Austin Energy to Revise Green Power Charge
July 27, 2009
Austin Energy will be submitting for City Council approval on the August 20
council agenda, a revised tariff for GreenChoice® Batch 6 of 5.7 cents per
kilowatt-hour (kWh) for a five-year term.
The current Batch 6 price is 8 cents/kWh for a 5-year term or 9.5 cents/kWh
for a 10-year term. These original Batch 6 prices, which include estimates
on transmission congestion costs, were set in December 2008 based on what
had been a year of significantly greater transmission congestion activity.
Estimated congestion cost at the time assumed that the Hackberry wind plant
(located near Abilene) which provides Batch 6 would be assigned to ERCOT’s
“West Zone” for congestion purposes and would therefore have higher
congestion costs. However, Hackberry was ultimately assigned to the North
Zone, thereby reducing its exposure to transmission congestion costs. In
addition, ERCOT implemented protocol and grid operational changes which have
resulted in reduced transmission congestion statewide.
The revised price reflects the cost of the contracted wind energy, ERCOT
support fees and charges associated with the energy and Austin Energy
GreenChoice® administrative costs. Transmission congestion costs associated
with Batch 6 wind energy would be recovered through the standard fuel
charge.
Under the proposed new rate, the electric bill of a GreenChoice® Batch 6
subscriber using 1,000 kWh a month would be about 20 percent higher on
average that that of a non-subscriber. Customers who have already subscribed
to Batch 6 would be allowed to change to the revised rate. Some
considerations regarding recovery of Batch 6 transmission congestion costs
through the fuel charge:
· Estimating prospective transmission congestion over a number of years for
inclusion in a fixed 5-year green power price is difficult, especially given
that ERCOT is scheduled to implement a new nodal wholesale market design at
the end of 2010.
· Even with prospective Batch 6 transmission congestion costs recovery
through the fuel charge, subscribers to Batch 6 will be paying the vast
majority of Batch 6 costs.
· If the Batch 6 energy supply did not exist, traditional generation would
take its place, the full cost of which would be paid for by all customers.
· Austin Energy is likely the only utility-sponsored green power program in
the nation (among 850) that has yet to spread the cost of its renewable
energy program across its customer base. All previous batches of GreenChoice
have been purchased by voluntary subscribers.
Austin Energy expects Batch 6 to sell well under the revised pricing.
However, should Batch 6 not sell—recovery of its costs will do little to
raise overall electric rates in Austin. Green power is purchased power and
purchased power costs are recovered through the fuel charge to customers.
Batch 6 began flowing in January 2009 but did not increase the Austin Energy
fuel charge this year. Staff estimates that even if it were necessary to
recover most of Batch 6 in the fuel charge long-term, its impact on the fuel
charge would be about 1-2 percent. The fuel charge on average is about
one-third of the average residential electric bill in Austin.
Austin Energy GreenChoice is number one in the nation for sales among 850
utility-sponsored green power programs-- seven years in a row. Austin Energy
customers purchase about 750-million kWh of wind-generated power annually
from the program. The utility replaces the fuel charge on the bill of a
GreenChoice subscriber with the green power charge for the respective Batch.
The green power (fuel) charge for previous batches of wind energy was fixed
for 10 years.
|