| Dominion to build coal-, biomass-fired power plant in
Va.
July 1
Dominion Virginia Power has commenced construction of a 585-megawatt
coal-fired power plant that also will burn up to 20 percent biomass to fuel
its boilers.
The $1.8 billion Virginia City Hybrid Energy Center in southwest Virginia
will be one of the cleanest of its kind, according to the company, which is
a subsidiary of Dominion Resources Inc. Construction is scheduled to take
four years.
Dominion is responding to the projected growth of electricity demand of
4,000 megawatts from its customers by 2017, the equivalent of some 1 million
homes. The Virginia Department of Environmental Quality issued the final air
permits for the plant, June 30.
Contact Waste News reporter Joe Truini at (330) 865-6166 or jtruini@crain.com

To subscribe or visit go to:
http://www.wastenews.com
|