Getting that Alaska Natural Gas Pipeline built has
been a daunting process. The political and financial
impediments have kept the project delayed for years. But
now, Gov. Sarah Palin submitted a new plan that she says
could prompt construction by next spring.
|
Ken Silverstein
EnergyBiz Insider
Editor-in-Chief |
The $30 billion project has been derailed for 25
years. The pipeline would be a 3,400-mile undertaking
that would send 4-5 billion cubic feet per day from
Alaska's North Slope to the Lower 48. The fields where
the gas is found hold 35 trillion cubic feet of known
reserves and would undoubtedly help serve America's
energy needs. Some experts say the region holds even
more natural gas resources.
The natural gas and the oil have been separated
during processing and the gas has subsequently been
re-injected into the ground in the Alaskan fields in an
effort to keep the crude flowing. Now it's just waiting
to be tapped and used by electric generators, but the
transportation costs to get it to the Lower 48 are high.
To bring the pipeline to fruition, federal lawmakers
have offered loan guarantees and other incentives.
Earlier offers by Alaska officials, however, were
considered generous to major producers that own the
leasing rights: BP, ConocoPhillips and ExxonMobil. That
prior proposal, offered by the former Gov. Frank
Murkowski who lost a bid for re-election, never got
voted on by the state legislature.
Now, Gov. Palin, who signed legislation in May to
provide $500 million in matching funds to the winner of
the license, has opened the application process and
producers have until Oct. 1, 2007 to respond. Their
applications must detail the pipeline's route, the
markets it will serve and how the project would get
built on time and on budget. The package also provides
other incentives that include tax exemptions for those
producers who physically ship their product to market.
While the oil giants that are the North Slope's lease
holders are non-committal, other producers such as El
Paso Corp. have expressed interest. Still, no one is
predicting just how many applications will arrive by the
October deadline. "We are trying to remove as many risks
to the builders as possible, and create stability and
predictability," says Marty Rutherford, Alaska's deputy
commissioner of the Department of Natural Resources. If
all goes well, the administration there says that
construction could begin next May.
Despite the aversion by BP, ConocoPhillips and
ExxonMobil, Gov. Palin says that each will still be a
part of the policymaking process. Those companies may
choose to refrain from ownership positions. But she says
that they will certainly want to supply natural gas to
the Lower 48 and will therefore have a direct interest
in ensuring the line gets built. Indeed, at least BP and
ConocoPhillips have said publicly they will stay
involved and, in fact, have not given up on ownership
rights. ExxonMobil, however, has been the most resistant
and has said that Alaska repeatedly changes the rules in
the middle of the game.
"The company agrees that development of Alaska's
North Slope gas resources is important to the state and
the nation, and we're trying to find a best path forward
to make it happen," says ConocoPhillips' VP of Alaska
North Slope Gas Development Brian Wenzel.
Long Road
The pipeline was originally authorized by the Federal
Energy Regulatory Commission under the Alaska Natural
Gas Transportation Act that went into effect July 1,
1979. Construction began soon after but stopped in the
early 1980s, largely because of the availability of
low-cost Canadian gas. Developers have spent more than
$125 million studying the project.
Now, conditions are ripe. For starters, the price of
natural gas has remained relatively high -- above the
$3.25 floor that producers have said they would need to
offset the risks associated with the 10-year project.
And Alaska, which would be making a hefty initial
investment, would do well too. It would reap millions of
dollars in new tax revenues associated with the effort
and hundreds of new jobs for state residents.
Congress has said it wants to promote the development
of natural gas resources in Alaska. It had previously
authorized loan guarantees that would require the
government to pick up 80 percent of the first $18
billion if the project should not be completed.
Furthermore, state and federal agencies have put the
project on the "fast track." FERC, in fact, has 20
months to review the deal once it gets the paperwork.
"We are under mandate to streamline the processes," says
Robert Cupina, a deputy director at FERC.
While the major oil companies have found the current
governor's proposal to be unattractive commercially,
reaction from those in Alaska natural gas circles
appears to be favorable. The overriding theme is that it
is probably a good thing if the same parties who would
supply the natural gas pipelines do not own them as
well. Stakeholders there want competing bids, although
they admit to being nervous about the number of
applications they will receive.
"This stands in mark contrast to the effort that
preceded this, in that this is open," says Jim Whitaker,
chairman of the Alaska Gasline Port Authority, in a
prior news story. "It's understandable. The rules are
straightforward. There are incentives. A number of
rationales that will lead to a pipeline being built and
all participants all would be competitors, have an
opportunity to compete. That's the way it should be."
The proposed Alaska natural gas pipeline has been on
a long roller coaster ride. Hopes shot up a couple years
ago as generous incentives were offered. But they
ultimately sank. Now, that same optimism is pervasive
with a new set of inducements that are less favorable to
Big Oil but more appealing to other producers. State
leaders will find out soon enough whether this tack pays
off. Under any circumstance, the ultimate goal of any
future pipeline is to quench America's thirst for
natural gas.
More information is available from Energy Central:
Natural Gas: America's Untapped Resource,
EnergyBiz, March/April 2006
Building up Gas - Kelliher Calls for Expanded Production,
EnergyBiz, May/June 2006