the pro bono aid of the Rutgers Environmental Law Clinic to
help it wedge itself into the NRC's years-long and sometimes opaque
license renewal proceedings.
Oyster Creek's operating license expires in 2009, but because renewal
takes years, Exelon submitted a relicensing application last summer. If
approved, it would keep Oyster Creek open until 2029 -- a total of 60
years. The reactor came online in 1969.
The outcome has national implications. Many of the country's nuclear
plants, built in the late 1960s and 1970s, are nearing the end of their
license periods, and the NRC has approved all 39 renewal applications it
has decided on so far. For the first time since the Three Mile Island
accident in 1979, U.S. utilities are planning to build new reactors.
Both the state and STROC have filed what the NRC calls "contentions"
-- essentially, objections based on specific problems with the plant --
to try to force the federal agency to consider their concerns when
ruling on the plant's application.
So far, lawyers for both the NRC and Exelon have challenged those
contentions in an effort to avoid delay in the relicensing process.
"I find it curious that the NRC lawyers actually aggressively try to
exclude citizens from the process," said Richard Webster, staff attorney
at the Rutgers clinic.
Critics of the plant, nine miles south of Toms River, say the
agency's criteria for relicensing are too narrow.
"We look at two things," NRC spokeswoman Diane Screnci said. "Whether
[plant operators] have programs in place to manage aging equipment and
whether continued operation would cause damage to the environment."
A three-judge panel is expected to rule on the contentions by Feb.
28.
At issue is a layer of metal less than an inch thick. It protects the
inside of the reactor's reinforced concrete containment area, called the
drywell.
In the event of a nuclear disaster, the metal may be the only barrier
keeping deadly radiation from seeping to the outside. It also provides
structural support for water and steam hoses and control cables that run
in and out of the reactor core.
In 1980, Oyster Creek inspectors discovered corrosion on the liner,
near its base, in a place where a sand bed was used to support the liner
and keep it from buckling.
Water had leaked out of cracks in the reactor vessel head during the
plant's biannual refuelings and had collected in the sand.
When technicians hunted for the cause of the water buildup, they
found that drains installed when the plant was built in the 1960s were
blocked with construction debris. They cleared the debris, scooped out
the sand and applied a layer of epoxy over the corrosion.
Technicians continue to monitor the corrosion with ultrasonic testing
equipment, said Exelon spokesman Peter Resler. In other words, they use
sound waves to gauge the thickness of the metal liner where it's
impossible or impractical to eyeball.
Opponents are unhappy with the frequency of those tests and say they
shouldn't be confined to spots on the metal that have had corrosion
problems.
"If you don't look, you don't find. That's the current motto of
Oyster Creek's operator," said Paul Gunter, director of the reactor
watchdog project of the Nuclear Information and Resource Service in
Washington, D.C.
Gunter fears undiscovered patches of corrosion have weakened the
metal, increasing the likelihood that the structure will buckle under
its own weight. In that case, Gunter said, radiation might be released
and pipes that carry coolant to the core would be crimped or severed by
the collapsing metal.
To avoid any chance of this, Gunter wants Exelon to dig up the
concrete at the base of the metal liner to check for corrosion.
Adding weight to Gunter's argument was an estimate done by the
plant's owner and found in its 2,400-page relicensing application. It
said the barrier had a 74 percent chance of failing if the reactor core
melted or its fuel suffered damage in an accident.
Resler, however, said concern over a meltdown is misplaced.
"If there were that 1 in 10 million chance of a severe disaster with
core damage, any release of radiation would be contained within that
structure by a very thick reinforced concrete shell," Resler said,
referring to the containment vessel.
The concrete varies in thickness from 4 to 6 feet and is reinforced
by steel bars, Resler said.
"It's fully designed to withstand what an anticipated accident would
put on it in terms of pressure," he said.
To force a public hearing, relicensing opponents must apply for
what's called "intervener status." They must prove to the three judges
of the Atomic Safety and Licensing Board Panel that they have a
legitimate "contention" with Exelon's application.
The state's contention also cites what it calls the vulnerability of
the plant to an aircraft attack and a concern that Exelon relies on a
separate company for emergency backup power. Lawyers for both the NRC
and Exelon argued that all the challenges were "inadmissible" on the
grounds that they were "outside the scope of a renewal proceeding"
because they failed "to establish that a genuine dispute exists on a
material issue of law or fact."
"The NRC is renowned as being a hostile forum for citizens," said
Webster of Rutgers. "It's very hard to get information. It's very hard
to really meaningfully participate in the decision-making process."
On Jan. 31, however, a team of NRC technicians discussed in a public
conference call their concern that the metal drywell liners of boiling
water reactors, like Oyster Creek, ought to be examined for corrosion
whenever plant operators apply for license extensions. They were
speaking generally, and not specifically about Oyster Creek. Thirty-four
of the nation's 103 commercial reactors are boiling-water reactors.
"So here you have on the one hand NRC technical people saying
corrosion is a concern, and on the other hand, you have NRC legal people
trying to quash any discussion of corrosion," Gunter said. "It's kind of
schizophrenic."
Six of the 17 reactors owned by Exelon have received 20-year license
extensions. The six Exelon reactors, in Pennsylvania and Illinois, have
approval to remain open until 2029 to 2034.
About half the electricity used in New Jersey is generated by nuclear
power. Oyster Creek supplies electricity to the equivalent of 600,000
households. New Jersey has three nuclear plants in Salem County. The
closest nuclear facility to North Jersey is the pair of reactors at the
Indian Point Energy Center in Westchester County, N.Y., 15 miles north
of the New Jersey border.
Exelon's annual revenues are $14 billion, and Resler called Oyster
Creek "a valued part of our fleet." So much so, Resler said, that Exelon
will spend $20 million on the license renewal.
"That's a major investment," Resler said. "We don't make that
investment unless we think it's a good one. And we do believe it's a
good investment at Oyster Creek."
© Copyright 2006 NetContent, Inc. Duplication and
distribution restricted.Visit http://www.powermarketers.com/index.shtml
for excellent coverage on your energy news front.
|