Renewable Energy Portfolios Standards and Transmission
Reliability
Location: New York
Author: George Campbell
Date: Tuesday, December 11, 2007
Renewable energy sources presently provide 10.1 percent of the U.S.
installed electric generation capacity. The flexible dispatch of existing
renewable electric sources of hydroelectric (80 percent of renewable total)
and biomass (10 percent) is contributing to the reliability of the U.S.
electric system much like more conventional forms of generation. However,
planning and operational practices may need to significantly change with new
Renewable Portfolio Standards (RPS) that have been implemented in
twenty-five states and is presently being debated in Congress to make it
mandatory in the other states. Much of the new renewable resource is
expected to be wind generation, which has much more variation in its power
production when compared to other forms of electric generation due to the
variability in wind. One potential solution is to marry demand response (DR)
with wind as an alternative to using other resources, such as combustion
turbines, to ensure reliable electric supply during peak times.
Almost half of the states with RPS require greater than 20 percent of the
electric capacity coming from renewable sources. While each state has
different requirements, most states include solar, wind, biomass, small
hydro projects, landfill gas, and some types of municipal solid waste-based
power plants as qualifying resources. Almost all states are excluding
existing large-scale hydro, which makes up the vast majority of the existing
electric renewable fleet. Therefore, most of the RPS sources will be new
builds and they could make up as much as 20 percent of the U.S. total if
present success is implemented in the other states.
The new RPS sources are likely to present planning and operational
challenges for the electric utility industry. Wind and solar are
intermittent resources which can substantively impact the way a transmission
and generation system is planned and operated.
Figure 1 graphs the typical variability and predictability of renewable
generating resources. Biomass, geothermal and hydro with storage have the
capability for a steady and predictable flow of power for reliability
dispatch and are in the lower left portion of the graph. However, wind is
the resource with the most volatility and uncertainty in predictability.
Figure 1
While all of the resources will have increased penetrations because of
the new RPS, wind is presently the one that is being installed to the
greatest degree and its fundamental economics will probably have it be the
dominant RPS in the future. Because wind represents less than one percent of
the installed U.S. electric system capacity it is not an operational problem
today but will be tomorrow if the United States does not properly plan for
this new resource.
Figure 2 lists the major generation and transmission planning and operations
processes that a wind generator will have to supply for reliability
purposes. Resource planning is a year-ahead process that insures that there
is enough physical generation available for the next year. Most transmission
operators require a 12 percent to 20 percent planning reserve margins to
manage the risk of unplanned generator and transmission outages and
unusually high demands. Because wind typically has a very low correlation
with peak demands in most areas of the United States, only a very small
fraction of its total installed capacity can be included for planning
reserves, if at all. For example, a recent study by the Electric Reliability
Council of Texas (ERCOT), found that 6,300 MW of wind had the same load
carrying capacity as 550 MW of thermal generation for a capacity rating of
only 8.7 percent. In addition power production needs to be ramped up and
down in real-time to manage voltage and frequency. Wind performs these tasks
at a lower level than most other generating resources.
Figure 2
While some reports cite Germany and Spain as having high amounts of wind
generating capacity and no reliability problems, those countries maintain
significantly higher Resource Adequacy Reserves (Planning Reserves) than the
United States. A report that was done for New York State by GE indicated
that their system could take up to 10 percent new wind resources and not
cause reliability problems. However, load growth in their system will reduce
its robustness over time. The solutions to wind's variable production fall
into a combination of the following:
1. Electricity Storage
2. Additional redundant capacity peaking reliability turbines
3. Demand Response
Electricity storage can take place with the following technologies: pumped
hydropower, flywheels, batteries, compressed air, super capacitors and
superconducting magnetic energy. All have significant capital costs and
flywheels are not yet commercial-scale. For wind to be evaluated with the
same capability as hydro with storage capability, the most economical
electric storage technology would have to be included. Because most of these
technologies cost significantly more than wind per installed capacity, the
cost of wind ($/KW) could more than triple. Therefore, there are less
expensive ways of dealing with the variation in wind production—such as the
installation of other, more conventional power plants to produce power when
needed.
For instance, installing combustion turbine (CT) peaking units for Planning
Reserve capacity that wind can't provide would maintain the reliability of
the transmission system. These units cost of approximately $400 - $500/KW
giving them significantly lower capital costs than any of the electric
storage options. However, they will probably require natural gas as a fuel
and additional gas transmission infrastructure will ultimately have to be
built to supply them fuel. Some level of CTs will definitely be part of the
solution.
To solve wind's production variability problem with DR would require more
load shifting on a grand scale. So how much DR capability will be needed? If
the goal is to have 20 percent of the U.S. capacity from new renewable
generation and wind makes up half of that, an additional 90,000 MW of wind
will be needed (as of 2005 there is only 8706 MW of installed capacity).
This assumes that conservation is extremely effective in the United States
and there is no electric load growth over 2006 levels. If DR provides half
of the solution to wind's variable production challenge, we will need an
additional 36,000 MW of load shifting capability, or nearly double today's
37,500 MW of listed capabilities. The actual DR target may be significantly
higher because most DR capability has not been audited in the United States
under the new NERC reliability standards. This reliability audit
verification may be one of the reasons that, in NERC's 2007 Summer
Assessment, only 21,900 MW of DR was reported for interruptible demand and
direct load control.
I believe to increase the DR market size requires the competitive organized
market (COM) practice of requiring default service to be taken by all large
commercial and industrial (C&I) customers under a rate that represents
wholesale electric spot prices (see my article of Sept. 17, 2007).
Residential customers could also have their prices exposed to the spot
market but the infrastructure cost may be too high. If customers are
shielded by rates that do not reflect the volatility in wholesale spot
prices, DR's total potential can't be fully developed. Many COM States now
require large customer default service rates to be based on wholesale
electric market spot energy, capacity and ancillary services prices. This
practice forces all customers to evaluate their DR capability as an
alternative to paying a premium for financially hedging against them. It
makes the DR market potential significantly higher during times that the
transmission and generation system operation is most at risk, at times of
high wholesale spot prices.
I believe the second part of increasing DR capability is to facilitate new
retail services suppliers such as the publicly traded companies EnerNOC,
Comverge and Energy Curtailment Specialists, Inc. They are now providing
comprehensive technology and consulting services along with centralized
customer energy and demand monitoring support to these large customers. As
this COM markets' best practice continues to evolve, vertically integrated
electric utilities (VIEUs) can also implement improved peak-day real time
pricing and encourage these new service providers to bring the same economic
benefits to their customers.
UtiliPoint's IssueAlert(SM) articles are compiled based on
the independent analysis of UtiliPoint consultants. The opinions expressed
in UtiliPoint's IssueAlert articles are not intended to predict financial
performance of companies discussed, or to be the basis for investment
decisions of any kind. UtiliPoint's sole purpose in publishing its
IssueAlert articles is to offer an independent perspective regarding the key
events occurring in the energy industry, based on its long-standing
reputation as an expert on energy issues. © 2004, UtiliPoint International,
Inc. All rights reserved. This article is protected by United States
copyright and other intellectual property laws and may not be reproduced,
rewritten, distributed, redisseminated, transmitted, displayed, published or
broadcast, directly or indirectly, in any medium without the prior written
permission of UtiliPoint International, Inc.
|