Newly installed wind turbines idled by Minnesota's
winter
Jan 22 - Saint Paul Pioneer Press (St. Paul, Minn.)
Last year, about a dozen Minnesota communities dreamed of clean, green
energy: spinning windmills powering hundreds of homes. Now, months after
the deadline, the windmills stand largely immobile, and communities are
still waiting for the power to flow.
Eleven cities, including North St. Paul and Anoka, are participating in
the wind turbine project, each getting a 115-foot windmill via the
Minnesota Municipal Power Association, or MMPA.
The turbines were to be fully operational by Nov. 7. To date, the number
is zero.
One reason offered this week at a North St. Paul City Council meeting:
hydraulic fluid and lubricating oil in the turbines' gear boxes. In cold
weather, the fluid turns gel-like and doesn't flow, said Derick Dahlen,
president of Avant Energy, which manages the MMPA. That can be
particularly problematic if the turbines are already at a standstill.
To fix the problem, a contractor installed heating elements
this week in the turbines. In addition, heat tracing is likely to be
added to the hydraulic lines and lubrication oil system.
But that might not be enough, said Dahlen, who blames his engineering
and construction contractor for the delay.
"I think they should absolutely have known about the cold weather issue,
but I think the problems go deeper with that. It's a contributing
factor, it's not a causal factor," Dahlen said. "The root problem is
that the contractor is not solving any problems. ... The weather warms
up, and they still don't
run."
"The units are not set up correctly," he added. "(The contractor denies)
that there's a problem."
Lisa Lutz, an attorney for the contractor, Henkles & McCoy Inc., said
the company only learned of the problem Thursday. Lutz said the company,
which is based in Blue Bell, Pa., and has an office in Lakeville, was
investigating.
In the meantime, residents driving past the turbines wonder why they
aren't running.
"Who's the idiot that didn't realize that a California whirligig is
something that doesn't work in Minnesota?" asked John Schmahl, a 35-year
North St. Paul resident and frequent gadfly at city meetings. "I have
never seen it turn. Not once."
Schmahl refers to the fact that the windmills were bought from
Escondido, Calif.-based, enXco, a subsidiary of the French company EDF
Energies Nouvelles, and have never operated under such cold conditions.
North St. Paul City Manager Wally Wysopal said yes, the city's windmill
has turned and even put some power on the grid.
But Dahlen admits: "This is the farthest north they (the windmills) have
been. So we expect to have some amount of issue with cold weather
operation ... and we expect to solve it, too. The problems are all
solvable problems."
Dahlen said the turbines had been refurbished, because the MMPA could
not afford new units, but have a history of running well.
Wysopal said he's disappointed by the delay.
"We're feeling that we just expected it to be going as soon as it went
up, but apparently that's not feasible sometimes," he said. "We see it
as a contractor issue; an issue between the contractor and (MMPA). ...
For now, we're going to accept that."
The windmills each cost about $417,000 and have been erected in Anoka,
Arlington, Brownton, Buffalo, Chaska, East Grand Forks, Le Sueur, North
St. Paul, Olivia, Shakopee and Winthrop, as well as at the MMPA's energy
park in Faribault. To fund the project, MMPA sold $5 million in
zero-interest bonds.
Under the program, the cities buy energy from MMPA, their primary energy
provider.
The turbines were installed to meet a state law requiring energy
producers to provide 25 percent of output from renewable sources by
2025. The delay in getting the windmills online has not affected the
supply, because other energy sources were already in place.
The 160-kilowatt turbines are much smaller than some modern turbines
elsewhere in the state. For example, the turbines at Xcel Energy's Grand
Meadow Wind Farm, near Rochester, stand nearly 40 stories tall, and
generate 1.5 megawatts. They work in temperatures down to 20 below, Xcel
officials said.
Leslie Brooks Suzukamo contributed to this report. Tad Vezner can be
reached at 651-228-5461.
-----
To see more of the Pioneer Press, or to subscribe to the newspaper, go
to http://www.twincities.com.
Copyright (c) 2010, Pioneer Press, St. Paul, Minn.
Distributed by McClatchy-Tribune Information Services.
(c) 2009,
McClatchy-Tribune Information Services
|