Cleaning the Transmission Process

Location: New York
Author: Ken Silverstein, EnergyBiz Insider, Editor-in-Chief
Date: Tuesday, July 1, 2008
Things are adrift in places around the country. In the Northeast, for
example, the states all have renewable portfolio standards while they also
participate in a regional greenhouse gas initiative, all of which is meant
to cleanse the air and cut global warming pollutants. The dilemma there and
elsewhere is that the transmission line permitting process is tumultuous and
impedes those goals.
Transmission limitations, in fact, are a major barrier to the growth of
renewable energy. The process is meant to be inclusive and to elicit the
views of all stakeholders. Regulators should strive for reasonable
compromises. But if such deals cannot be reached, then they must seek to
achieve the greatest good for the greatest number. Transmission planning
requires it. And so does the federal law.
A recent U.S. Department of Energy study found that wind alone could provide
20 percent of U.S. electricity by 2030. To do so, though, significantly more
investment in transmission is needed. Not only is there is competition among
all types of generators to carry their electrons in the current lines but
new lines are necessary to transport wind resources from the remote
locations where they are most abundant.
"As renewable energy becomes more popular, the request to move these
resources is growing," says John Bear, president of the Midwest Independent
System Operator (ISO,) at the Edison Electric Institute's annual conference
in Toronto. "There is not enough infrastructure" -- a situation that denies
utilities access to lower cost generation.
The Midwest ISO, in fact, has determined that adding 5,000 miles of new
transmission to transport wind from the Dakotas to the New York City area
would result in substantial savings for customers. While the generation and
transmission costs would total $13 billion, the grid operator says that
customers would save about $600 million annually. In the case of New
England, a greater investment in transmission has paid off, enabling prices
to fall in congested areas such as Southwest Connecticut.
But more needs to be done there and elsewhere around the nation. To supply
20 percent of the electric generation market by 2030, the Energy Department
estimates that $60 billion in new wires would be necessary -- something that
the agency says would cut greenhouse gas emissions by 25 percent.
Tough Sell
The objective is to provide reliable, cost-effective and diverse energy
resources to customers. Federal regulators have been given more authority to
site projects. Now it's up to the Federal Energy Regulatory Commission and
the North American Electric Reliability Corp. (NERC) that reports to it to
carry out and enforce compulsory standards that could add greater
certainties and bring innovative projects to the fore.
To succeed, federal regulators advise utilities to begin the process early
-- to meet with all constituents well in advance of filing the initial
paperwork. It's about ensuring that the procedure is inclusive and
transparent. They must understand the legitimate concerns of the
stakeholders involved. It's about building relations with the business
community, environmental groups, landowners, public officials and the press.
"You don't want neighbors to fear the project," says Jane Peverett, CEO of
the BC Transmission Corp., at the Edison meeting. "The process must be fair
and open. The people must have a say and have access to credible third
parties."
In theory, utilities are supposed to have an easier time constructing new
lines. The Energy Policy Act of 2005 sets out to give federal regulators the
ability to override state regulators if key projects are unnecessarily
delayed. It also allows them to provide some financial incentives to entice
investors to spend capital on transmission projects, which have been
considered risky because they can take years to come on line.
As a result, transmission investment has declined in real terms -- adjusted
for inflation -- from 1975 to 1998. While there have been increases since
1998, FERC says that the level is still less than what was invested in 1975.
Over the same time period, however, the demand for electricity has doubled.
That's resulted in a significant decrease in transmission capacity,
requiring new lines get built.
NERC is particularly concerned about Southern California, which depends on
imported power that is transported across heavily burdened transmission
lines. At the same time, the state has increased renewable energy
initiatives and now requires the major utilities there to provide 20 percent
of their power from green sources by 2010.
Those requirements and the current congestion are the reasons behind San
Diego Gas & Electric's effort to build the Sunrise Powerlink transmission
line. It's also the basis for Southern California Edison decision to spend
$15.5 million on transmission and distribution, of which $2.1 billion will
be dedicated to carrying renewable sources.
"The nation has tremendous renewable energy reserves, but the existing
electric transmission system was not designed to tap these new kinds of
generation," says Don Furman, senior vice president at Iberdrola Renewables.
"The good news is that we have the opportunity to solve both problems at
once, while strengthening our economy, the environment, and energy
security."
Investing in infrastructure has always been a tough sell. Private entities
have limited resources and the pay off is often too distant. But the
transmission grid is aging and it needs to be updated and expanded so that
it can meet the expected future demand for power. Doing so would give
utilities the access they need to clean generation while also helping to
increase the reliability of the grid.

Copyright © 1996-2006 by
CyberTech,
Inc.
All rights reserved.
|