| Court hears arguments over proposed Muhlenberg
plant
Jul 30 - McClatchy-Tribune Regional News - James Mayse
Messenger-Inquirer, Owensboro, Ky.
Attorneys for the state Natural Resources and Environmental Protection
Cabinet and Thoroughbred Generation attempted to sway the state Court of
Appeals on Tuesday into overturning a lower court ruling that has
effectively blocked the construction of a 1,500-megawatt coal-fired power
plant in Muhlenberg County.
For their part, lawyers for the Sierra Club argued the lower court had ruled
properly to deny Thoroughbred an air emissions permit, saying the proposed
plant's pollution controls were recognized as insufficient by the lower
court judge.
The Court of Appeals will likely issue a judgment within a month. Whether
that ruling is the end of the dispute is an open question, since either side
can appeal.
Peabody Energy wants to build the Thoroughbred Energy Campus near Central
City. Officials announced their intention to build the coal-burning power
plant in 2001, and the state granted the company an air emissions permit in
2002 -- but the Sierra Club appealed the ruling.
In 2005, a hearing officer for what was then called the Environmental and
Public Protection Cabinet recommended the permit application be sent back
for more review, to make sure the plant would use the best available
pollution control technology. In her 300-page report, the hearing officer
also recommended further study to ensure the plant's emissions would not
injure plant and animal life.
One year later, then-Cabinet Secretary LuJuana Wilcher overruled the hearing
officer's recommendations and granted Peabody the permit. The Sierra Club
sued, and a Franklin Circuit Court judge ruled last year the permit should
not have been granted, saying Wilcher's decision was not backed up with
evidence.
The state environmental cabinet then appealed the Franklin Circuit Court
ruling. During much of Tuesday's hearing, the three-judge panel focused on
whether stronger emissions control technology was available when Peabody was
designing the plant.
Attorney Robin Thomerson, one of the lawyers representing the environmental
cabinet, said the burden was not on the cabinet and Peabody to prove the
plant had the best pollution controls.
"When you issue a permit and a challenge comes forward ... the burden of
proof is set by regulation and says the burden of proof is on the challenger
to show the Cabinet made the error," Thomerson said.
The sulfur dioxide scrubbers in the original plan would remove 98 percent of
the pollutant from plant emissions. But the permit process requires
companies that will emit pollutants to utilize the "best available control
technology" to reduce emissions -- and the Sierra Club argued that
technology existed when the plant was being designed that would reduce
sulfur dioxide emissions by 99 percent.
Thomerson said the Sierra Club's petition "did not show a 99 percent rate
was available or achievable." When Judge Joy Moore noted the hearing
officer's report listed several plants that had achieved 99 percent sulfur
dioxide removal, Thomerson said that level of removal was not consistent.
"Many of them worked in the short term but couldn't work in the long term,"
Thomerson said.
Harry Johnson, an attorney representing Thoroughbred, said later that
companies can only use technologies that are "commercially" available.
"There are technologies out there that will work, but it's a two-prong
analysis," Johnson said. "You have to go to the second step: What can (the
technology) achieve in the life of the plant?
"We methodically went through (and found) ... the 99 percent was not
achievable every single day," Johnson said.
"A (best available control technology) limit is something we've got to meet
all the time," Johnson said. "The (state Division of Air Quality) is going
to be knocking on your door when you don't meet that limit."
Vendors asked to bid on the sulfur dioxide scrubbers could not guarantee
they could meet the 99 percent standard, Johnson said.
Sierra Club attorney Sanjay Narayan said the hearing officer's report showed
other plants had eliminated 99 percent of their sulfur dioxide emissions.
Thoroughbred had failed to use "best available control technology" for the
pollutant because other plants had eliminated 99 percent of their sulfur
dioxide emissions while Thoroughbred's plan was to eliminate 98 percent.
"They were commercially available," Narayan said.
When Judge Jeff Taylor asked if a "line" had to be drawn, Narayan said: "The
line has been drawn (on pollution controls): You have to be able to go out
and buy it.
"The whole point of the (best available control technology) requirement is
to make sure (plants) use state-of-the-art technology," Narayan said. " ...
All you have to look at is what ... is commercially available."
When Moore asked if a technology could be considered "commercially
available" if vendors would not guarantee it would consistently meet the 99
percent standard, Narayan claimed Peabody did not ask for a 99 percent
guarantee.
The hearing officer's report says Peabody's bid letter required firms to
submit a system to eliminate 98 percent of sulfur dioxide but made bids for
a system that would eliminate 99 percent optional.
The lack of a vendor guarantee is "not evidence something is not
commercially viable," Narayan said. The 98 percent standard was based on
what other plants had achieved in the past, not on what was commercially
available, Narayan contended.
"The Cabinet never got to the topic of whether it is technologically
feasible," Narayan said.
Thomerson said the hearing officer recommended against issuing the air
emissions permit based on data that became known after Peabody had submitted
its permit application. Such "post-dated" information should not have been
considered, Thomerson said.
"That's what the whole permit process is -- what is available, what is
achievable -- at the time the permit is issued," Thomerson said. " ... At
the time the permit was issued, that was the best available control
technology."
Clayton asked why an analysis hadn't been done on the effect of plant
emissions on surrounding areas. One concern Sierra Club officials have
raised is the proximity of the plant to Mammoth Cave National Park.
Johnson said such a study was not required for the permit.
"You have other regulations that look at the impact of all the other sources
combined," Johnson said. The federal Environmental Protection Agency did not
object to the plant receiving a permit, and the National Park Service
withdrew its objections after emissions controls were upgraded, Johnson
said.
Narayan said the EPA has a limited role in the state's permit process.
The Sierra Club argued emissions from the plant would place the region at
the limit in terms of air quality, which would prohibit development of other
businesses that would emit pollutants as well.
Johnson said Wilcher correctly read the regulation to mean she could only
look at the effect of such "increment consumption" in Muhlenberg County.
"The Cabinet is giving all of that resource to one party," Narayan said.
Public notice about plant emissions should have included information about
areas affected by "increment consumption," Narayan said.
"A state-of-the-art plant, at the end of the day, will only be good for
Kentucky's economy," Narayan said. A plant with the best available pollution
controls would allow for other economic development in the surrounding
region and would reduce respiratory illnesses attributed to industrial
emissions, Narayan said.
Such illnesses don't "cost industry anything, but it costs the state quite a
bit," Narayan said.
After the hearing, Roger Brucker, one of the individuals who filed suit
against the permit with the Sierra Club, said the appellate court's ruling
would have a broad impact.
"I think there are a number of coal plants planned," Brucker said. "If the
Cabinet can (issue permits) on the basis of what was achieved in the past
... anything is possible."
Copyright © 2008 The
McClatchy Company |