| Idaho utility companies, wind developers come to 
    agreement   Feb 23 - McClatchy-Tribune Regional News - Joshua Palmer The Times-News, 
    Twin Falls, Idaho
 A nearly three-year dispute between Idaho utility companies and wind 
    developers has been resolved, according to a statement issued by the Idaho 
    Public Utilities Commission.
 
 The disagreement, which involved three major cases that argued how much it 
    costs to add wind power to the public utility grid, was resolved through 
    discussions between the Idaho Power Co. and Idaho wind farm developers.
 
 Both Idaho Power and the developers said they were satisfied with the 
    ruling.
 
 "This was really a joint agreement between Idaho Power and our wind farm 
    developers,"said Dennis Lopez, corporate communications specialist with the 
    Idaho Power Co. "It was a discussion that lasted two or three years and it 
    certainly was a long and strange journey."
 
 Although Idaho Power was the primary utility in the deliberations, smaller 
    utilities such as the Avista Power Company in eastern Idaho were also a part 
    of the negotiations.
 
 To resolve cost issues, the utility commission established an amount that 
    utilities can assess against wind developers to make up for the costs 
    associated with integrating wind into the power grid. The commission also 
    removed a cap on the size of small-power projects that can qualify for a 
    rate published by the commission.
 
 However, the judgment was not easily reached.
 
 In 2005, Idaho Power asked the commission to suspend small-power wind 
    development so it could study how much it costs the company to provide 
    back-up generation when wind output fluctuates.
 
 The commission denied the suspension, but agreed to decrease the size of 
    small-power projects -- from 10 megawatts to 100 kilowatts.
 
 Later that year, Idaho Power Co. and two other major utilities completed 
    studies to determine wind integration costs.
 
 The utilities and most windfarm developers proposed a settlement that would 
    bring the size limit of projects back up to 10 MW.
 
 Wind developers proposed more certainty to utilities by agreeing to share 
    the cost of buying wind forecasting services, and provide guarantees that 
    their projects would be mechanically able to generate at full output during 
    85 percent of the hours during a month.
 
 "The commission finds that the costs of wind integration are real, not 
    illusory," the commission said in a written statement.
 
 The commission established a tiered-discount for Idaho Power and another 
    utility that increases as more wind is added, but caps the discount so that 
    it can go no higher than $6.50 per MWh.
 
 According to a statement from the utilities commission, one of the wind 
    developers in the case, Exergy Development Group of Idaho, argued against an 
    integration discount saying "the science is in its 'infancy,' and that 
    enough variables and uncertainties exist to make it impossible to determine 
    a fair rate."
 
 Wind-powered electrical generation is gaining popularity in the U.S.
 
 Renewable Energy Systems America Developments has proposed a 185-turbine 
    generation project, called China Mountain, on 9,000 acres west of U.S. 
    Highway 93 between Twin Falls and Jackpot. Power from the project would 
    initially be used by Nevada utilities.
 
 Another energy company has leased BLM land related to a proposed 100-turbine 
    wind farm on Cotterel Mountain in Cassia County.
 
 Joshua Palmer may be reached at 735-3231 or at jpalmer@magicvalley.com
 |