18 May 2007
Electricity capacity margins are expected to be adequate to ensure
reliable electric service throughout North America this summer, under
normal summer weather conditions, according to Rick Sergel, president
and CEO of the North American Electric Reliability Corporation (NERC).
However, widespread and sustained hot and humid weather could threaten
that reliability. NERC will release this and other conclusions in its
2007 Summer Assessment.
Areas of the greatest concern, which NERC has put on its Summer Watch
List, are:
• Southern California, which relies on large amounts of imported
power, transported across transmission lines that are heavily loaded
during normal operation.
• The Greater Connecticut region, which relies heavily on imported
power; although the addition of 200 MW of demand-reduction measures
since last summer will help the situation.
• British Columbia, which faces the risk of severe flooding that
could damage transmission equipment or require taking equipment out of
service.
Areas with improved conditions since last summer include:
• The Southeast, where utilities invested more than $1.21 billion in
transmission in 2006.
• Boston, where the ability to import electricity has been boosted by
1,000 MW due to two new 345 kV transmission lines running from
Stoughton, Mass., into Boston, which became operational in October 2006
and May 2007 respectively.
• Southwestern Connecticut, which can import 230 more MW of
electricity since a 345 kV transmission line from Bethel to Norwalk was
put into service in October 2006.
• Texas, which has reduced its transmission congestion, allowing it
to reduce the number of less-efficient generating units that must run in
tight reliability situations from seven to one.
Several issues highlighted in NERC's Long-term Reliability Assessment
issued in October 2006 are being addressed. The amount of demand
represented by customer Interruptible Demand and Direct Control Load
Management programs increased since last year by more than 10 percent in
Florida, 13 percent in other parts of the southeastern United States,
and almost 20 percent in the western United States and Canada. Many
regions are studying the interdependence of fuel delivery and
reliability, and improving coordination between fuel suppliers and
generators.
In Nebraska, all 37 transmission lines damaged in December 2006 ice
storms are back in service, six weeks ahead of schedule.
Copyright © 2007: PennWell Corporation, Tulsa, OK;
All Rights Reserved. To subscribe or visit go to:
http://www.omeda.com/cgi-win/poe.cgi?add&p=webedit
|