| Nuclear Energy Slows Down 
 
 
  Location: New York
 Author: Ken Silverstein, EnergyBiz Insider, Editor-in-Chief
 Date: Monday, March 17, 2008
 No one ever said that the re-emergence of nuclear power would take the fast 
    lane. The road, in fact, is filled with potholes that include some high 
    profile deferments and ever-increasing capital costs.
 
 Despite the delays, the long-term underlying fundamentals are favorable to 
    the nuclear industry. Newer reactor designs are not only considered to be 
    even more productive but also to have safety redundancies to give 
    communities greater assurances. Emissions from nuclear energy, meantime, are 
    negligible when compared to fossil fuels -- an important factor if one 
    considers that regulatory pressures to limit greenhouse gases that cause 
    global warming will only intensify.
 
 While nuclear developers are doing the necessary groundwork to build, they 
    still have not committed themselves. Most immediately, the credit markets 
    are weak and the cost of raw materials such as cement, copper and steel is 
    expensive. Those dynamics have caused Berkshire Hathaway's MidAmerican 
    Energy to put off developing a nuclear plant in Idaho as well as South 
    Carolina Electric & Gas to postpone submitting a combined license 
    application to federal regulators.
 
 The South Carolina utility, however, may choose to move forward given that 
    access to generous benefits provided by the Energy Policy Act of 2005 may be 
    limited. That law provides for loan guarantees of up 80 percent of a 
    project's cost, while it also gives a tax credit of 1.8 cents per 
    kilowatt-hour for 6,000 megawatts of capacity from new nuclear power plants 
    for the first eight years of operation.
 
 Certainly, the presidential candidates have all reacted favorably to nuclear 
    energy. But proponents are concerned that shifting sentiments in future 
    congresses would lead to the eradication of those financial incentives that 
    are needed to make sure the first few modern reactors actually get built. 
    After that, they say investors will be satisfied and that the industry will 
    create economies of scale to bring down prices.
 
 "Nuclear projects are lengthy -- possibly requiring 7-10 years to design and 
    construct -- and there is some concern in the industry that a new 
    administration and more strongly Democratic congress may not be as favorable 
    to nuclear development," says Christine Tezak, regulatory analyst with the 
    Stanford Group. "We agree, and believe that the controversial loan guarantee 
    programs are particularly vulnerable to a change in political winds after 
    the 2008 elections."
 
 By 2010, utilities are expected to have submitted applications for 33 new 
    reactors at 22 sites to the Nuclear Regulatory Commission for approval. When 
    the first applications were submitted in 2007, the developers had estimated 
    the cost to construct to be in the $4 billion to $6 billion range. Now, 
    though, the price is in the $7 billion to $8 billion range -- the single 
    greatest factor causing MidAmerican to get cold feet. Despite its 
    reluctance, major utilities such as Dominion, Progress Energy and the 
    Tennessee Valley Authority are keeping their eye on the ball.
 
 TVA, which began its forays into nuclear energy in the 60s, says that the 
    fuel source is second only to hydro in terms of cost efficiency. The demand 
    for energy in its southeast region necessitates the expansion of its nuclear 
    portfolio that already comprises 30 percent of its total generation, the 
    company says. Last November, it applied for an operating license to build 
    two modern reactors in Alabama, which is in addition to spending $2.5 
    billion to complete Unit 2 at its Watts Bar facility in Tennessee.
 
 Progress Energy, meantime, says it will file an application to build two 
    nuclear reactors at an existing nuclear plant site in North Carolina. 
    Interestingly, the location was chosen in the 1970s and was designed to 
    accommodate four reactors. But as history unfolded, only one of the units 
    was actually built. The utility has notified federal regulators that if it 
    moves forward with the two new reactors, they would be online around 2018. 
    It says that a final decision is still more than a year away.
 
 "The overall demand for electricity is not going to decrease in our 
    fast-growing part of the country and, as a utility, we have an obligation to 
    meet that growing demand," says Progress Energy's CEO Bill Johnson. "Using 
    nuclear power, we can help secure our energy future with a fuel that does 
    not contribute to global warming."
 
 Critics of nuclear power, however, say that those nuclear-bound utilities 
    have a fallacious energy strategy. If history is any indication, it would be 
    a monumental task for them to stay on time and on budget. According to Arjun 
    Makhikani, who advised TVA in the late 1970s and who now heads a nuclear 
    watchdog group called the Institute for Energy and Environmental Research, 
    says that utilities canceled 121 reactors in the post-1974 period and 
    subsequently wasted $50 billion in 1995 dollars.
 
 The TVA, in fact, was the last one to activate a new nuclear reactor -- 
    Watts Bar Unit 1 in Spring City, Tenn. -- in 1996. That reactor ended up 
    costing $6 billion to build after construction and financing in a process 
    that took 20 years.
 
 "Enjoying virtually every conceivable advantage at its birth -- from high 
    public popularity to lavish government funding to virtually unanimous 
    political support -- the commercial nuclear power industry in the United 
    States is a moribund one, with virtually every one of its early advantages 
    reversed," says Makhikan.
 
 It's a different time now. Nuclear plants in the United States have solid 
    safety and performance records. Last year, they exceeded previous production 
    levels and generated 807 billion kilowatt-hours of power. Those 
    achievements, on top of the current regulatory climate, are adding to 
    nuclear power's new appeal. While the financial risks associated with 
    development remain an impediment, they can be mitigated by continuing along 
    the path that Congress laid out in the 2005 Energy Policy Act.
 
 
Copyright © 1996-2006 by 
CyberTech, 
Inc. 
All rights reserved.  |