Doe Releases Filing Instructions For Federal Risk
Insurance For New Nuclear Power Plants
The U.S. Department of Energy (DOE) today released instructions for
companies building new nuclear power plants in the United States to enter
into a Conditional Agreement with DOE to qualify for a portion of the $2
billion in federal risk insurance. Authorized by the Energy Policy Act of
2005 (EPAct), risk insurance is intended to cover costs associated with
certain regulatory or litigation-related delays - which are no fault of the
company -that stall the start-up of new nuclear power plants.
These instructions enable sponsors of new nuclear power plants to begin the
process of addressing certain barriers to building the nuclear generating
capacity necessary to meet our Nation's growing energy needs, DOE Assistant
Secretary for Nuclear Energy Dennis Spurgeon said. Federal risk insurance
provides an mechanism to spur construction of new nuclear power plants that
will help power our economy with advanced technologies and confront global
climate change.
The Conditional Agreement is the first step in the process toward a risk
insurance contract. Sponsors of advanced nuclear facilities, whose
application for a combined Construction and Operating License (COL) has been
docketed by the Nuclear Regulatory Commission (NRC), can enter into a
Conditional Agreement with DOE; however, EPAct authorizes DOE to enter into
contracts with only the first six sponsors that are issued a license and
begin construction of new nuclear facilities and meet all contractual
conditions to provide risk insurance for certain regulatory and litigation
delays in the full power operation of their facility. Up to $500 million in
coverage is available for the initial two licensed plants for which
construction is started and up to $250 million is available for the next
four plants.
Today's instructions on requesting a conditional agreement contract consist
of a five step process that includes: Advance Notification of Sponsor
Intent; Request Submitted by Sponsor; DOE Initial Review of Request; DOE
Processing of Request; and the Execution of the Conditions.
The following is a general explanation of the instructions, information
requirements, and review processes leading to execution of a Conditional
Agreement with DOE.
Step One: Advance Notification of Sponsor Intent: Optional and preferred,
but not required. Advance notification is desirable to provide DOE with
valuable information for planning and managing the review of requests for
Conditional Agreements, and may facilitate the DOE review and processing of
individual requests for a Conditional Agreement.
Step Two: Submission Request for a Conditional Agreement: Includes a letter
by the qualified sponsor to DOE accompanied by the supporting information
and documentation, including a copy of the sponsor's docketed combined
Construction and Operating License Application, the date the NRC docketed
the application, and a summary level schedule identifying key projected
dates of construction, testing, and full power operation. This schedule
should also identify key milestones including major phases of construction,
dates for startup testing period, power escalation schedule, and anticipated
date of full power operation.
Step Three: DOE Initial Review of Request: DOE will conduct an initial
review of the request to determine whether the information as provided by
the Sponsor is adequate. If the provided information in the request is
adequate, DOE will notify the Sponsor that the information is adequate and
begin processing the request.
Step Four: DOE Processing of Request: In processing the request, DOE will
determine the estimated cost of a standby support contract based on the
financial information provided by the Sponsor. The methodology used to
derive the estimated cost of a standby support contract will be consistent
with the methodology described in the final rule on Standby Support for
Certain Nuclear Plant Delays (71 Fed. Reg. 46306, August 11, 2006).
Step Five: Execution of a Conditional Agreement: Once steps three and four
have been met and a review and processing of the request is complete, DOE
will determine whether the requirements for a Conditional Agreement have
been satisfied. DOE will notify the sponsor of its determination and, if the
requirements for a Conditional Agreement have been met, DOE will send a
Conditional Agreement to the sponsor that includes the necessary information
to complete the Conditional Agreement.
Today's announcement follows previous progress through the Department's
Nuclear Power 2010 program, which is a joint government and industry cost-
shared effort to promote the expansion of nuclear power in the United States
and work toward the submission of COL applications for new nuclear plants to
the NRC. In October of this year, Tennessee Valley Authority, the Nation's
largest public power utility and a member of NuStart Energy, a consortium of
nuclear energy companies selected through DOE's Nuclear Power 2010 program
submitted a COL application to the NRC. In November of this year, Dominion,
another Nuclear Power 2010 participant, submitted an application for a COL
for North Anna 3.
To review the instructions for requesting a Conditional Agreement and other
information on federal risk insurance, visit the Office of Nuclear Energy. |