Nuclear Energy Slows Down
Location: New York
Author: Ken Silverstein, EnergyBiz Insider, Editor-in-Chief
Date: Monday, March 17, 2008
No one ever said that the re-emergence of nuclear power would take the fast
lane. The road, in fact, is filled with potholes that include some high
profile deferments and ever-increasing capital costs.
Despite the delays, the long-term underlying fundamentals are favorable to
the nuclear industry. Newer reactor designs are not only considered to be
even more productive but also to have safety redundancies to give
communities greater assurances. Emissions from nuclear energy, meantime, are
negligible when compared to fossil fuels -- an important factor if one
considers that regulatory pressures to limit greenhouse gases that cause
global warming will only intensify.
While nuclear developers are doing the necessary groundwork to build, they
still have not committed themselves. Most immediately, the credit markets
are weak and the cost of raw materials such as cement, copper and steel is
expensive. Those dynamics have caused Berkshire Hathaway's MidAmerican
Energy to put off developing a nuclear plant in Idaho as well as South
Carolina Electric & Gas to postpone submitting a combined license
application to federal regulators.
The South Carolina utility, however, may choose to move forward given that
access to generous benefits provided by the Energy Policy Act of 2005 may be
limited. That law provides for loan guarantees of up 80 percent of a
project's cost, while it also gives a tax credit of 1.8 cents per
kilowatt-hour for 6,000 megawatts of capacity from new nuclear power plants
for the first eight years of operation.
Certainly, the presidential candidates have all reacted favorably to nuclear
energy. But proponents are concerned that shifting sentiments in future
congresses would lead to the eradication of those financial incentives that
are needed to make sure the first few modern reactors actually get built.
After that, they say investors will be satisfied and that the industry will
create economies of scale to bring down prices.
"Nuclear projects are lengthy -- possibly requiring 7-10 years to design and
construct -- and there is some concern in the industry that a new
administration and more strongly Democratic congress may not be as favorable
to nuclear development," says Christine Tezak, regulatory analyst with the
Stanford Group. "We agree, and believe that the controversial loan guarantee
programs are particularly vulnerable to a change in political winds after
the 2008 elections."
By 2010, utilities are expected to have submitted applications for 33 new
reactors at 22 sites to the Nuclear Regulatory Commission for approval. When
the first applications were submitted in 2007, the developers had estimated
the cost to construct to be in the $4 billion to $6 billion range. Now,
though, the price is in the $7 billion to $8 billion range -- the single
greatest factor causing MidAmerican to get cold feet. Despite its
reluctance, major utilities such as Dominion, Progress Energy and the
Tennessee Valley Authority are keeping their eye on the ball.
TVA, which began its forays into nuclear energy in the 60s, says that the
fuel source is second only to hydro in terms of cost efficiency. The demand
for energy in its southeast region necessitates the expansion of its nuclear
portfolio that already comprises 30 percent of its total generation, the
company says. Last November, it applied for an operating license to build
two modern reactors in Alabama, which is in addition to spending $2.5
billion to complete Unit 2 at its Watts Bar facility in Tennessee.
Progress Energy, meantime, says it will file an application to build two
nuclear reactors at an existing nuclear plant site in North Carolina.
Interestingly, the location was chosen in the 1970s and was designed to
accommodate four reactors. But as history unfolded, only one of the units
was actually built. The utility has notified federal regulators that if it
moves forward with the two new reactors, they would be online around 2018.
It says that a final decision is still more than a year away.
"The overall demand for electricity is not going to decrease in our
fast-growing part of the country and, as a utility, we have an obligation to
meet that growing demand," says Progress Energy's CEO Bill Johnson. "Using
nuclear power, we can help secure our energy future with a fuel that does
not contribute to global warming."
Critics of nuclear power, however, say that those nuclear-bound utilities
have a fallacious energy strategy. If history is any indication, it would be
a monumental task for them to stay on time and on budget. According to Arjun
Makhikani, who advised TVA in the late 1970s and who now heads a nuclear
watchdog group called the Institute for Energy and Environmental Research,
says that utilities canceled 121 reactors in the post-1974 period and
subsequently wasted $50 billion in 1995 dollars.
The TVA, in fact, was the last one to activate a new nuclear reactor --
Watts Bar Unit 1 in Spring City, Tenn. -- in 1996. That reactor ended up
costing $6 billion to build after construction and financing in a process
that took 20 years.
"Enjoying virtually every conceivable advantage at its birth -- from high
public popularity to lavish government funding to virtually unanimous
political support -- the commercial nuclear power industry in the United
States is a moribund one, with virtually every one of its early advantages
reversed," says Makhikan.
It's a different time now. Nuclear plants in the United States have solid
safety and performance records. Last year, they exceeded previous production
levels and generated 807 billion kilowatt-hours of power. Those
achievements, on top of the current regulatory climate, are adding to
nuclear power's new appeal. While the financial risks associated with
development remain an impediment, they can be mitigated by continuing along
the path that Congress laid out in the 2005 Energy Policy Act.
Copyright © 1996-2006 by
CyberTech,
Inc.
All rights reserved.
|