The Clock is Ticking: States Rush to Meet Renewable
Portfolio Standard Deadlines
07.02.08 |
Henry Louie, Business Development Manger, 3TIER
|
In April of 2008, Ohio became the 26th state to adopt either a Renewable
Portfolio Standard (RPS) or similar renewable energy goal. The passage of
the Ohio RPS may turn out to be a watershed moment in American energy policy
as there are now more states with renewable energy targets than without -- a
milestone that is not lost on those championing a national RPS. Cautious
energy policy experts point to the fact that no two state RPSs are alike as
an argument against adopting a one-size-fits-all national policy. While it
is not clear if a national RPS will remain in the realm of fantasy,
utilities in 26 states are now faced with the very real task of complying
with state RPSs, with deadlines rapidly approaching.
According to a recently released 2007 study performed by the Lawrence
Berkeley National Laboratory, approximately 60 GW of new renewable resources
– likely predominately wind-based -- will be needed to meet existing state
RPSs in the year 2025. To construct and integrate this significant amount of
generation will require innovative solutions by engineers and planners who
will face a myriad of challenges, including:
* Transmission constraints
* Supply-chain bottlenecks
* Intermittency of renewable generation
* Ambiguity or rigidness in the interpretation of the RPSs.
This article presents a case study of the challenges and approaches taken by
some utilities to overcome these challenges on the road to RPS compliance.
The state of Washington is selected as a microcosm for the study. The
salient aspects of the RPS in Washington are similar to that of many other
RPSs, so relevance to other states is maintained.
A Mandate by the People
In November of 2006, the people of the state of Washington passed Initiative
937. The initiative required large utilities -- those with more than 25,000
customers -- to serve escalating amounts of their load with energy from
renewable resources, beginning with 3 percent in 2012, climbing to 15
percent in 2020. The distinction between energy and capacity in the
initiative is significant, as most renewable resources have capacity factors
in the range of 25-35 percent. This means that three to four times the
amount of nameplate resources must be built than if the standard was based
on capacity. The abundant freshwater hydro resources of Washington are by
and large excluded from counting toward the RPS target levels.
Accessing the Resource
In Washington, as in many other parts of the country, access to transmission
remains a preeminent challenge. Transmission constraints through the Cascade
Mountains serve as a barrier between the wind resource-rich Columbia Basin
and the populous urban centers of Western Washington. It has been estimated
that the current transmission system will reach its limit within the next
nine years. Construction of additional transmission has been mired due to a
number of speculative interconnection requests and an inefficient study
process.
The Bonneville Power Administration is addressing these challenges through a
network open season that will help to differentiate speculative
interconnection requests in its queue from those with merit. Thereafter,
integration studies will be performed on clusters of renewable projects to
reduce the wait time before transmission service is available.
Supply Chain Bottlenecks
Procuring wind turbines has been another challenge as manufacturers may have
order backlogs extending for several years. The rush of utilities to
purchase renewable energy during times of tight supply has resulted in
escalating capital costs. Calls for domestic investments in turbine or
component manufacturing facilities are tempered by uncertainty over the
extension of the federal production tax credit. As the demand for these
parts continues to rise exponentially, it is believed by many that the
supply chain problem will only get worse before it gets better.
Wind Integration
A study by the Northwest Power and Conservation Council found that 6,000 MW
of wind plant capacity could be integrated into the Northwest in the next 20
years. The integration largely relies on the flexibility of the region’s
hydro system to balance wind plant power output fluctuations. However, since
the capacity of the hydro resources will not significantly increase, the
scalability of this approach is questionable. Recent studies on the
integration of wind plants in other parts of the country show promising
results, with integration costs on the order of several dollars per MWh of
wind generation. However, devising equitable allocation of the integration
costs remains a contentious problem with no panacea in sight.
The Devil in the Details
Authors of RPSs in many cases have gone to lengths to understand the
technical challenges of meeting the target levels. However, there are cases
in which technical details were overlooked or not understood, resulting with
unintended consequences. For example, yearly accounting of RPS compliance,
instead of a multi-year rolling average, fails to account for long-term
atmospheric oscillations -- \—such as El Niño -- in wind and solar plant
power output. This is analogous, and in some respects related, to the wet
and dry years that hydro generation engineers must prepare for. It is
therefore possible for a utility to meet an RPS on average over the long
term, but also be penalized for non-compliance for many of individual years.
The end result is that utilities must overbuild renewable resources in order
to consistently make RPS targets, with potentially adverse economic results.
Innovative Solutions
Despite the formidable challenges, 17 utilities serving a total demand of 68
million MWh are required to comply with Washington’s RPS. If the 15 percent
target was required today, approximately 1,160 aMW (average MW) of renewable
energy capacity would be needed. Currently, there are approximately 1,164 MW
of wind plant capacity in the state, with approximately twice that amount in
various stages of permitting and construction. Assuming that all the
generation serves native load, roughly three or four times the current
amount of installed renewable generation capacity in Washington will be
needed to meet the 2015 target. Despite this deadline looming just 12 years
away, many of the state’s utilities are on target to meet the requirement. A
survey of the approach taken by the state’s three largest utilities follows.
Puget Sound Energy. In Washington, Puget Sound Energy (PSE) is on the
forefront of procuring renewable resources. This investor-owned utility owns
and operates two wind plants in the eastern part of the state, for a total
capacity of over 360 MW. These projects currently serve over 5 percent of
PSE’s load. In addition, PSE also owns a 500 kW solar plant adjacent to its
Wild Horse wind plant. PSE has plans to expand its ownership of wind plants
through additional development.
Seattle City Light. Seattle City Light, a municipal utility and Washington’s
second largest load-serving entity has taken a different approach to meeting
the RPS target. Instead of owning wind plants, Seattle City Light has signed
a 20-year contract with the Stateline Wind Energy Center as an off-taker for
a portion of the energy produced. The city has examined meeting future
requirements through the purchase of renewable energy credits and acquiring
the output from a portfolio of geothermal, wind and landfill gas generation.
Snohomish County PUD. While wind generation will no doubt be a large
contributor to this utility meeting the RPS, Snohomish County PUD -- located
adjacent to Puget Sound -- is exploring adding up to 100 aMW of tidal power.
Local tidal power will allow Snohomish County PUD to circumvent the
transmission congestion and added losses of acquiring distant wind
resources.
Summary
The United States may be approaching a turning point in its energy policy,
albeit through a patchwork of state-level renewable portfolio standards.
What this approach lacks in unity it makes up in flexibility -- allowing
individual utilities to identify the best course of action. While
undoubtedly some utilities will miss the targeted levels, innovative
solutions like those in Washington State and elsewhere paint an encouraging
picture.
Copyright © 1996-2008 by
CyberTech, Inc. All rights reserved. To subscribe or visit go to:
http://topics.energycentral.com
|