Don't Bill Now for New Reactors, Panel Argues
ATLANTA - Dec 24 - Augusta Chronicle, The
Georgia Power Co.'s customers shouldn't pay $1.6 billion for two power
plants before they're built on the site of Plant Vogtle near Waynesboro, say
the public-advocacy staff of the Georgia Public Service Commission.
The staff filed its conclusions late Friday in documents with the
commission. A spokeswoman for the company said its executives would have no
comment until they have had more of a chance to review those documents.
The company is seeking permission to include one-third of the construction
costs in the base rates it charges its customers. Its experts argue in
documents and testimony before the commission that customers would save much
of the financing costs by paying up front.
The five-man commission must decide in March. In the meantime, it asked its
public-advocacy staff for a recommendation.
The staff said the company's idea is a bad one.
"Revenues should only be collected from those ratepayers who are receiving
service, otherwise current ratepayers are forced to subsidize future
ratepayers, and they are forced to pay for assets that are not benefiting
them," writes Tom J. Newsome, the director of utility finance with the
commission.
Mr. Newsome said that the staff assumed many customers would move out of
Georgia Power's service area before the plants begin operation. In that
case, 75-80 percent would lose money or save only an average of 35-40 cents
for every dollar of prepayment.
Georgia Power has argued in documents it filed over the fall that the
financial risks of constructing two power plants next to two existing plants
are reasons for the up-front payment plan. Rating agencies, such as Moody's
and Standard & Poor's, will downgrade company bonds from "A" to BBB because
of the added risk to bond investors during construction, company experts
said.
But commission staffers counter that most electric utilities' bonds have a
BBB rating and that the slight difference in the interest rates for the
lower rating would only amount to a fraction of the total plant cost, now
estimated to be as high as $6.4 billion.
Plus, according to the staffers, if customers could keep the money in their
own pockets instead of paying ahead for the plant, it would make them $570
million richer.
Monday, the former president of Oglethorpe Power Co., Forrest F. Stacy,
filed testimony on behalf of a group of major retailers who are fighting
Georgia Power's prepayment plan proposal.
Oglethorpe, which generates power for electric-membership cooperatives, is
one of the co-owners of Plant Vogtle along with 50 cities. Mr. Stacy said
Georgia Power's customers would face many financial risks if the plants are
not completed as budgeted.
"This is significant because cost overruns were a great problem with Vogtle
units 1 and 2," he said. "Further, delays in the completion of the units
would likely increase the risk of an increase of labor, commodity and
component cost increases."\
THE BACK STORY NUCLEAR REACTORS
BACKGROUND: Georgia Power sought approval from the Public Service Commission
to build two nuclear reactors to augment the two already in operation near
Waynesboro.
PAYING FOR THE PROJECT: Georgia Power would expect to pay as high as $6.4
billion for its share in the plant. The project would double the plant's
generation capacity and add about $12 to customers' monthly power bills. The
company sought permission to include one- third of the construction costs in
the base rates it charges customers.
DEVELOPMENTS: - Late Friday, the PSC public advocacy staff filed an opinion
with the commission that customers should be charged only if they are
receiving service, not "subsidize future ratepayers."
- On Monday, former Oglethorpe Power Co. president Forrest F. Stacy filed
testimony on behalf of a group of retailers who are fighting the pre-payment
proposal.
WHAT'S NEXT: The PSC won't make a final decision until March about the
payment plan.
Originally published by Walter C. Jones Morris News Service.
(c) 2008 Augusta Chronicle, The. Provided by ProQuest LLC.
All rights Reserved. |