Power plant opponents plan court battle
Jul 8 - McClatchy-Tribune Regional News - Michael Sluss The Roanoke
Times, Va.
Opponents of a new coal-fired power plant in Wise County plan to take their
fight to the courts after failing to persuade state regulators to block
construction of the project.
A coalition of environmental groups said during a news conference Monday
that they will file legal challenges to regulatory rulings allowing Dominion
Virginia Power to build a 585-megawatt plant on a 1,700-acre site near St.
Paul.
The utility company began construction of the $1.8 billion plant last week,
just five days after receiving a permit from the Virginia Air Pollution
Control Board.
"This case has been going on for a while in terms of the administrative and
regulatory proceedings, but the legal fight begins now," said Cale Jaffe, a
lawyer with the Southern Environmental Law Center.
Opponents have argued that the plant will encourage destructive mining
practices and contribute to pollution. But Dominion has cleared two major
regulatory hurdles, getting needed approvals from the State Corporation
Commission and the Air Pollution Control Board.
Opponents said they intend to challenge the legality of the air pollution
permits, largely because they do not require Dominion to curb carbon dioxide
emissions. A state judge in Georgia last week invalidated an air pollution
permit for a planned coal-fired plant in that state because the permit
established no carbon dioxide limits.
The Georgia judge relied on a 2007 U.S. Supreme Court ruling that allows
carbon dioxide to be regulated as a pollutant. But the federal government
has yet to issue such regulations.
Jaffe said a lawsuit challenging the air pollution permits will be filed in
a circuit court, but he has not determined which jurisdiction. Opponents
also plan to go to the Virginia Supreme Court to appeal the SCC's decision
to grant Dominion a certificate of public convenience and necessity for the
plant.
Dominion said any effort to slow construction of the plant would be "an
effort to delay reliable energy and cleaner air for Virginia."
The Wise County plant is scheduled to open in 2012. Dominion officials have
said the plant will be designed so that equipment to capture carbon dioxide
can be added when the technology becomes available. |