Nuclear Foes Ready for Battle
Feb 20 - The News & Observer
The arguments against nuclear power used to be pretty simple, even if not
universally convincing: The plants are inherently dangerous and doomed to
fail.
But in an era of higher energy costs, nuclear foes hope they can make a case
that has broader public appeal, based on cost and need.
Opponents are preparing to challenge Progress Energy's proposal to add a
second reactor at the Shearon Harris plant in Wake County. They will argue
that there are cheaper options and that growing demand for electricity can
be met with conservation and other efforts.
The Raleigh utility, which submitted a 4,000-plus page application with the
Nuclear Regulatory Commission on Tuesday, disagrees, saying it will need the
new reactor to generate electricity in about a decade.
The cost of a new power plant is not a theoretical debate but a matter of
pocketbook economics. The cost will be covered using utility customers'
monthly payments. And recent cost estimates for power plants are staggering.
"We think that nuclear will sink under its own weight," said Molly Diggins,
North Carolina director of the Sierra Club in Raleigh. "Nuclear is the least
likely option to be built, due to the financial risk."
Florida Power & Light, which is proposing using the same Westinghouse AP1000
nuclear plant as Progress Energy, said recently that a single reactor would
cost $6 billion to $9 billion to finance and build. That's three times more
than industry estimates provided several years ago. Soaring labor and
materials costs have driven up costs.
Progress Energy, still negotiating with Westinghouse, won't publicly
disclose estimates for a new reactor at Shearon Harris until it signs a
contract in about two years. But the company will offer a glimpse of its
budget when it provides Florida regulators an estimate next month for a
proposed Westinghouse reactor in that state.
"It could be the mistake that puts the company out of business," said Jim
Warren, director of N.C. Waste Awareness and Reduction Network. The Durham
group will oppose the proposed expansion at Shearon Harris.
Progress Energy has applied to the NRC for two new nuclear reactors at
Shearon Harris and would build the first reactor by 2020. The company has
not said when or whether it might build a third reactor at the Wake County
site, where one reactor has been in operation since 1987.
The NRC review will focus primarily on safety systems, emergency
preparedness and other compliance. The N.C. Utilities Commission will review
the utility's need for the power plant, as well as its cost.
Progress Energy has said customers' electricity use is growing by about 2
percent a year and will require the construction of a large power plant to
meet demand. The company is looking at expanding conservation programs and
buying power from independent generators of solar power and other renewable
energy sources to curb demand. But it predicts an increasing appetite for
electricity.
"Power plants are not discretionary," said Progress spokesman Rick Kimble.
"You're not reducing the number of children in schools. You're not reducing
the number of homes going up."
But environmental organizations for years have contended that North Carolina
could meet its energy needs without building more large power plants. They
point to California, where electricity consumption remained flat over the
past 12 years as that state embraced conservation and renewables.
But California's electricity costs are 50 percent higher on average than
consumers pay in North Carolina, giving alternatives an edge that they don't
enjoy in this state. The outlook is changing. Global-warming concerns and
rising energy costs resulted in a new state law requiring that 12.5 percent
of electricity come from renewables and efficiency programs by 2021.
Critics dismiss Progress Energy's growth projections as exaggerations
designed to justify the construction of power plants. They point to
projections in the 1970s that four nuclear reactors would be needed at
Shearon Harris. Only one was built.
Last year, the Utilities Commission agreed with opponents and rejected Duke
Energy's bid to build two coal-burning units at the Cliffside Steam Station,
west of Charlotte. The agency permitted the addition of one power plant,
with a ballooning price of $2.4 billion.
Because the cost of concrete, steel and labor are not expected to drop,
escalating estimates for power plants are a boon for advocates of
efficiency.
"The conservation effort potential is so large that getting just a part of
it will eliminate the demand growth of electricity," said John Blackburn, a
retired Duke University economics professor who testifies as an expert
witness in utility cases for environmental groups. "If we do all the
efficiency stuff and then start bringing on renewable resources, we'll see a
decline in the demand for existing power plants."
-----
To see more of The News & Observer, or to subscribe to the newspaper, go to
http://www.newsobserver.com .
Copyright (c) 2008, The News & Observer, Raleigh, N.C.
Distributed by McClatchy-Tribune Information Services. |