FERC approves incentive rates to accommodate
renewable energy projects
Feb 08, 2008 -- Federal Energy Regulatory Commission Documents and
Publications/ContentWorks
The Federal Energy Regulatory Commission (FERC) today granted Xcel Energy
Services, Inc.'s request for incentive transmission rates as part of its
plan for six transmission upgrades to meet state renewable energy generation
standards and serve increased power demand in the Upper Midwest.
Xcel, on behalf of Northern States Power Company of Minnesota and Northern
States Power Company of Wisconsin (together, NSP Companies), filed proposed
modifications to the NSP companies' transmission rate formula under the
Midwest Independent Transmission System Operator, Inc's (Midwest ISO) open
access transmission and energy markets tariff. The proposed modifications
permit two types of incentive rate treatments for the upgrades: recovery of
return on 100 percent of prudently incurred construction work in progress (CWIP)
and recovery of prudently incurred costs of transmission facilities that are
canceled or abandoned for reasons beyond the NSP Companies' control.
The transmission upgrades will help serve renewable energy resources,
particularly wind energy. Xcel is looking to build transmission to
accommodate between 300 and 700 megawatts of windpower.
"There is a growing interest in, and the capability of developing, renewable
resources in the Midwest," FERC Chairman Joseph T. Kelliher said. "We
carefully evaluate requests for incentives, and Xcel has met the standard.
Xcel's proposal not only will help improve reliability and strengthen the
nation's grid system, but provide the necessary links to the expanding
renewable market in the region."
The NSP companies are two of Xcel's operating utilities and serve customers
in Minnesota, North Dakota, South Dakota, western Wisconsin and part of
Michigan's Upper Peninsula. The companies are transmission-owning members of
the Midwest ISO. Along with other utilities in the region subject to the
Midwest ISO's oversight, the companies have been developing plans to upgrade
the regional transmission infrastructure and plan to invest approximately $1
billion in six expansion projects to serve their five-state service
territory.
The Energy Policy Act of 2005 directed FERC to develop incentive-based rate
treatments for transmission of electric energy in interstate commerce. In
Order No. 679, as modified by Order No. 679-A, the Commission set out the
process under which utilities could seek transmission rate incentives. Under
Order No. 679, the proposed incentive rate must also be shown to have a
"nexus between the incentive sought and investment being made." Order No.
679-A clarified the nexus test is met when an applicant demonstrates that
the total package of incentives requested is "tailored to address the
demonstrable risks or challenges faced by the applicant." This nexus test is
fact-specific and requires the Commission to review each application on a
case-by-case basis.
FERC found that the NSP Companies have shown a nexus between the proposed
CWIP incentive and their investments in the expansion projects as well as
between the proposed abandoned plant recovery and their planned investment.
Consistent with Order Nos. 679 and 679-A, authorizing the CWIP treatment and
abandoned plant recovery for the projects would enhance cash flow, reduce
interest expense, assist with financing and improve credit quality.
FERC conditionally accepted the companies' proposal to modify their
transmission rate formula to use projected test year cost inputs, with a
true-up mechanism to reflect actual costs.
"Our analysis indicates that the NSP Companies' proposal to switch to
forward-looking estimated transmission costs with a true-up mechanism is
just and reasonable," FERC said. To provide customers with sufficient time
to review revenue requirement information, FERC directed the companies to
provide estimated information to customers by Sept. 1 each year, instead of
their proposed Oct. 1 date.
The proposed rate incentives and formula rate modifications are effective
Jan. 1, 2008.
News Provided By
|