Wind Power -- New Wyoming Plant Generating
Plenty of Interest EVANSTON, Wyo. - Oct 28 - Deseret News (Salt
Lake City)
The idea of alternative energy has been a hot topic recently, especially
with the skyrocketing price of gasoline and other fossil fuels.
But 20 or 30 years ago, few people were interested in developing
environmentally friendly or "green" energy sources.
Gary Tassainer, president of Lehi-based Tasco Engineering, is an electrical
engineer by training, and developing wind power has been his passion for
more than two decades. He said he has been working on high-voltage
electrical systems for about 30 years.
"For me personally, power generation has been my love of life," he said.
"I've spent a good portion of my career trying to get generation projects up
and done."
His firm's wind farm is about 20 miles east of Evanston, Wyo., and sits on
several acres of cattle grazing land just a few miles off I-80.
"We're supposed to be finished Nov. 30, and we'll be pretty close to that,"
said Tassainer.
He expects to begin generating electricity by next spring. The 29- turbine
project covers six parcels of land that are each one square mile, he said.
There is also a 200-megawatt wind farm project about 10 miles to the west
developed by Florida Power and Light and also sells its power to PacifiCorp.
In addition to developing wind power, Tassainer has built electrical
generation systems using natural gas in St. George, Springville and Eagle
Mountain. But he started seriously looking into possibilities for wind in
1998, gathering data, obtaining required permits and researching how to
facilitate the sale of electricity to power suppliers.
"I've worked so hard on this with so many drawbacks and so many setbacks,"
he said. At one point he told his business partner, Tasco business
development director Rick Frandsen, he doubted the project would ever get
done.
"I've spent half my life on it, and we're never going to see it," Tassainer
said. However, he said Frandsen kept encouraging him to move forward and see
it through.
Part of the problem has been bureaucratic red tape because the project is
situated on land that contains part of the historic Mormon Trail. In
addition, other regulations and requirements had to be met before the
project could proceed -- not to mention resistance by local residents who
consider the towers eyesores.
"There have been some public hearings where people have expressed the fact
they didn't want (the wind turbines)," he said. "I've always said, 'Would
you prefer to suck brown smoke or look at these turbines?"'
The wind turbines stand 80 meters tall with rotor blades of varying length,
depending upon the design, and huge cables run from the generator at the top
down the length of the tower into transformers in the base of the unit, then
underground into an electrical substation and eventually into transmission
lines.
"From the ground to the tip of the blade is over 400 feet," Frandsen said.
For the turbines to operate, winds speeds can range from 5 mph up to about
50 mph. Frandsen said if winds are too high, the computer will stop the
blades and "lock out" the turbine.
Also, he said the turbines are silent and have no impact on the land or
livestock.
"(Ranchers) will graze this land. There won't be fences around; the cattle
that graze now are going to graze right up to (the towers)," he said.
Frandsen added the land that is encumbered is the land on which the towers
are constructed.
It takes about 100 workers to construct the project, with about 20 permanent
workers needed to operate the wind farm after completion of all phases.
"And those are good-paying jobs; we're talking 40K and up," Tassainer said.
Though the project is located in Wyoming, Tassainer said he leases some of
the property for his wind farm from Utahns who actually own the land. It
took Tasco almost 10 years to get Phase 1 up and ready to run, but Tassainer
said subsequent phases should now only take about a year to develop.
New power generation
Tasco designed and built the transmission lines that now connect to power
distribution lines owned by Rocky Mountain Power. The majority of the
electricity generated from the project will go to homes and businesses along
the Wasatch Front.
"It's taken a lot of hard work to get here, but we just couldn't be more
proud of a project," said Tassainer.
Initially, the company was incorporated as Tassainer Co., but he changed it
upon realizing the difficulties people had spelling his name. It later
became Tasco Engineering.
The company's current project includes 29 turbines for Phase 1; Phase 2 will
have 38 turbines, with 38 for each subsequent phase -- at least three phases
and likely six. Overall the project could take six more years to complete.
Other than Phase 1, each farm will generate up to 80 megawatts of
electricity. Each turbine is rated at 2,100 kilowatts (which would power 700
homes at full capacity). Phase 1 would power 20,300 homes. Subsequent phases
would power 26,600 houses at full capacity.
"Most wind production facilities are rated somewhere between 30 and 45
percent. But, actually, the highest I've ever seen is like 42 percent," said
Tassainer.
"On an average day, 7,000 homes could get their power just from Phase 1,"
said Frandsen.
Advancing technology
Tassainer said wind technology has made huge improvements over the past
seven to 10 years.
"Quite frankly, until three years ago when we started seeing major increases
in (the prices of) oil and gas, wind has not been as competitive," Tassainer
said. "The technology itself has been a hard technology for utilities to
accept."
He added it has taken some time for power producers to catch up with the
"out of the box" thinking wind power requires.
"PacifiCorp has changed their attitude nearly 180 degrees in the last six
years," Tassainer said.
He attributes the change to the "exceeding pressure" due to the high price
of coal and oil and natural gas.
"Anybody is a fool who doesn't admit that we've got some problems with our
environment," he said. "The global warming deal is real, and people that
don't believe that, they've got their head in the sand."
He conceded that technology is advancing to make fossil fuels burn cleaner,
and nuclear energy could also play a more prominent role in the coming
years.
Tassainer said, "One thing you need to keep in mind is that if all of the
wind in the United States was developed for (electricity) generation, it
would only satisfy 20 percent of the demand."
He said the development of wind power is a supplement to the nation's energy
needs, not a way to eliminate any other particular source.
"Too many people fought the technology because they thought it would be a
replacement, and it just can't."
Costly yet profitable
Tassainer said wind power generation has now become so popular, companies
that manufacture turbine towers cannot keep up with demand, and the waiting
time for new towers is 2009.
He estimated the cost to develop and ultimately build this project at about
$150 million for the first phase, he said. Costs were so high, he said, that
he had to sell his project to Mission Energy, a subsidiary of California
Edison, which supplies electricity to Los Angeles. However, he retained the
rights to develop the electrical system for the project.
Tassainer said the wind energy industry is in its infancy right now, but it
is already feeling the heat of competition from various companies wading
into the industry.
He said in the beginning, landowners were expected to get about
$2,000-$3,000 per turbine for leasing their property, but dynamics have
changed dramatically and so has profitabilty. Today, landowners are "getting
between $7,000 and $8,000 per turbine (annually) if it sits on their
property," said Tassainer. "And those are 20-year leases."
Fruits of labor
"People have spent their careers at petroleum-based power plants, and I took
a major paradigm shift when I moved to a renewable resource 10 years ago,"
said Tassainer.
He said when he talked to utility companies in the initial years about
renewable fuel projects, they "thought I was crazy." He researched the
success some European countries were having developing wind energy.
"Most of the technology comes out of Denmark, then Germany jumped on and
probably the U.S. came along about 15 years ago," said Tassainer.
"It's been phenomenal. (But) a year ago it was depressing," he said.
Tassainer said last year he had a conversation with a neighbor who was a
successful businessman who told him to re-evaluate his plans because he was
spending too much money trying to pursue the wind energy project and
jeopardizing his family's future. He advised Tassainer to return to his base
business and get back to solvency.
In addition, Tassainer's eldest son, who is the company's accountant, also
warned of impending financial ruin if changes weren't made.
After heeding their advice, Tasco was able to right itself and Tassainer was
also able to fund his pet project, albeit a little less aggressively. The
result was finally realized recently when Tasco was able to strike the deal
to complete the wind farm project and find a buyer for the energy it
produced.
Tassainer said for years he was unable to convince anyone to invest in his
dream, but just a few weeks ago he was offered $150 million from a venture
capitalist group to fund his next project.
He said, "I'll consider it."
After years of struggle and significant personal sacrifice, Tassainer said
he is now able to enjoy the fruits of his "labor of love."
At 59, he said he plans to retire in three years knowing that his financial
future and professional legacy will be secure.
"It's just been a dream come true, that's all there is to it," he said.
E-mail: jlee@desnews.com
(c) 2007 Deseret News (Salt Lake City). Provided by ProQuest Information and
Learning. All rights Reserved. |