| FERC approves incentive rates to accommodate 
    renewable energy projects   Feb 08, 2008 -- Federal Energy Regulatory Commission Documents and 
    Publications/ContentWorks
 The Federal Energy Regulatory Commission (FERC) today granted Xcel Energy 
    Services, Inc.'s request for incentive transmission rates as part of its 
    plan for six transmission upgrades to meet state renewable energy generation 
    standards and serve increased power demand in the Upper Midwest.
 
 Xcel, on behalf of Northern States Power Company of Minnesota and Northern 
    States Power Company of Wisconsin (together, NSP Companies), filed proposed 
    modifications to the NSP companies' transmission rate formula under the 
    Midwest Independent Transmission System Operator, Inc's (Midwest ISO) open 
    access transmission and energy markets tariff. The proposed modifications 
    permit two types of incentive rate treatments for the upgrades: recovery of 
    return on 100 percent of prudently incurred construction work in progress (CWIP) 
    and recovery of prudently incurred costs of transmission facilities that are 
    canceled or abandoned for reasons beyond the NSP Companies' control.
 
 The transmission upgrades will help serve renewable energy resources, 
    particularly wind energy. Xcel is looking to build transmission to 
    accommodate between 300 and 700 megawatts of windpower.
 
 "There is a growing interest in, and the capability of developing, renewable 
    resources in the Midwest," FERC Chairman Joseph T. Kelliher said. "We 
    carefully evaluate requests for incentives, and Xcel has met the standard. 
    Xcel's proposal not only will help improve reliability and strengthen the 
    nation's grid system, but provide the necessary links to the expanding 
    renewable market in the region."
 
 The NSP companies are two of Xcel's operating utilities and serve customers 
    in Minnesota, North Dakota, South Dakota, western Wisconsin and part of 
    Michigan's Upper Peninsula. The companies are transmission-owning members of 
    the Midwest ISO. Along with other utilities in the region subject to the 
    Midwest ISO's oversight, the companies have been developing plans to upgrade 
    the regional transmission infrastructure and plan to invest approximately $1 
    billion in six expansion projects to serve their five-state service 
    territory.
 
 The Energy Policy Act of 2005 directed FERC to develop incentive-based rate 
    treatments for transmission of electric energy in interstate commerce. In 
    Order No. 679, as modified by Order No. 679-A, the Commission set out the 
    process under which utilities could seek transmission rate incentives. Under 
    Order No. 679, the proposed incentive rate must also be shown to have a 
    "nexus between the incentive sought and investment being made." Order No. 
    679-A clarified the nexus test is met when an applicant demonstrates that 
    the total package of incentives requested is "tailored to address the 
    demonstrable risks or challenges faced by the applicant." This nexus test is 
    fact-specific and requires the Commission to review each application on a 
    case-by-case basis.
 
 FERC found that the NSP Companies have shown a nexus between the proposed 
    CWIP incentive and their investments in the expansion projects as well as 
    between the proposed abandoned plant recovery and their planned investment. 
    Consistent with Order Nos. 679 and 679-A, authorizing the CWIP treatment and 
    abandoned plant recovery for the projects would enhance cash flow, reduce 
    interest expense, assist with financing and improve credit quality.
 
 FERC conditionally accepted the companies' proposal to modify their 
    transmission rate formula to use projected test year cost inputs, with a 
    true-up mechanism to reflect actual costs.
 
 "Our analysis indicates that the NSP Companies' proposal to switch to 
    forward-looking estimated transmission costs with a true-up mechanism is 
    just and reasonable," FERC said. To provide customers with sufficient time 
    to review revenue requirement information, FERC directed the companies to 
    provide estimated information to customers by Sept. 1 each year, instead of 
    their proposed Oct. 1 date.
 
 The proposed rate incentives and formula rate modifications are effective 
    Jan. 1, 2008.
 
 News Provided By
 
  |