Duke Energy Corp. may build only one 800-megawatt coal-fired
generator at its aging Cliffside plant in Western North
Carolina, not the two that Duke requested almost two years ago,
the N.C. Utilities Commission ruled yesterday.
The commission
said that Duke, based in Charlotte. failed to prove that it will
need both units to meet increasing consumer demand. The brief
“notice of decision” also indicated that Duke had been
considering putting as much as half of the power generated by a
two-unit facility on the wholesale market.
Duke must also invest 1 percent of its annual retail revenue
from electricity sales in energy efficiency programs, the order
said.
One commissioner, Robert V. Owen Jr., dissented, saying that
the application should have been entirely denied. The commission
said it will release complete details of its decision soon.
A spokeswoman for Duke Energy, Paige Sheehan, said that the
company must see the complete ruling before assessing its
impact.
“There’s not a whole lot we can say in terms of the next
steps,” Sheehan said. “It’s a significant step in our plan for
new generation. Clearly (the commission) recognized there is
growing demand.”
Opponents expressed satisfaction with at least some aspects
of the ruling.
“It is a kind of victory. The glass is certainly half-full,”
said Michael Shore of the North Carolina office of Environmental
Defense.
Others said that even one coal-burning generator will be bad
for the state’s air and add to the greenhouse gases blamed for
global warming, and some wondered whether Duke would find it
cost-effective to build only one unit.
A few noted that Duke Energy’s chief executive, Jim Rogers,
has joined chief executives of nine other major U.S.
corporations to push for a nationwide limit on carbon-dioxide
emissions in order to combat global climate change. They hope
that the required investment in energy efficiency will lead Duke
to abandon the Cliffside project.
“It’s clear to me that if (Rogers) is serious about energy
efficiency, building these coal plants would have sucked all the
air out of the room,” said Stephen Smith, the director of the
Southern Alliance for Clean Energy.
Permission to build the single unit and related
power-transmission facilities at the Cliffside Steam Station is
conditional upon Duke Energy retiring the four existing
100-megawatt units as soon as the new generator is operational,
the commission said.
Duke Energy, with 2.2 million customers in the Carolinas,
first sought a permit for the Cliffside generators in May 2005,
saying that they would be the most reliable, acceptable way of
meeting increasing demand.
Opponents argued — and the company acknowledged — that the
project would lead to more carbon-dioxide emissions, and
complained that Duke Energy didn’t fairly consider adding
capacity through conservation or such renewable fuels as solar
or wind.
Critics were also angered this fall when the company restated
the full project’s cost as $3 billion, 50 percent more than
originally estimated.
Several opponents said they will now shift their attention to
the N.C. Division of Air Quality, which must decide whether to
grant an air-quality permit. That permit must also be approved
by the federal Environmental Protection Agency.
“This is really only the first step in the process for Duke,”
said Gudrun Thompson, an attorney with the Southern
Environmental Law Center. “We are going to be very involved in
fighting the air-quality permit for this plant.”