| ERCOT is 100 percent over budget on revamp of
Texas electric grid
Nov 27 - McClatchy-Tribune Regional News - Jim Fuquay Fort Worth
Star-Telegram, Texas
The operator of the state's largest electricity grid said it is more than
100 percent over budget and two years behind schedule on its ongoing program
to modernize the transmission system.
The Electric Reliability Council of Texas, which serves about 75 percent of
the state, disclosed in filings Wednesday with the Public Utility Commission
that it expects to spend $660 million implementing a system that divides the
transmission network into thousands of "nodes" rather than the current five
zones. ERCOT also said it doesn't expect to bring the nodal system online
until the end of 2010.
Two influential state legislators said they are unhappy with the news, and
the project could be at risk unless a pending study shows that the expected
benefits outweigh the cost of the overhaul. The nodal system aims to improve
the flow of power across transmission lines, reducing congestion and
lowering prices.
"It's exceptionally disturbing," said Rep. Phil King, R-Weatherford,
chairman of the House Regulated Industries Committee, which oversees the
state's electricity markets. "I don't want to see us strap $660 million on
Texas consumers unless the savings exceed that," he said.
Sen. Troy Fraser, R-Horseshoe Bay, chairman of the Senate Business and
Commerce Committee, called the budget estimate "extremely high and
unacceptable."
A new cost-benefit study of the nodal project is due Dec. 15. A similar
study three years earlier projected $6 billion in benefits and a cost of
$260 million.
In March, ERCOT Chairman Bob Kahn said he was "75 to 80 percent" sure the
program would be completed by the target date of Jan. 1, 2009. By May, ERCOT
said it would be later than that but offered no estimate of when.
The PUC authorized ERCOT to pursue the nodal project in 2003. ERCOT
initially put a $125 million price tag on the development of the system, but
Kahn told Fraser's committee Nov. 18 that money was only to get the program
started. ERCOT's board approved a total cost of $267 million in January 2007
and then raised it to $319 million in January 2008, ERCOT said.
The cost of the nodal system is principally being borne right now by the
state's electricity generators. But those costs eventually are expected to
be passed on to ratepayers.
ERCOT on Nov. 19 asked the PUC to more than double the surcharge, to 38
cents per megawatt-hour, that it needs to pay for the nodal project on an
interim basis. That charge, which it seeks no later than by Feb. 1, would
first be passed along to electricity generators.
The surcharge compares with negotiated wholesale power prices that routinely
average $70 to $75 per megawatt-hour.
Monday, Dallas-based Luminant Generation, the state's biggest electricity
generator, filed an objection to ERCOT's plans, saying it departed from
established procedure and represented an "enormous additional and surprising
burden" to participants in the market. Luminant said it wouldn't have time
to work the unexpected charge into previously negotiated rates.
Wednesday, the Alliance for Retail Markets, which represents several of the
state's electricity retailers, also objected, noting that the generators'
added costs would simply be passed along to retailers.
At the Nov. 18 committee hearing, ERCOT's lack of progress and rising costs
on the nodal project drew criticism from committee members. Kahn testified
that the project was costing $12 million a month, a figure that sparked
sharp questioning. Kahn acknowledged that ERCOT's approach of using a mix of
outside software vendors working on open-ended contracts had led to
problems. He said some vendors were not giving ERCOT their highest priority
and were reluctant to cooperate with other vendors.
"I can't believe you've got cost-plus contracts" that have no set
performance standards, Senate Business and Commerce Committee Vice Chairman
Chris Harris told Kahn. "Why would you do that? This is serious," said
Harris, an Arlington Republican.
Kahn said ERCOT had worked with vendors to improve communication and has
"forced them to step up to the line in the last four or five months."
JIM FUQUAY, 817-390-7552