Putting wind on the wires: A Texas tale

by Sandy Smith, Utility Wind Integration Group

Industry experts and advocates have projected that wind could contribute up to 20 percent of U.S. energy supply by the year 2030. One major obstacle for achieving that goal is the inadequacy of the transmission system as it currently exists. Put simply: where wind is, transmission generally isn't.

There are a number of policy initiatives in place or getting underway to address this limitation. Some are nationwide in scope, such as the National Interest Electric Transmission Corridors, which the U.S. Department of Energy is responsible for designating under the Energy Policy Act of 2005. Others have a more regional focus, such as the activities of the Wyoming Infrastructure Authority in identifying, siting, and building transmission to carry energy from areas where wind (along with fossil fuels) is plentiful to other parts of the country.

Texas, which overtook California last year in the American Wind Energy Association's rankings as the state with the most wind capacity, has implemented a plan that could help the state hang on to that title for some time. In 2005, the Texas legislature passed a bill increasing the state's Renewable Portfolio Standard, or amount of electricity which utilities must obtain from renewable resources, to 5000 MW by 2015.

Realizing that the key component for meeting this objective consists of electricity generated in wind-rich West Texas, necessitating upgrades to the transmission grid, the legislature called for the designation of Competitive Renewable Energy Zones (CREZ). The CREZ concept flips the existing transmission planning process around by planning ahead for transmission in wind-rich areas so that when new generation is ready to connect to the grid, the lines are already there.

Texas occupies a unique place in transmission planning circles because roughly 85 percent of its transmission does not cross state lines and is therefore not subject to Federal Energy Regulatory Commission (FERC) regulation. The state's separate grid is controlled by the Electric Reliability Council of Texas (ERCOT), an independent system operator that in essence, operates the state's electricity market. The fact that the state can act on its own on electricity regulation and transmission has facilitated out-of-the-box thinking on how to accommodate the growth of renewable energy.

There is plenty of activity related to wind power project development underway in Texas, and more is to come. According to ERCOT there is 2,992 MW of wind generation currently in operation on their system, with an additional 1,701 MW planned through 2008. This does not include that part of the grid that is not under ERCOT's control. ERCOT reports that there is 2,600 MW of publicly-announced projects in their interconnection queue and almost seven times that number of MW in the queue that has not yet been publicly announced.

On paper, each CREZ is expected to support roughly 1000 MW of generation and the costs for transmission would be paid for by ratepayers. Stakeholders with an interest in how CREZs will be defined and where they will be located had until February to request the Public Utility Commission of Texas (PUCT) to consider them as intervening parties. After considering stakeholder input, the PUCT will rule on July 5 on an unspecified number of CREZ corridors that are not necessarily limited to the ERCOT system. The remaining portion of Texas' transmission is located within the Southwest Power Pool (SPP). The CREZ enabling legislation covers all transmission in Texas, but transmission to support CREZ areas in SPP territory would be subject to SPP tariffs, over which Texas has no jurisdiction. The enabling legislation does not specify who would pay for new transmission in SPP, a matter that will need to be considered.

A number of companies and organizations have expressed interest in the CREZ process, requesting hearings or filing petitions to nominate CREZs. Wind developers such as Horizon Wind Energy, BP Energy North America, and Shell Wind Energy are participating in the process. The wind development community has provided assurances to the State of Texas that wind projects will be put into operation if the transmission is built. Texas Governor Rick Perry announced in October that $10 billion in investment was promised, enough to finance about 10,000 MW of wind plant development.

In addition, several companies have partnered together to form ventures to build merchant transmission for the CREZs. Electric Transmission Texas LLC (ETT), a proposed joint venture between subsidiaries of American Electric Power and MidAmerican Energy Holdings Company, filed on February 27 a transmission proposal with the PUCT for the construction of approximately 1,000 miles of transmission lines to support CREZ development. At the same time, ETT proposed for consideration by the PUCT and ERCOT an additional approximately 900-mile, high-voltage, high-capacity backbone transmission system.

In response to the legislation, ERCOT initiated a study on transmission alternatives for CREZs. Completed in December, the analysis provides an assortment of options based on four geographic areas: the coast, southwest Texas, central-western Texas and the Panhandle. Among the report's findings:

* New bulk transmission lines would be required to support additional wind generation out of the West Texas area.
* The coastal area has a lower capacity factor (a measurement of the use of the installed wind capacity), but the wind output is more consistent with ERCOT's load and the transmission cost is the lowest.
* The Panhandle area has more wind generation resources with high annual capacity factors, but transmission cost is higher and the area is within Southwest Power Pool, not ERCOT.

ERCOT is performing an analysis of the impact of significant additional wind generation on the level of the different ancillary services that it needs to maintain system reliability. In addition, ERCOT has indicated that further analysis of several issues will be needed once a specific set of CREZs is designated by the PUCT and wind developers have indicated specific locations for projects. These additional analyses include reactive support needs, dynamic stability analyses, optimization of the "on-ramps" within the CREZs and analysis of the specific projects or operational procedures needed to mitigate curtailments of existing wind generation.

A lot of work is underway in identifying and ironing out the details, but it is apparent that several certainties are emerging: transmission construction will begin after the CREZ designation is completed and the upfront cost will be paid for by ratepayers. Once the transmission is built, the PUCT is going to watch and see if the mantra "if you build it, they will come" applies to wind power and transmission in Texas.


Sandy Smith is communications coordinator for the Utility Wind Integration Group, an association of utilities and other stakeholders interested in the responsible integration of wind generation into utility power systems. He can be reached at sandy@uwig.org.
 

Copyright © 2007: PennWell Corporation, Tulsa, OK; All Rights Reserved.  To subscribe or visit go to:  http://uaelp.pennnet.com