Thailand's fuel supply woes
A wave of organized and well-attended protests against new coal-fired power
generation projects could become a major hindrance to the diversification of
fuel usage in Thailand's gas-dominated electricity generation sector.
The potential setback for coal use came as delays also occurred in signing
up one anticipated source of new gas supplies.
Rallies were held in September against coal-fired power projects planned by
IRPC and the Babcock & Brown Co-Loxley partnership in Rayong and Samut
Songkhram, respectively.
The opposition could prompt other bidders in the forthcoming round of
independent power producer (IPP) projects to abandon coal-based schemes.
They would be forced to turn to other types of power plants, notably those
run on natural gas, which have attracted less opposition. But the kingdom is
already heavily reliant on gas-fired projects.
The local and environmentalist opposition to new coal-fired power plants as
well as to nuclear energy could mean that Thailand's reliance on natural gas
for power generation could balloon from the current 70% to as much as 90% by
2020 or before.
IRPC and Babcock & Brown Co-Loxley are among the sixty or so local and
international companies pursuing the concessions to install 3,200 megawatts
(MW) of generating capacity from 2012 under the country's second IPP tender.
The 3,200 MW of capacity represents the first in a series of IPP bids
planned in connection with Thailand's revised power supply development plan,
which calls for the installation of at least 32,000 MW of capacity over the
next 15 years.
Thai power demand is projected to grow by 5% to 6% a year, or an average of
1,400 MW a year. Thailand's most recent peak power demand, registered on
March 28, 2007, was 21,896.4 MW.
Within the 32,000 MW of total new capacity, IPP developers are being called
on to build 12,600 MW of plant from 2007 to 2021. This represents 31.75% of
the additional generating plant the kingdom is projected to require over the
next 15 years.
Bids for the country's first IPP tender in more than a decade are due for
submission in October 2007. The Energy Ministry plans to complete the bid
evaluation process by December with a view to clinching the power purchase
agreements by June 2008.
The negative perception of coal held by much of the Thai public dates back
to problems that occurred more than a decade ago, and in particular the
controversy over the high sulfur dioxide emissions produced by the 2,400-MW
Mae Moh lignite-fired complex in Lampang in the 1980s and 1990s. The plant
is owned by the state-run Electricity Generating Authority of Thailand (Egat).
The perceptions remain in spite of the fact that comprehensive air pollution
control and mitigation measures have been implemented since then.
This includes the Baht 7.1 billion ($207.2 million) installation of flue gas
desulphurization units on the ten generators, which absorb more than 90% of
the sulfur dioxide emissions.
These measures mean that the air around Mae Moh is now much better than in
Bangkok in terms of its SO2 content. The annual average is about two
micrograms per cubic meter at Mae Moh compared to five micrograms per cu m
in Bangkok.
Following the Mae Moh controversy there were prolonged and high-profile
protests in Prachuab Khiri Khan province at the time of the first IPP tender
in the mid-1990s. These led to the eventual demise of the Union Power
Development Company's 1,400-MW coal-fired project and Gulf Power
Generation's 734-MW facility.
The two Prachuab Khiri Khan schemes have since been relocated to the Central
Plains and switched from coal use to gas-fired combined-cycle systems.
Egat's Mae Moh plant and the BLCP Power Company's 1,400-MW IPP facility are
the country's only large coal-fired power plants, although there are a
substantial number of smaller coal-fired generating plants developed on a
captive basis or through the small power producer program.
The BLCP Power project was awarded in the first IPP bidding round and,
operating in the highly-industrialized eastern coastal province of Rayong,
contributes about 20% of national power supplies.
IRPC
In the latest development IRPC, which is a subsidiary of the
state-controlled energy company PTT, has already bowed to pressure from
local communities and environmental activists. The opponents had set up a
road blockade to protest against the IPRC's proposed 1,600-MW coal-fired
project.
IRPC president Piti Yimprasert said the company will now not bid in the
second IPP bidding round on the basis of the coal-fired project, due to a
lack of understanding about the firm's policy and the project. But IRPC is
keeping its options open for the third and successive IPP rounds and says
that, ahead of any future tenders, it will involve local residents in all
the processes of project planning and execution, especially relating to the
environmental impact assessment.
IRPC executives also hinted that the company is pondering switching the fuel
source of the proposed second-round project from coal to natural gas. And
Energy Minister Piyasvasti Amranand has weighed in, saying that IRPC should
not build a coal-fired power plant in Rayong as the project site is located
near communities.
He noted that new IPP plants must abide by environmental requirements and
the new constitution, which requires people's participation in projects that
will affect their lives. Power plant builders should review their projects
if there is opposition from residents, the minister added.
Egat is meanwhile pressing ahead with plans to build its own coal-fired
plants, although the utility has been seeking with limited success to
advance the option for many years. Egat governor Kraisri Karnasuta has said
that the company is conducting feasibility studies to find suitable
locations for a number of coal-fired plants, each with 800 MW of capacity,
to come on line between 2014 and 2015 (see PiA 486/12).
Meanwhile in a separate development Thailand's negotiations over a planned
liquefied natural gas (LNG) supply contract with Iran have become bogged
down by inflated gas prices. These have resulted in large part from the
higher development costs now expected at the project on the Pars gas field.
The difficult price negotiations between PTT and a consortium comprising the
National Iranian Oil Company, France's TotalFinaElf and Malaysia's Petronas,
are expected to delay the conclusion of the contract by six months to
mid-2008.
The uncertainty over the contract has also prompted PTT to look in more
detail at other possible LNG deals with countries including Algeria,
Australia, Qatar, and Egypt in case the talks with Iran are delayed further
or collapse.
In July 2006 PTT had signed an in-principle agreement with the Iranian Oil
Ministry for three million metric tons a year of Iranian LNG from 2012, with
a further 2 million mt a year to be supplied from 2014. At that time, both
sides hoped to conclude a contract in June 2007, with contracts to be signed
before the end of 2007.
But PTT executive vice-president Chitrapongse Kwangsukstith said the Pars
group wants to include higher development costs in the selling price, which
has repeatedly prolonged the negotiations. He added, however, that PTT
wanted to see a successful conclusion to the negotiations with Iran.
While a deal has yet to be struck, he noted that PTT will continue to build
an LNG receiving terminal and related facilities in Rayong province at a
cost of $700 million. The facility is scheduled to be completed by the end
of 2010.
Iran has denied that a disagreement on prices has delayed the LNG contract
with PTT. Mohsen Pakaein, the Iranian ambassador to Thailand, said in a
statement that the negotiations have proceeded smoothly. He stressed that he
had not received reliable reports that the talks were facing obstacles.
But he did note that "the process of reaching an agreement in energy talks
was very delicate, complex and requires patience." The ambassador also
emphasized that the project would serve the interests of both countries in
the long term and negotiations would continue without any hindrance due to
mutual goodwill. And in a sign of the increasing concerns over securing new
gas supplies, Chitrapongse indicated in late September that PTT plans to ask
the Vietnamese and Malaysian governments and state energy companies to join
it in seeking to develop the Natuna gas resources in the Indonesian sector
of the South China Sea. He noted that all three countries had expressed
interest in buying gas from the offshore D-Alpha field, which has enormous
estimated gas resources, at more than 50 trillion cubic feet, but has very
high carbon dioxide content at about 70%. Chitrapongse said that PTT had
expressed interest in participating in the project for more than a decade,
but that the prospect had earlier been less attractive because of its high
production costs compared with alternative sources.
He added that a 2,000-kilometer (1,240-mile) pipeline costing more than Baht
100 billion ($3 billion) could link Natuna with PTT's existing and
developing pipeline system in the Gulf of Thailand to allow the delivery of
about 3 billion cu ft of gas a day to the project partners.
Created: October 1, 2007
Platts Power in Asia Power in Asia gives you the best available information
and analysis on Asian opportunities, new projects to bid for, news from the
region, and important news from industry and government contacts.
|