| SMUD pullout dims hopes for big power project
Jul 3 - McClatchy-Tribune Regional News - Ed Fletcher The Sacramento Bee,
Calif.
One of the largest public works projects in the West -- 600 miles of
high-voltage power lines through Northern California -- is on life support
after its biggest player abruptly pulled the plug.
A magnet for opposition from both owners of properties the transmission
lines would cross and environmental activists, the project was promoted as
vital to the region's clean-energy future.
A consortium of municipal power providers said the lines were needed to
bring renewable solar, wind and geothermal energy from the northeast corner
of California to power-thirsty urban areas.
On Wednesday, the Sacramento Municipal Utility District told The Bee it was
pulling out of the $1.5 billion project due to regulatory and financial
uncertainties -- leaving a gaping hole in the project budget. SMUD had been
expected to shoulder 35 percent of the project's costs.
The Transmission Agency of Northern California -- the project's sponsor --
has 15 members. But only five had agreed to fund the power line project's
environmental impact studies and, if it ultimately was approved, finance the
project.
The remaining participants are the city of Santa Clara, Redding Electric
Utility, and the Modesto and Turlock irrigation districts.
The Western Area Power Authority is a federal partner.
On Thursday, those partners grappled with questions about the project's
viability.
"We need another entity or entities to step forward in order to move this
thing forward," said Paul Hauser, director of Redding Electric.
Keeping the project alive means one or more of the existing players would
have to absorb SMUD's $525 million share, or a new partner would have to be
found to salvage the project -- or even pieces of it, officials said.
Most of the staff and board members of the participating utilities contacted
by The Bee said they doubted the project would survive, despite the need for
additional transmission capacity.
Tom Van Groningen, the Modesto Irrigation District board chairman, said he
would "give serious consideration" to pulling out was well.
The likelihood of carrying on without SMUD is "very, very slight," he said.
Modesto had expected to pay $300 million of the total project cost, he said.
Santa Clara remains interested in the added transmission capacity, but a
city spokesman said going it alone doesn't pencil out.
With SMUD out of the picture, "financing will be up in the air," said Dan
Beerman, a city spokesman.
The Turlock Irrigation District was a participant, but its interest was
limited to east/west lines between Tracy and Turlock, officials said. The
district was not expected to pay for or use the more controversial
north/south portion of the project.
The federal Western Area Power Authority, which delivers power to
governmental and nonprofit entities from federal dams, also has some limited
involvement.
If the project is to live on, it will be the feds that save it, some
opponents of the project speculated.
But that's not a logical leap, said Randy Wilkerson, an authority spokesman.
"Western isn't in the business of bankrolling transmission projects,"
Wilkerson said. "We do participate in transmission projects that have a need
and can -- in the foreseeable future -- pay for themselves."
Wilkerson said that like other players, Western is required to break even.
Randy Fiorini, vice president of the Turlock Irrigation District, said he
wasn't surprised SMUD had pulled out.
Some of the project's opposition -- which has been fierce -- probably can be
attributed to the lack of initial outreach, Fiorini said. Three tentative
routes for the transmission lines were plotted on a map before stakeholders
could weigh in.
"There has been so much controversy with the way the scoping was handled,"
he said.
SMUD acknowledged difficulty with the process but said the public uproar
wasn't key to to its decision to pull out.
Rather, SMUD officials said a changing regulatory environment -- and how
that might affect the financial picture -- was the main factor.
There is talk at the state and federal level of changing the way
transmission projects are placed and funded. Given the uncertainty, it made
sense to hold off, said SMUD spokeswoman Elisabeth Brinton.
Rule changes could force SMUD to share in the cost of energy grid projects
in which it is not directly involved. And it could force SMUD to share the
assets it paid for, officials said.
"The game rules are changing," Brinton said. "We are going to the game, but
we don't know if we are playing football, baseball or softball."
------
Call The Bee's Ed Fletcher, (916) 321-1269.
(c) 2009,
McClatchy-Tribune Information Services |