Renewable Energy Portfolios Standards and Transmission Reliability



Location: New York
Author: George Campbell
Date: Tuesday, December 11, 2007


Renewable energy sources presently provide 10.1 percent of the U.S. installed electric generation capacity. The flexible dispatch of existing renewable electric sources of hydroelectric (80 percent of renewable total) and biomass (10 percent) is contributing to the reliability of the U.S. electric system much like more conventional forms of generation. However, planning and operational practices may need to significantly change with new Renewable Portfolio Standards (RPS) that have been implemented in twenty-five states and is presently being debated in Congress to make it mandatory in the other states. Much of the new renewable resource is expected to be wind generation, which has much more variation in its power production when compared to other forms of electric generation due to the variability in wind. One potential solution is to marry demand response (DR) with wind as an alternative to using other resources, such as combustion turbines, to ensure reliable electric supply during peak times.

Almost half of the states with RPS require greater than 20 percent of the electric capacity coming from renewable sources. While each state has different requirements, most states include solar, wind, biomass, small hydro projects, landfill gas, and some types of municipal solid waste-based power plants as qualifying resources. Almost all states are excluding existing large-scale hydro, which makes up the vast majority of the existing electric renewable fleet. Therefore, most of the RPS sources will be new builds and they could make up as much as 20 percent of the U.S. total if present success is implemented in the other states.

The new RPS sources are likely to present planning and operational challenges for the electric utility industry. Wind and solar are intermittent resources which can substantively impact the way a transmission and generation system is planned and operated.

Figure 1 graphs the typical variability and predictability of renewable generating resources. Biomass, geothermal and hydro with storage have the capability for a steady and predictable flow of power for reliability dispatch and are in the lower left portion of the graph. However, wind is the resource with the most volatility and uncertainty in predictability.



Figure 1



 

While all of the resources will have increased penetrations because of the new RPS, wind is presently the one that is being installed to the greatest degree and its fundamental economics will probably have it be the dominant RPS in the future. Because wind represents less than one percent of the installed U.S. electric system capacity it is not an operational problem today but will be tomorrow if the United States does not properly plan for this new resource.

Figure 2 lists the major generation and transmission planning and operations processes that a wind generator will have to supply for reliability purposes. Resource planning is a year-ahead process that insures that there is enough physical generation available for the next year. Most transmission operators require a 12 percent to 20 percent planning reserve margins to manage the risk of unplanned generator and transmission outages and unusually high demands. Because wind typically has a very low correlation with peak demands in most areas of the United States, only a very small fraction of its total installed capacity can be included for planning reserves, if at all. For example, a recent study by the Electric Reliability Council of Texas (ERCOT), found that 6,300 MW of wind had the same load carrying capacity as 550 MW of thermal generation for a capacity rating of only 8.7 percent. In addition power production needs to be ramped up and down in real-time to manage voltage and frequency. Wind performs these tasks at a lower level than most other generating resources.



Figure 2



While some reports cite Germany and Spain as having high amounts of wind generating capacity and no reliability problems, those countries maintain significantly higher Resource Adequacy Reserves (Planning Reserves) than the United States. A report that was done for New York State by GE indicated that their system could take up to 10 percent new wind resources and not cause reliability problems. However, load growth in their system will reduce its robustness over time. The solutions to wind's variable production fall into a combination of the following:

1. Electricity Storage
2. Additional redundant capacity peaking reliability turbines
3. Demand Response

Electricity storage can take place with the following technologies: pumped hydropower, flywheels, batteries, compressed air, super capacitors and superconducting magnetic energy. All have significant capital costs and flywheels are not yet commercial-scale. For wind to be evaluated with the same capability as hydro with storage capability, the most economical electric storage technology would have to be included. Because most of these technologies cost significantly more than wind per installed capacity, the cost of wind ($/KW) could more than triple. Therefore, there are less expensive ways of dealing with the variation in wind production—such as the installation of other, more conventional power plants to produce power when needed.

For instance, installing combustion turbine (CT) peaking units for Planning Reserve capacity that wind can't provide would maintain the reliability of the transmission system. These units cost of approximately $400 - $500/KW giving them significantly lower capital costs than any of the electric storage options. However, they will probably require natural gas as a fuel and additional gas transmission infrastructure will ultimately have to be built to supply them fuel. Some level of CTs will definitely be part of the solution.

To solve wind's production variability problem with DR would require more load shifting on a grand scale. So how much DR capability will be needed? If the goal is to have 20 percent of the U.S. capacity from new renewable generation and wind makes up half of that, an additional 90,000 MW of wind will be needed (as of 2005 there is only 8706 MW of installed capacity). This assumes that conservation is extremely effective in the United States and there is no electric load growth over 2006 levels. If DR provides half of the solution to wind's variable production challenge, we will need an additional 36,000 MW of load shifting capability, or nearly double today's 37,500 MW of listed capabilities. The actual DR target may be significantly higher because most DR capability has not been audited in the United States under the new NERC reliability standards. This reliability audit verification may be one of the reasons that, in NERC's 2007 Summer Assessment, only 21,900 MW of DR was reported for interruptible demand and direct load control.

I believe to increase the DR market size requires the competitive organized market (COM) practice of requiring default service to be taken by all large commercial and industrial (C&I) customers under a rate that represents wholesale electric spot prices (see my article of Sept. 17, 2007). Residential customers could also have their prices exposed to the spot market but the infrastructure cost may be too high. If customers are shielded by rates that do not reflect the volatility in wholesale spot prices, DR's total potential can't be fully developed. Many COM States now require large customer default service rates to be based on wholesale electric market spot energy, capacity and ancillary services prices. This practice forces all customers to evaluate their DR capability as an alternative to paying a premium for financially hedging against them. It makes the DR market potential significantly higher during times that the transmission and generation system operation is most at risk, at times of high wholesale spot prices.

I believe the second part of increasing DR capability is to facilitate new retail services suppliers such as the publicly traded companies EnerNOC, Comverge and Energy Curtailment Specialists, Inc. They are now providing comprehensive technology and consulting services along with centralized customer energy and demand monitoring support to these large customers. As this COM markets' best practice continues to evolve, vertically integrated electric utilities (VIEUs) can also implement improved peak-day real time pricing and encourage these new service providers to bring the same economic benefits to their customers.

UtiliPoint's IssueAlert(SM) articles are compiled based on the independent analysis of UtiliPoint consultants. The opinions expressed in UtiliPoint's IssueAlert articles are not intended to predict financial performance of companies discussed, or to be the basis for investment decisions of any kind. UtiliPoint's sole purpose in publishing its IssueAlert articles is to offer an independent perspective regarding the key events occurring in the energy industry, based on its long-standing reputation as an expert on energy issues. © 2004, UtiliPoint International, Inc. All rights reserved. This article is protected by United States copyright and other intellectual property laws and may not be reproduced, rewritten, distributed, redisseminated, transmitted, displayed, published or broadcast, directly or indirectly, in any medium without the prior written permission of UtiliPoint International, Inc.