Electric utilities plan to spend $1B on new
power plants
Nov 11 - Alaska Journal of Commerce
Electric utilities have nearly $1 billion worth of new power plant
projects planned for Southcentral Alaska.
Matanuska Electric Association is in the preliminary stages of talks
with contractors or private developers on a new 180-megawatt gas-fired
power plant that could be built on a 70-acre land tract in Eklutna, just
north of Anchorage, said MEA officials.
Cost for the plant could be in the $400 million range, according to Joe
Griffith, MEA's general manager. The Palmer-based utility purchased the
land from Eklutna Inc. as a potential power plant site.
Griffith and other Southcentral Alaska electric utilities presented
their latest plans at an Anchorage Chamber of Commerce luncheon Nov. 2.
MEA's new plant could either be built by a contractor and owned by the
utility or built privately by an independent power producer that would
sign a power-supply agreement with the utility, said Lorali Carter, MEA
communications director.
The utility is looking at both options, she said.
MEA is asking for bids from contractors by Jan. 29, with the goal of
awarding a contract to build the plant next May and for construction to
begin April 2012.
"We are on a very aggressive schedule because of the end of our
all-requirements contract with Chugach Electric," in December 2014,
Carter said. MEA currently purchases the bulk of its power from Chugach
Electric Corp.
Besides getting the power plant construction underway and the financing
secured, the utility must also secure a supply of natural gas for the
plant, Griffith said.
That is becoming more of a challenge because of the depletion of gas
reserves in producing fields in the Southcentral region.
The utility has considered a range of renewable and alternative power
generation strategies, but none of them can provide sufficient
electricity by 2015, when MEA needs it, Griffith said. Of the renewable
energy options, the Fire Island wind project being pursued by Cook Inlet
Region Inc. is the most promising, he said.
Large hydro projects in the region, as well as geothermal projects, are
also promising but more in the long term. For the time being, the
utilities will have to stick with natural gas.
A second major power plant project in the planning stages is the
Southcentral Power Project, a 180- to 270-megawatt gas-fired plant in
south Anchorage that would be built by Chugach Electric and Municipal
Light and Power, Anchorage's city-owned utility. Chugach would own 70
percent of the project.
The plant is estimated to cost between $350 million and $400 million,
Chugach spokesman Phil Steyer said. It would be located near
International Airport Road in south Anchorage near Chugach Electric's
existing station there.
"We are currently in the design and permitting stages for the plant. We
have a request for qualifications on the street now to develop a list of
qualified contractors. A final request for proposals to build the plant
would be coming within a few months, Steyer said.
Chugach and MEA would finance their respective portions of the project
separately. The goal is to have the plant in operation by 2015, Steyer
said.
Efficient combined-cycle power generation systems would be used in the
new plant, which capture waste heat to generate more electricity, Steyer
said.
These new technologies generate more power with less gas. Typically a
modern combined-cycle plant can generate a kilowatt of power using 7,000
British thermal units, or Btus, of gas, compared to older turbines,
which needed 10,000 Btus to generate a kilowatt of power.
Making electricity with new generation systems that use 30 percent less
gas will result in less demand on remaining gas reserves in Southcentral
Alaska gas fields, Steyer and Griffith said.
In addition to its $111 million participation in the Southcentral Power
Project with Chugach, Municipal Light and Power has $137 million in
upgrades of turbines planned at two of its plants in Anchorage, ML&P
general manager Jim Posey said.
Equipment for the upgrades will likely be ordered next year. One of the
new turbines is expected to be on line by 2013 and the other by 2014,
Posey said. The expected savings in use of gas through using modern,
more efficient turbines is 25 percent, he said.
Tim Bradner can be reached at tim.bradner@alaskajournal.com.
-----
To see more of the Alaska Journal of Commerce, or to subscribe to the
newspaper, go to http://www.alaskajournal.com.
Copyright (c) 2009, Alaska Journal of Commerce, Anchorage
Distributed by McClatchy-Tribune Information Services.
(c) 2009,
McClatchy-Tribune Information Services
|