Consumers have a right to be wary of building new
generation. After all, they were told in the mid 1990s
that the nation was short power facilities and
henceforth "agreed" to a massive build out. Everyone
knows the punch line: Demand sank and so did a lot of
unregulated generation companies that saw their stock
and bond values rapidly tumble.
|
Ken Silverstein
EnergyBiz Insider
Editor-in-Chief |
Now, five years after the worst of it, utilities are
looking pretty good. A rebounding economy has driven up
the demand for power and kept them cranking along. Their
bottom lines, for the most part, are healthy. The
offshoot is that the expected future demand for
electricity and natural gas is expected to keep steadily
rising and necessitate the building of new power
generation.
Today, neither lenders nor utilities will take risks
unless the unregulated generation capacity is either
fully contracted from the get-go or, in the case of
regulated companies, the cost of construction and
production can be passed through to customers.
Regulators, meanwhile, are reluctant to dismiss rate
cases if underlying commodity prices are jumping and
affecting utilities' financial health. All this is
occurring while the topic of global warming has come to
dominate the national roundtable. That will have a
profound effect on what types of generation get built.
"We made the mistake in the 1990s of overstating our
needs," says Tony Earley, CEO of DTE Energy, at Edison
Electric Institute's annual conference in Denver. "The
public may think we want to make investments and then
put them in the rate base."
That may be the perception of some consumers. But it
is not the reality. According to the Energy Information
Administration, the nation needs 50,000 megawatts by
2014 and 258,000 megawatts by 2030. That will cost about
$412 billion. And that need comes atop a projected
decline nationally in electricity reserve margins
through 2015.
Obviously, those projections come in the wake of the
2003 Blackout -- one that cost the economy
multi-millions in lost economic opportunity. The
thinking among many of the utility execs who addressed
Edison's conference was that industry could avert
another colossal failure, but that the solution would be
far less than ideal. Instead of building the needed base
load generation that would be operational much of the
time, they largely felt consumer groups and regulators
would allow them to build a series of smaller plants.
Integrated Approach
Only Southern Co. expressed some degree of optimism.
It uses an "integrated resource planning" model that
relies on early and open dialogue with all stakeholders.
Every three years it forecasts the demand for power in
its service territory and what its future generation
needs might be. The utility is therefore able to get
preauthorized permission to build new plants.
The strategy works. "The southeast is the only area
of the country where the reserves are actually
increasing because we use an integrated approach," says
CEO David Ratcliffe. "You need to certify how much and
what you need. You can't presume when you get ready to
file everyone will understand."
In Southern's case, it has built 35,700 megawatts of
generation since 1988. Most of that has been combined
cycle natural gas plants that are used during peak time
periods when demand is highest. It is now trying to
build a nuclear power plant as well as a demonstration
integrated coal gasification facility by 2010. That
plant would cleanse coal of its impurities before the
emissions would go out the smokestack.
Southern's tack involving integrated resource
planning is the way to go, says John Rowe, CEO of Exelon
Corp. And while the Southeast may be more conducive to
building more generation, the challenge is more daunting
in most of the rest of the country. The nation may need
base load plants, he says. But the political reality is
that there will be a lot of "ad hoc" solutions that will
increase expenses.
Rowe accepts the premise that the industry will have
to invest at least $400 billion in generation in the
coming decades to meet future electricity demand and
that all new plants will be in accordance with a carbon
constrained economy. Such public policy would tend to
push utilities to build renewable energy facilities, as
well as nuclear ones that do not emit any greenhouse
gases. But, he is quick to say that green energy is just
one component of the whole discussion and that the
country still has a ways to go before any utility will
commit the billions needed to construct nuclear units.
The ultimate challenge, therefore, is to look at all
available energy supplies and then to subsequently
explain the constraints to regulators and consumers.
Demand is going up and more generation is needed. At the
same time, the country is backing strict pollution
limits and specifically with regard to greenhouse gas
emissions. If the nation intends to meet its power needs
and do so in a way that is the most environmentally
benign, it can expect its energy costs to rise as a
result.
Will the country embrace these changes? "I am looking
at the future and it doesn't work," says Exelon's Rowe.
"It does not get us the kind of infrastructure we need."
That view is tempered by years of experience. But in
recent times the nation has endured a wide-scale
blackout along with potential threats of environmental
devastation. Consequently, the nation appears to have
softened and become open to new ideas.
To win the battle, it will take lots of investment in
energy research and development along with the capital
needed to build climate-friendly plants. Those choices
include coal gasification, renewable and nuclear
facilities that come at a premium today. The industry
must henceforth work with stakeholders to build a
groundswell of public and financial support. That, in
turn, will lead to newer and more cost effective
technologies, all of which will potentially spur the
commercialization of cutting-edge projects.
More information is available from Energy Central:
Massive Build Ahead - Generation Shortage Looms - An
Executive Summit, EnergyBiz, Sept/Oct 2006
For more on this topic, visit the Energy Central
Generation Technologies Topic Center.
Copyright © 1996-2006 by
CyberTech,
Inc.
All rights reserved.
|