| Yucca Mountain Layoffs Imminent, Official Warns   Jan 18 - Las Vegas Review - Journal
 The nation's nuclear waste chief painted a dismal picture Tuesday of the 
    Yucca Mountain Project's future, one that shows 500 layoffs and casts doubt 
    on submitting a license application this summer.
 
 Given the lack of funding to achieve program goals, the first deliveries of 
    77,000 tons of spent nuclear fuel probably will not arrive for entombment in 
    the ridge in 2017 because the repository will not be open, said Ward Sproat, 
    director of the Department of Energy's Office of Civilian Radioactive Waste 
    Management.
 
 "There are going to be significant layoffs, several hundred. They're going 
    to come in waves," he told Nevada's Legislative Committee on High-Level 
    Radioactive Waste.
 
 He later told the committee, led by state Sen. Mike McGinness, R- Fallon, 
    that "at least 500 people would be removed from the program in the next 
    several months, the majority in Nevada, some in New Mexico from Sandia 
    (National) labs."
 
 Of the "65 to 70" workers at the Yucca Mountain site, 100 miles northwest of 
    Las Vegas, where a fence stretches across the entrance to the 
    25-foot-diameter tunnel that loops through the ridge, "basically all are 
    going to be let go in the next 30 days," Sproat said.
 
 Project spokesman Allen Benson said the tunnel's ventilation system was shut 
    down in late December to save on "substantial" electrical bills. The cost at 
    the site for electrical utilities, water and maintenance was $3 million last 
    year.
 
 Sproat said the program staffs some 2,400 full-time positions, but funding 
    cutbacks by Congress of $108 million from the 2008 budget this late in the 
    fiscal year have left him no choice but to pursue layoffs.
 
 The Bush administration requested $494.5 million for the fiscal year that 
    began on Oct. 1. Congress in December approved $386.5 million.
 
 The lack of money probably will push back the Department of Energy's 
    self-imposed June 30 license application deadline.
 
 "I cannot stand behind the June 30, 2008, date," Sproat said about the 
    deadline he had set for submitting a license application to the Nuclear 
    Regulatory Commission. The submission would start what he expected to be at 
    least a three-year review.
 
 Sproat, a political appointee who predicts he will be fired in 12 months 
    under a new administration, said he hopes the license application will be 
    submitted under his watch.
 
 "I am mildly optimistic, cautiously optimistic, that we will get a license 
    application done, but I just don't know yet," he said.
 
 Because of the cutbacks, complete construction of a rail line across 
    east-central Nevada to deliver spent fuel will slip at least two years to 
    2016. As for construction to be under way in October 2009, "that's not going 
    to happen," he said.
 
 "The transportation piece is off the critical path. That's where we took the 
    resources from" to make up for funding reductions, Sproat said.
 
 And, receipt of the waste in 2017, as planned, isn't feasible.
 
 "I would say the 2017 date is not achievable given the funding we've got," 
    he said.
 
 Bob Loux, executive director of Nevada's Nuclear Projects Agency and a 
    critic of the Yucca Mountain Project, said outside the meeting that many of 
    the layoffs will involve contractor personnel whose jobs would end anyway as 
    their roles in the licensing work are completed.
 
 Despite Sproat's direction to scale back aspects of the project, Nevada is 
    not going to soften in its opposition, Loux said.
 
 Late Tuesday, attorneys representing Nevada filed a 30-page appeal with the 
    Nuclear Regulatory Commission that challenged a three-judge panel's 
    rejection of Nevada's challenge that a database of 3.5 million licensing 
    documents should not be certified as complete because crucial studies and 
    safety reports are missing or are works in progress.
 
 Without the documents, Nevada would have difficulty completing its review of 
    the licensing data in the required six-month span, the state said.
 
 "For these reasons, the commission should reverse the ... board's decision, 
    strike DOE's certification and require that DOE may certify only when it has 
    provided all of the core technical documents necessary to permit 'focused 
    and meaningful contentions,' " the appeal said.
 
 At the committee's meeting, Loux described a list of more than 25 concerns 
    about the project, including DOE's repository design being only about 40 
    percent complete and the agency's failure to address fully the potential for 
    terrorism and sabotage in transporting nuclear waste across the nation.
 
 Contact reporter Keith Rogers at krogers@reviewjournal.com or (702) 
    383-0308.
 
 (c) 2008 Las Vegas Review - Journal. Provided by ProQuest 
    Information and Learning. All rights Reserved.
 |